Solar / Alternative Energy PV Permit (State Plan Review) + Land Use Certificate in Unincorporated Uinta County, Wyoming
Unincorporated Uinta County has no county-run solar permit or building code (see land-use-certificate). A rooftop or ground-mount solar PV installation requires: (1) a Wyoming State Fire Marshal's Office (Dept. of Fire Prevention & Electrical Safety) Plan Review, using the state's dedicated 'Electrical PV Plan Checklist' — because Uinta County has not taken delegated electrical authority (WSFM chart: ELEC INSP/PR = S/S), this state-level review applies here just as it does to standard electrical wiring; and (2) a county Land Use Certificate as the alteration-to-a-structure zoning approval, using the same $50 (dwelling/address required) or $25 (no address required) fee as any other construction/alteration — there is no distinct county solar fee or application. Uinta County's own Land Use Resolution 23-02 was checked in full and contains no solar-specific provisions (no accessory-use size threshold, no setback rule) — solar is not separately addressed in county zoning here, unlike some neighboring Wyoming counties (e.g., Sweetwater, Laramie) that do have dedicated solar accessory-use standards.
Verified 2026-07-20 · Source
When you need this permit
- State Plan Review required for 'Alternative Energy installation or alteration (solar, residential wind, generator, etc.)' per the Wyoming State Fire Marshal's Dept. of Fire Prevention & Electrical Safety — applies statewide wherever the WSFM (not a delegated county) holds electrical jurisdiction, which includes unincorporated Uinta County
- Submit plans via the WSFM eLicensing/ePermit/ePayment Portal using the dedicated 'Electrical PV Plan Checklist'
- Plans are accepted or rejected for review within 5 business days of receipt; a complete submittal is reviewed within 21 business days of acceptance (or 10 business days after any additional requested information is received, whichever is greater)
- Review fees are calculated per the ICC Building Valuation Data table and the Department of Fire Prevention and Electrical Safety Rules, Chapter 2, Section 3 — the applicant is notified of the fee due once plans are accepted; fees must be paid before a Permit to Construct is issued
- No work may begin before the Permit to Construct is issued
- A county Land Use Certificate is also required for the structural alteration itself, at the standard $50 (address/dwelling) or $25 (no address) fee, per the Uinta County Land Use Certificate process (see land-use-certificate entry) — Uinta County's Land Use Resolution 23-02 contains no solar-specific accessory-use standard, so ordinary new-construction/alteration rules apply
- Uinta County is served by WSFM electrical inspector Dan Tobin (covers Fremont, Sublette, Uinta, Lincoln, and Teton counties; the WSFM page's own formatting leaves ambiguous whether a '(Licensing Only)' qualifier applies county-wide or just to Teton — confirm current inspection-vs-licensing-only status for Uinta directly with WSFM)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Electrical / PV Interconnection
Performed under the WSFM statewide electrical program once the Permit to Construct is issued
See the full Unincorporated Uinta County inspection guide — scheduling & re-inspection fees →
Tips
- There is no dedicated county solar permit or fee — the structural/zoning side is just the standard $25-$50 Land Use Certificate, and the substantive review is done at the STATE level by the Wyoming State Fire Marshal's Office using its own 'Electrical PV Plan Checklist,' not by Uinta County.
- Confirm with WSFM (Jeff Schoen, 307-673-1461) whether your specific project needs the full Alternative Energy plan review or just a standard wiring permit — the WSFM page lists Alternative Energy installation/alteration as one of several project types requiring plan review.
- Uinta County's own Land Use Resolution 23-02 has no solar-specific accessory-use rules (unlike Sweetwater or Laramie counties) — a rooftop or ground-mount system here is treated as ordinary construction/alteration for zoning purposes.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Uinta County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Uinta County
Solar / Alternative Energy PV Permit (State Plan Review) + Land Use Certificate in other cities
Look up this fee in a different city →
Now live
Build your Unincorporated Uinta County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Uinta County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →