EV Charger / EVSE Permit in South Ogden, Utah

South Ogden's Consolidated Fee Schedule (last amended 16 Jun 2026) has no distinct EV-charger/EVSE line item, and the city does not publish a separate Electrical Permit fee at all — all Building Department work, including EV charger/EVSE installation (a dedicated circuit and/or panel work), is billed under the single valuation-based Building Permit Fee table in the Building Department Fees section. This was confirmed by a full read of the Building Department Fees pages (Building Permit Fees and Building Inspection Fees) of the official fee schedule, which lists no separate electrical or EV-specific fee category.

Verified 2026-07-20 · Source

When you need this permit

  • Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property
  • New dedicated electrical circuit and/or panel capacity to serve the charger
  • Subject to the same valuation-based Building Permit Fee table as other building/electrical work

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (valuation-based)South Ogden City Fee Schedule (last amended 16 Jun 2026), Building Department Fees § Building Permit Fees. No separate Electrical Permit or EV Charger fee category exists in this schedule; EV/EVSE work is billed under this general valuation-based table like any other building permit.
$0–$1,300: $47.00 flat, rising per the same valuation table used for all Building Department permits (e.g. $2,001–$25,000: $68.35 for the first $2,000 plus $14.00 per additional $1,000 or fraction thereof).
Residential Plan Review FeeSouth Ogden City Fee Schedule, § Building Inspection Fees.
45% of the building permit fee cost
Re-inspection FeeSouth Ogden City Fee Schedule, § Building Inspection Fees.
$47.00 per hour

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in South Ogden?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Electrical Rough-In / Final

    Inspection of the new EVSE circuit, panel work, and charger installation by the Building & Inspections Department; schedule by calling (801) 622-2913 between 9:00 AM-3:00 PM with 24 hours notice.

See the full South Ogden inspection guide — scheduling & re-inspection fees →

Tips

  • South Ogden has no separate EV-charger fee category and no standalone Electrical Permit fee — EV/EVSE installations are billed under the same valuation-based Building Permit Fee table used for all other building work.
  • Confirm current project valuation with the Building Department before applying, since the fee is tiered by building/project value rather than a flat EV-specific charge.
  • Schedule required inspections by calling (801) 622-2913 between 9:00 AM and 3:00 PM with at least 24 hours notice.

Frequently asked questions

A standard Building Permit filed through the city's online permit portal. Because South Ogden does not break out a separate electrical fee, the charge is calculated from the same valuation-based fee table used for other building work.

No. South Ogden's Consolidated Fee Schedule does not list a distinct EV-charger or electrical-permit fee category. EV charger/EVSE installations are billed under the city's general valuation-based Building Permit Fee table, starting at $47.00 for the lowest valuation tier.

South Ogden does not publish a plan-review timeline for this permit. Contact South Ogden City Building & Inspections Department at (801) 622-2913 or (801) 622-2713 (Building Official Tyson Egbert); general department (801) 622-2700 for current turnaround.

You'll need: Building Permit Application. Depending on your project, South Ogden may also ask for: Electrical Plan / Circuit Diagram. See the required-documents checklist on this page for details on each.

South Ogden requires 1 inspection(s) for an ev charger / evse permit, in order: Electrical Rough-In / Final. Schedule each through South Ogden City Building & Inspections Department ((801) 622-2913 or (801) 622-2713 (Building Official Tyson Egbert); general department (801) 622-2700).

Apply through South Ogden City Building & Inspections Department at 3950 S Adams Ave., South Ogden, UT 84403. Phone: (801) 622-2913 or (801) 622-2713 (Building Official Tyson Egbert); general department (801) 622-2700, email: tegbert@southogdencity.gov. Office hours: Monday–Friday, 8:00 AM–4:30 PM, per the official Building & Inspections Department page. Inspection scheduling calls must be placed between 9:00 AM–3:00 PM with at least 24 hours notice, per the official FAQ page.. Official information: https://www.southogdencity.com/departments/building_&_inspections/index.php.

South Ogden, Utah has adopted: GOVERNING LAW: Utah Code § 15A-2-103 (le.utah.gov/xcode/Title15A/Chapter2/15A-2-S103.html), version effective 7/1/2026 (amended by Ch. 47, 2026 General Session), sets the statewide-mandatory construction code suite (Utah Code § 15A-1-204 — binds every municipality; local amendments permitted, a different edition is not). South Ogden's official Building & Inspections FAQ page ('What code editions are being enforced?') still displays the pre-7/1/2026 edition list; re-checked live 2026-07-16, page text is byte-identical to the earlier fetch: 'The city is currently enforcing the following codes: 2021 Edition of the International Building Code, 2021 Edition of the International Residential Code, 2021 Edition of the International Plumbing Code, 2021 Edition of the International Mechanical Code, 2021 Edition of the National Electrical Code, 2021 Edition of the International Fuel Gas Code, 2021 Edition of the International Fire Code, 2009 Edition of the International Building Code (ICC/ANSI A117.1) for Accessibility Standards.' State law governs regardless of the page's lag; each line below states current law first, then the page's as-published (stale or omitted) text.; 2024 Edition of the International Building Code (IBC) — per Utah Code § 15A-2-103(1)(a), effective 7/1/2026. South Ogden's FAQ still lists '2021 Edition of the International Building Code' (live re-check 2026-07-16).; 2021 Edition of the International Residential Code (IRC), plus Appendix AQ of the 2021 IRC — per Utah Code § 15A-2-103(1)(b)/(c); this edition did NOT change in the 7/1/2026 flip. Matches South Ogden's FAQ, which lists '2021 Edition of the International Residential Code' (live re-check 2026-07-16).; 2024 Edition of the International Plumbing Code (IPC) — per Utah Code § 15A-2-103(1)(d), effective 7/1/2026. South Ogden's FAQ still lists '2021 Edition of the International Plumbing Code' (live re-check 2026-07-16).; 2024 Edition of the International Mechanical Code (IMC) — per Utah Code § 15A-2-103(1)(e), effective 7/1/2026. South Ogden's FAQ still lists '2021 Edition of the International Mechanical Code' (live re-check 2026-07-16).; 2023 Edition of the National Electrical Code (NEC) — per Utah Code § 15A-2-103(1)(g); this edition did NOT change in the 7/1/2026 flip and has been state law since before this project's original 2026-07-07 review. South Ogden's FAQ still lists '2021 Edition of the National Electrical Code' (live re-check 2026-07-16) — this is a PRE-EXISTING discrepancy that predates and is unrelated to the 2026-07-01 code-cycle flip (South Ogden's page was already citing a stale NEC edition under the prior law too); reported here as-published rather than corrected, per grounded-data policy of not inventing a fact the city's own source does not state.; 2024 Edition of the International Fuel Gas Code (IFGC) — per Utah Code § 15A-2-103(1)(f), effective 7/1/2026. South Ogden's FAQ still lists '2021 Edition of the International Fuel Gas Code' (live re-check 2026-07-16).; 2024 International Energy Conservation Code (IECC), one statewide edition (no residential/commercial split) — per Utah Code § 15A-2-103(1)(h), effective 7/1/2026. Not mentioned on South Ogden's FAQ, department page, Forms page, or City Fee Schedule as of live re-check 2026-07-16; added here as a statute-sourced omission (applies statewide regardless of city publication), not fabricated.; 2024 International Existing Building Code (IEBC) — per Utah Code § 15A-2-103(1)(i), effective 7/1/2026. Not mentioned on any South Ogden source reviewed as of live re-check 2026-07-16; added as a statute-sourced omission.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — per Utah Code § 15A-2-103(1)(n), effective 7/1/2026. Not mentioned on any South Ogden source reviewed as of live re-check 2026-07-16; added as a statute-sourced omission.; Modular Building Institute (MBI) Standards 1200 and 1205 — per Utah Code § 15A-2-103(1)(o), statewide-mandated for modular units. Not mentioned on any South Ogden source reviewed as of live re-check 2026-07-16; added as a statute-sourced omission.; 2021 Edition of the International Fire Code (IFC) — per the official FAQ page (live re-check 2026-07-16, unchanged); South Ogden City Code Title 3, Chapter 1 separately adopts by reference 'the International Fire Code version adopted by the State of Utah Fire Marshal's Office for the respective year' (Ordinance 24-05, effective 2 Jul 2024), so the specific IFC edition in force tracks the State Fire Marshal's current adoption. NOTE: Utah Code § 15A-2-103 does NOT adopt the IFC — it is separately governed under Title 15A Chapter 5, outside the scope of this section; South Ogden's IFC citation and Fire Code ordinance are therefore unaffected by, and not mis-scoped to, § 15A-2-103.; 2009 Edition of the International Building Code (ICC/ANSI A117.1) for Accessibility Standards — per the official FAQ page (live re-check 2026-07-16, unchanged). This accessibility standard is not among the codes enumerated in Utah Code § 15A-2-103(1); reproduced here as South Ogden's own published statement, not itself corrected against that section.; Utah's statewide construction-code framework under Utah Code Title 15A (State Construction and Fire Codes Act) governs code adoption and amendment authority for all Utah municipalities, including South Ogden; § 15A-2-103 is now the direct authority used above for the codes it enumerates, since South Ogden's own FAQ page has not been updated to reflect the 7/1/2026 edition changes.. Local amendments apply — see the South Ogden overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the South Ogden building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.