Fremont County has no general building permit or county-issued electrical permit for unincorporated-area construction (consistent with this database's other Fremont County permitTypes). Installing a Level 2 or DC fast EV charger's dedicated circuit requires the same statewide Wyoming State Fire Marshal (Dept. of Fire Prevention & Electrical Safety) wiring permit used for all other electrical work in the unincorporated county — Fremont County's BLDG/ELEC jurisdiction is marked S/S (state) on the WSFM 'LOCAL AND STATE JURISDICTIONS' chart, meaning the state, not the county, issues and inspects electrical permits here. Re-verified 2026-07-20: pulled the current 2025 codified Wyoming Statutes text of W.S. § 35-9-120 directly (same statewide statute documented in this database's Albany County ev-charger-permit entry) — this is the actual governing statute behind the Wyoming State Fire Marshal wiring-permit program that Fremont County (with no county building code or electrical enforcement authority of its own) relies on entirely. The statute currently codifies a flat $50.00 electrical wiring permit fee (c)(ii), plus a separate $20.00 + $0.50/amp inspection fee under 'all other electrical installations' (c)(i)(E) — the category an EV charger branch circuit falls under. This is a real, current, statutory, citable governing figure, sufficient to upgrade this entry from partial to verified.

Verified 2026-07-20 · Source

When you need this permit

  • No county building or electrical permit applies — the County has not adopted a general building code and has not taken electrical-code delegation under W.S. § 35-9-121
  • A Wyoming State Fire Marshal Wiring Permit is required for the EV charger's dedicated circuit or service work, submitted through the state's eLicense portal (wyelectrician.imagetrendlicense.com)
  • Installation must comply with the National Electrical Code edition currently in effect statewide (2026 NEC effective July 1, 2026, per wsfm.wyo.gov/electrical-safety)
  • Confirm whether the specific parcel falls within an incorporated city (e.g., Riverton, Lander) before assuming this unincorporated-county process applies — those cities run separate permitting systems

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Standard Wiring Permit (State WSFM — no distinct EV charger line item)Wyoming State Fire Marshal's Office (Dept. of Fire Prevention & Electrical Safety) wiring-permits program — the same flat statewide fee documented in this database's electrical-permit and solar-pv-permit entries for Fremont County. No EV-charger-specific fee line was found on the WSFM wiring-permits page; the fee is waived if an electrical inspection is separately requested and paid for.
$50.00
All other electrical installations (statutory category covering a new EV charger branch circuit)Wyoming Statutes § 35-9-120(c)(i)(E) (2025 codification, current as of this 2026-07-20 verification) — e.g. a 40-50A EV charger circuit computes to roughly $40.00-$45.00 under this line item, in addition to the flat $50.00 wiring permit fee.
$20.00 plus $0.50 per ampere rating of the electrical service

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in Unincorporated Fremont County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Electrical (State WSFM)

    Conductor sizing, breaker/panel work, grounding, and EVSE equipment connection verified by a WSFM-assigned regional electrical inspector under the state wiring permit

See the full Unincorporated Fremont County inspection guide — scheduling & re-inspection fees →

Tips

  • Fremont County issues NO electrical permits of any kind — an EV charger circuit needs a State of Wyoming wiring permit ($50) from the WSFM, not a county permit, the same pattern documented for standard electrical and solar work in this file.
  • Confirm your parcel isn't within an incorporated city (Riverton, Lander, Dubois, Hudson, Shoshoni, Pavillion, South Pass City) before applying — those cities run their own separate electrical permitting systems distinct from this unincorporated-county/state process.
  • Re-confirmed 2026-07-20 directly against the current codified Wyoming Statutes (W.S. § 35-9-120): the $50.00 flat wiring permit fee is current law, and a new EV charger branch circuit is separately billed at $20.00 + $0.50/amp under the 'all other electrical installations' inspection fee category.

Frequently asked questions

Unincorporated Fremont County requires an ev charger / evse permit for: No county building or electrical permit applies — the County has not adopted a general building code and has not taken electrical-code delegation under W.S. § 35-9-121; A Wyoming State Fire Marshal Wiring Permit is required for the EV charger's dedicated circuit or service work, submitted through the state's eLicense portal (wyelectrician.imagetrendlicense.com); Installation must comply with the National Electrical Code edition currently in effect statewide (2026 NEC effective July 1, 2026, per wsfm.wyo.gov/electrical-safety); Confirm whether the specific parcel falls within an incorporated city (e.g., Riverton, Lander) before assuming this unincorporated-county process applies — those cities run separate permitting systems. If your project isn't listed, confirm with Fremont County Planning Department at (307) 332-1077 before starting work.

In Unincorporated Fremont County, the published Standard Wiring Permit (State WSFM — no distinct EV charger line item) is: $50.00. Additional published fees: All other electrical installations (statutory category covering a new EV charger branch circuit) — $20.00 plus $0.50 per ampere rating of the electrical service. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Unincorporated Fremont County does not publish a plan-review timeline for this permit. Contact Fremont County Planning Department at (307) 332-1077 for current turnaround.

You'll need: WSFM Wiring Permit Application (online, eLicense portal). See the required-documents checklist on this page for details on each.

Unincorporated Fremont County requires 1 inspection(s) for an ev charger / evse permit, in order: Electrical (State WSFM). Schedule each through Fremont County Planning Department ((307) 332-1077).

Apply through Fremont County Planning Department at 450 North 2nd Street, Lander, WY 82520. Phone: (307) 332-1077, email: support@fremontcountywy.gov. Office hours: Mon–Fri (contact department for current hours). Official information: https://fremontcountywy.gov/government/departments/planning_department/building_codes.php.

Unincorporated Fremont County, Wyoming has adopted: NO county-wide building code and NO county-specific building permit for private construction. Fremont County's own Planning Department page states verbatim: 'Fremont County does not have any County-wide Zoning or County specific Building Codes, except the following' (small wastewater/septic permits and floodplain zoning in mapped FEMA hazard areas near Lander, Riverton, Dubois, and Hudson) — https://fremontcountywy.gov/government/departments/planning_department/building_codes.php; Confirmed against the Wyoming Dept. of Fire Prevention & Electrical Safety 'LOCAL AND STATE JURISDICTIONS' chart (updated 7/7/2026 as of this check — the date label itself changed from a prior 5/11/2026, but the underlying Fremont County determination did not — embedded at wsfm.wyo.gov/electrical-safety): Fremont County's BLDG INSP/PR and ELEC INSP/PR columns are both still marked S/S (state) for the unincorporated county, meaning the county has NOT taken general building-code delegation under W.S. § 35-9-121 — the State of Wyoming, not Fremont County, has building jurisdiction over unincorporated private construction; Fremont County's own building-codes page RECOMMENDS (does not require) that residents follow the State of Wyoming's adopted codes for new construction: 2024 International Building Code, 2024 International Existing Building Code, 2024 International Mechanical Code, 2024 International Fire Code, 2024 International Fuel Gas Code, and the National Electrical Code (2023 edition was in effect through June 30, 2026; per wsfm.wyo.gov/electrical-safety, the 2026 NEC edition took effect statewide July 1, 2026) — these are recommendations for quality/insurability, not a locally enforced code, and the county issues no building permit and performs no building inspection against them; Fremont County explicitly states it does NOT issue Certificates of Occupancy; Commercial/public construction is NOT fully unregulated: per Wyoming Statute § 35-9-108, a State Fire Marshal plan review IS required for government/school buildings, buildings over 5,000 sq ft with public access, childcare centers (10+ children), multi-story buildings, places of assembly, fire-protection-system work, alternative energy installations (solar/wind/generator), aboveground flammable/combustible liquid storage tanks, Type I commercial kitchen hoods, spray finish applications, and RV/camping/mobile-home park site plans — contact the State Fire Marshal's Plan Review office (Jeff Schoen, (307) 673-1461, jeff.schoen@wyo.gov) for any of these commercial scopes; The Incorporated Cities within Fremont County (Riverton, Lander, Dubois, Hudson, Shoshoni, Pavillion, and South Pass City) each have their OWN separate zoning and building codes and issue their own permits — this LEAN page covers ONLY unincorporated (outside city-limits) Fremont County. See the separate City of Riverton page for Riverton's own building department.. Local amendments apply — see the Unincorporated Fremont County overview page for the full list.

No. Fremont County has no county-wide building code and has not taken electrical-permit delegation from the State — its BLDG/ELEC jurisdiction is marked S/S (state) on the WSFM jurisdiction chart. Installing an EV charger's dedicated circuit requires a $50 Wyoming State Fire Marshal Wiring Permit, submitted through wyelectrician.imagetrendlicense.com, not a county application.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Fremont County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.