Commercial Tenant Improvement / Tenant Finish Permit in South Ogden, Utah

Required for tenant improvement, remodel, or interior finish work in existing commercial space in South Ogden. South Ogden's City Fee Schedule does not publish a separate TI-specific fee line — TI/remodel work is billed under the same valuation-based Building Permit Fee table and the same 65% Commercial Plan Check and Site Plan Review fee as new commercial construction.

Verified 2026-07-19 · Source

When you need this permit

  • Commercial tenant improvement, remodel, or interior finish scope in an existing commercial building
  • Commercial structural sheets and structural calculations must be stamped by an engineer where structural work is involved, per the official FAQ
  • Work must comply with the state-mandated 2024 IBC/IPC/IMC/IFGC and 2023 NEC (see codesAdopted)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (valuation-based)South Ogden City Fee Schedule (last amended 16 Jun 2026), § Building Permit Fees. No separate TI-specific valuation table is published.
Same valuation-bracket table published for residential and new commercial permits
Commercial Plan Check and Site Plan ReviewSouth Ogden City Fee Schedule, § Building Inspection Fees. The same rate applies to TI/remodel work as to new commercial construction — no distinct TI line item is published.
65% of the building permit fee cost
Re-inspection Fee (assessed under Section 108.8)South Ogden City Fee Schedule, § Building Inspection Fees.
$47.00 per hour

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Tenant Improvement / Tenant Finish Permit permit actually take in South Ogden?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    4-Way Rough Inspection

    Framing, electrical, heating/AC, and plumbing for the TI/remodel scope, complete and ready for wall coverings.

  2. 2

    Final Inspection

    Completed TI/remodel work verified before occupancy sign-off.

See the full South Ogden inspection guide — scheduling & re-inspection fees →

Tips

  • South Ogden does not discount tenant improvements relative to new commercial construction — both are billed at the same 65% Commercial Plan Check and Site Plan Review rate against the same valuation-based Building Permit Fee table.

Frequently asked questions

South Ogden requires a commercial tenant improvement / tenant finish permit for: Commercial tenant improvement, remodel, or interior finish scope in an existing commercial building; Commercial structural sheets and structural calculations must be stamped by an engineer where structural work is involved, per the official FAQ; Work must comply with the state-mandated 2024 IBC/IPC/IMC/IFGC and 2023 NEC (see codesAdopted). If your project isn't listed, confirm with South Ogden City Building & Inspections Department at (801) 622-2913 or (801) 622-2713 (Building Official Tyson Egbert); general department (801) 622-2700 before starting work.

In South Ogden, the published Building Permit Fee (valuation-based) is: Same valuation-bracket table published for residential and new commercial permits. Additional published fees: Commercial Plan Check and Site Plan Review — 65% of the building permit fee cost; Re-inspection Fee (assessed under Section 108.8) — $47.00 per hour. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

South Ogden does not publish a plan-review timeline for this permit. Contact South Ogden City Building & Inspections Department at (801) 622-2913 or (801) 622-2713 (Building Official Tyson Egbert); general department (801) 622-2700 for current turnaround.

You'll need: Building Permit Application; Tenant Improvement / Remodel Plans. See the required-documents checklist on this page for details on each.

South Ogden requires 2 inspection(s) for a commercial tenant improvement / tenant finish permit, in order: 4-Way Rough Inspection, Final Inspection. Schedule each through South Ogden City Building & Inspections Department ((801) 622-2913 or (801) 622-2713 (Building Official Tyson Egbert); general department (801) 622-2700).

Apply through South Ogden City Building & Inspections Department at 3950 S Adams Ave., South Ogden, UT 84403. Phone: (801) 622-2913 or (801) 622-2713 (Building Official Tyson Egbert); general department (801) 622-2700, email: tegbert@southogdencity.gov. Office hours: Monday–Friday, 8:00 AM–4:30 PM, per the official Building & Inspections Department page. Inspection scheduling calls must be placed between 9:00 AM–3:00 PM with at least 24 hours notice, per the official FAQ page.. Official information: https://www.southogdencity.com/departments/building_&_inspections/index.php.

South Ogden, Utah has adopted: GOVERNING LAW: Utah Code § 15A-2-103 (le.utah.gov/xcode/Title15A/Chapter2/15A-2-S103.html), version effective 7/1/2026 (amended by Ch. 47, 2026 General Session), sets the statewide-mandatory construction code suite (Utah Code § 15A-1-204 — binds every municipality; local amendments permitted, a different edition is not). South Ogden's official Building & Inspections FAQ page ('What code editions are being enforced?') still displays the pre-7/1/2026 edition list; re-checked live 2026-07-16, page text is byte-identical to the earlier fetch: 'The city is currently enforcing the following codes: 2021 Edition of the International Building Code, 2021 Edition of the International Residential Code, 2021 Edition of the International Plumbing Code, 2021 Edition of the International Mechanical Code, 2021 Edition of the National Electrical Code, 2021 Edition of the International Fuel Gas Code, 2021 Edition of the International Fire Code, 2009 Edition of the International Building Code (ICC/ANSI A117.1) for Accessibility Standards.' State law governs regardless of the page's lag; each line below states current law first, then the page's as-published (stale or omitted) text.; 2024 Edition of the International Building Code (IBC) — per Utah Code § 15A-2-103(1)(a), effective 7/1/2026. South Ogden's FAQ still lists '2021 Edition of the International Building Code' (live re-check 2026-07-16).; 2021 Edition of the International Residential Code (IRC), plus Appendix AQ of the 2021 IRC — per Utah Code § 15A-2-103(1)(b)/(c); this edition did NOT change in the 7/1/2026 flip. Matches South Ogden's FAQ, which lists '2021 Edition of the International Residential Code' (live re-check 2026-07-16).; 2024 Edition of the International Plumbing Code (IPC) — per Utah Code § 15A-2-103(1)(d), effective 7/1/2026. South Ogden's FAQ still lists '2021 Edition of the International Plumbing Code' (live re-check 2026-07-16).; 2024 Edition of the International Mechanical Code (IMC) — per Utah Code § 15A-2-103(1)(e), effective 7/1/2026. South Ogden's FAQ still lists '2021 Edition of the International Mechanical Code' (live re-check 2026-07-16).; 2023 Edition of the National Electrical Code (NEC) — per Utah Code § 15A-2-103(1)(g); this edition did NOT change in the 7/1/2026 flip and has been state law since before this project's original 2026-07-07 review. South Ogden's FAQ still lists '2021 Edition of the National Electrical Code' (live re-check 2026-07-16) — this is a PRE-EXISTING discrepancy that predates and is unrelated to the 2026-07-01 code-cycle flip (South Ogden's page was already citing a stale NEC edition under the prior law too); reported here as-published rather than corrected, per grounded-data policy of not inventing a fact the city's own source does not state.; 2024 Edition of the International Fuel Gas Code (IFGC) — per Utah Code § 15A-2-103(1)(f), effective 7/1/2026. South Ogden's FAQ still lists '2021 Edition of the International Fuel Gas Code' (live re-check 2026-07-16).; 2024 International Energy Conservation Code (IECC), one statewide edition (no residential/commercial split) — per Utah Code § 15A-2-103(1)(h), effective 7/1/2026. Not mentioned on South Ogden's FAQ, department page, Forms page, or City Fee Schedule as of live re-check 2026-07-16; added here as a statute-sourced omission (applies statewide regardless of city publication), not fabricated.; 2024 International Existing Building Code (IEBC) — per Utah Code § 15A-2-103(1)(i), effective 7/1/2026. Not mentioned on any South Ogden source reviewed as of live re-check 2026-07-16; added as a statute-sourced omission.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — per Utah Code § 15A-2-103(1)(n), effective 7/1/2026. Not mentioned on any South Ogden source reviewed as of live re-check 2026-07-16; added as a statute-sourced omission.; Modular Building Institute (MBI) Standards 1200 and 1205 — per Utah Code § 15A-2-103(1)(o), statewide-mandated for modular units. Not mentioned on any South Ogden source reviewed as of live re-check 2026-07-16; added as a statute-sourced omission.; 2021 Edition of the International Fire Code (IFC) — per the official FAQ page (live re-check 2026-07-16, unchanged); South Ogden City Code Title 3, Chapter 1 separately adopts by reference 'the International Fire Code version adopted by the State of Utah Fire Marshal's Office for the respective year' (Ordinance 24-05, effective 2 Jul 2024), so the specific IFC edition in force tracks the State Fire Marshal's current adoption. NOTE: Utah Code § 15A-2-103 does NOT adopt the IFC — it is separately governed under Title 15A Chapter 5, outside the scope of this section; South Ogden's IFC citation and Fire Code ordinance are therefore unaffected by, and not mis-scoped to, § 15A-2-103.; 2009 Edition of the International Building Code (ICC/ANSI A117.1) for Accessibility Standards — per the official FAQ page (live re-check 2026-07-16, unchanged). This accessibility standard is not among the codes enumerated in Utah Code § 15A-2-103(1); reproduced here as South Ogden's own published statement, not itself corrected against that section.; Utah's statewide construction-code framework under Utah Code Title 15A (State Construction and Fire Codes Act) governs code adoption and amendment authority for all Utah municipalities, including South Ogden; § 15A-2-103 is now the direct authority used above for the codes it enumerates, since South Ogden's own FAQ page has not been updated to reflect the 7/1/2026 edition changes.. Local amendments apply — see the South Ogden overview page for the full list.

Not on a percentage basis. South Ogden's City Fee Schedule applies the same 65% Commercial Plan Check and Site Plan Review fee to tenant improvements as to new commercial construction; the dollar amount differs only because the underlying project valuation typically differs.

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the South Ogden building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in South Ogden.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.