EV Charger / EVSE Permit in Unincorporated Fremont County, Wyoming
Fremont County has no general building permit or county-issued electrical permit for unincorporated-area construction, consistent with the other Fremont County permit types. Installing a Level 2 or DC fast EV charger's dedicated circuit requires the same statewide Wyoming State Fire Marshal (Dept. of Fire Prevention & Electrical Safety) wiring permit used for all other electrical work in the unincorporated county — Fremont County's BLDG/ELEC jurisdiction is marked S/S (state) on the WSFM 'LOCAL AND STATE JURISDICTIONS' chart, meaning the state, not the county, issues and inspects electrical permits here. The governing statute is W.S. § 35-9-120 in the current 2025 codified Wyoming Statutes — the same statewide statute cited in the Albany County ev-charger-permit entry, and the authority behind the Wyoming State Fire Marshal wiring-permit program that Fremont County, having no county building code or electrical enforcement authority of its own, relies on entirely. The statute codifies a flat $50.00 electrical wiring permit fee at (c)(ii), plus a separate $20.00 + $0.50/amp inspection fee under 'all other electrical installations' at (c)(i)(E) — the category an EV charger branch circuit falls under.
Verified 2026-07-20 · Source
When you need this permit
- No county building or electrical permit applies — the County has not adopted a general building code and has not taken electrical-code delegation under W.S. § 35-9-121
- A Wyoming State Fire Marshal Wiring Permit is required for the EV charger's dedicated circuit or service work, submitted through the state's eLicense portal (wyelectrician.imagetrendlicense.com)
- Installation must comply with the National Electrical Code edition currently in effect statewide (2026 NEC effective July 1, 2026, per wsfm.wyo.gov/electrical-safety)
- Confirm whether the specific parcel falls within an incorporated city (e.g., Riverton, Lander) before assuming this unincorporated-county process applies — those cities run separate permitting systems
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Wyoming State Fire Marshal's Office (Dept. Show full citationHide
Wyoming State Fire Marshal's Office (Dept. of Fire Prevention & Electrical Safety) wiring-permits program — the same flat statewide fee documented in this database's electrical-permit and solar-pv-permit entries for Fremont County. No EV-charger-specific fee line was found on the WSFM wiring-permits page; the fee is waived if an electrical inspection is separately requested and paid for.Review timeline
Inspection process
- 1
Electrical (State WSFM)
Conductor sizing, breaker/panel work, grounding, and EVSE equipment connection verified by a WSFM-assigned regional electrical inspector under the state wiring permit
See the full Unincorporated Fremont County inspection guide — scheduling & re-inspection fees →
Tips
- Fremont County issues NO electrical permits of any kind — an EV charger circuit needs a State of Wyoming wiring permit ($50) from the WSFM, not a county permit, the same pattern documented for standard electrical and solar work in this record.
- Confirm your parcel isn't within an incorporated city (Riverton, Lander, Dubois, Hudson, Shoshoni, Pavillion, South Pass City) before applying — those cities run their own separate electrical permitting systems distinct from this unincorporated-county/state process.
- directly against the current codified Wyoming Statutes (W.S. § 35-9-120): the $50.00 flat wiring permit fee is current law, and a new EV charger branch circuit is separately billed at $20.00 + $0.50/amp under the 'all other electrical installations' inspection fee category.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fee schedules
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Fremont County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Unincorporated Fremont County's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Unincorporated Fremont County yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Unincorporated Fremont County lands. Privacy.
Other permits in Unincorporated Fremont County
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Wyoming →
Look up this fee in a different city →
Related guides
Now live
Build your Unincorporated Fremont County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Fremont County — in one checklist. Free, for any city and any number of projects.
Get started →