Commercial Tenant Improvement / Tenant Finish Permit in Ivins, Utah

Required for tenant improvement and tenant finish work in existing commercial buildings in Ivins. No dedicated tenant-improvement checklist, application category, or fee line was found published on ivinsutah.gov as of 2026-07-19 — the same generic 'Building Permit Fees' section of the Consolidated Fee Schedule (Ordinance No. 2024-12) that governs all other building permit types in this file is the only identified fee mechanism.

Reviewed 2026-07-19 · Source

When you need this permit

  • Commercial remodel or tenant improvement work in an existing commercial structure
  • Application submitted through the Ivins City Inspect online portal (utah.cityinspect.com)
  • Project valuation stated on the application, used to calculate the fee under the city's 1997 Valuation Code

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (valuation-based), inferred mechanismIvins City Consolidated Fee Schedule (Ordinance No. 2024-12) publishes only one generic 'Building Permit' valuation line with no tenant-improvement-specific rate. This entry assumes the same mechanism applies to TI work based on the schedule's general framing, but that has not been independently confirmed against a TI-specific line item.
Based on Valuation, using the City's 1997 Valuation Code
Plan Check FeeIvins City Consolidated Fee Schedule (Ordinance No. 2024-12): 'Plan Check: 10% of Building Permit' — no tenant-improvement-specific rate is separately published.
10% of the Building Permit fee
State Permit TaxIvins City Consolidated Fee Schedule (Ordinance No. 2024-12): 'State Permit Tax: 1% of Building Permit.'
1% of the Building Permit fee

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Tenant Improvement / Tenant Finish Permit permit actually take in Ivins?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Framing / Structural (if applicable)

    Wall construction and any structural modifications verified before close-in, where applicable to the scope of work.

  2. 2

    MEP Rough-In

    Electrical, mechanical, and plumbing rough-in verified against submitted plans.

  3. 3

    Final

    All work complete before occupancy.

See the full Ivins inspection guide — scheduling & re-inspection fees →

Tips

  • Ivins does not publish a dedicated tenant-improvement fee schedule or checklist — confirm the applicable fee mechanism and document requirements directly with the Building/Zoning Department at (435) 634-9753 before submitting.

Frequently asked questions

Ivins requires a commercial tenant improvement / tenant finish permit for: Commercial remodel or tenant improvement work in an existing commercial structure; Application submitted through the Ivins City Inspect online portal (utah.cityinspect.com); Project valuation stated on the application, used to calculate the fee under the city's 1997 Valuation Code. If your project isn't listed, confirm with Ivins City Building/Zoning Department at (435) 634-9753 before starting work.

In Ivins, the published Building Permit Fee (valuation-based), inferred mechanism is: Based on Valuation, using the City's 1997 Valuation Code. Additional published fees: Plan Check Fee — 10% of the Building Permit fee; State Permit Tax — 1% of the Building Permit fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Ivins does not publish a plan-review timeline for this permit. Contact Ivins City Building/Zoning Department at (435) 634-9753 for current turnaround.

You'll need: Building Permit Application (CityInspect). See the required-documents checklist on this page for details on each.

Ivins requires 3 inspection(s) for a commercial tenant improvement / tenant finish permit, in order: Framing / Structural (if applicable), MEP Rough-In, Final. Schedule each through Ivins City Building/Zoning Department ((435) 634-9753).

Apply through Ivins City Building/Zoning Department at 85 N Main St, Ivins, UT 84738. Phone: (435) 634-9753. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://ivinsutah.gov/building-department/.

Ivins, Utah has adopted: 2024 International Building Code (IBC) — adopted via Ivins City Ordinance No. 2025-08 amending Title 14 'Buildings and Construction' (which adopts the state construction code by reference, per Ivins City Code Title 14, Ch.1, and so auto-tracks statutory changes); Utah Code § 15A-2-103(1)(a); effective 2026-07-01, superseded the 2021 edition; 2021 International Residential Code (IRC) — Utah Code § 15A-2-103(1)(b); unaffected by the 7/1/2026 statute revision, continues in force; 2024 International Plumbing Code (IPC) — Utah Code § 15A-2-103(1)(d); effective 2026-07-01, superseded the 2021 edition; 2024 International Mechanical Code (IMC) — Utah Code § 15A-2-103(1)(e); effective 2026-07-01, superseded the 2021 edition; 2024 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); effective 2026-07-01, superseded the 2021 edition; 2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); unaffected by the 7/1/2026 statute revision, continues in force; 2024 International Energy Conservation Code (IECC) — Utah Code § 15A-2-103(1)(h); effective 2026-07-01, superseded the 2021 edition; 2024 International Existing Building Code (IEBC) — Utah Code § 15A-2-103(1)(i); effective 2026-07-01, superseded the 2021 edition; 2024 International Swimming Pool and Spa Code (ISPSC), residential provisions — Utah Code § 15A-2-103(1)(n); effective 2026-07-01, superseded the 2021 edition; Ivins charges a distinct Pool Permit Fee ($300, per its Consolidated Fee Schedule); NOTE: Effective July 1, 2026 (now in force) — 2024 editions of IBC, IPC, IMC, IFGC, IECC, IEBC, and ISPSC replaced the 2021 editions per Utah Code § 15A-2-103 (version effective 7/1/2026, superseded 1/1/2027; text independently re-verified live at le.utah.gov 2026-07-16). The 2021 IRC and 2023 NEC were unaffected and remain in force. Because Ivins Ordinance No. 2025-08 adopts the state code by reference rather than restating specific editions, Ivins is not expected to have a separate city-document lag of the kind seen in some sibling cities — this was not independently re-verified against the amlegal-hosted Ivins Code text this session (that site's full ordinance text is not renderable via automated fetch, per the localAmendments entry above).. Local amendments apply — see the Ivins overview page for the full list.

No dedicated tenant-improvement checklist or fee schedule is published on ivinsutah.gov as of 2026-07-19. TI work in Ivins is expected to go through the same CityInspect application and Consolidated Fee Schedule (Ordinance No. 2024-12) 'Building Permit Fees' mechanism used for other commercial and residential permits — confirm directly with the Building/Zoning Department.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Ivins building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Ivins.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.