Residential Building Permit (New Construction, Additions, Remodels) — Springerville, Arizona · Requirements sheet
Verified 2026-07-07 · Source: https://www.springervilleaz.gov/building-department
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit (New Construction, Additions, Remodels) in Springerville, Arizona
Required for new single-family residential construction, additions, remodels involving plumbing/electrical/foundation/structural changes, porches, and garages in the Town of Springerville. Requires a preceding Plan/Design Review approval and is reviewed against the 2015 IRC/IBC as adopted by the Town, with Springerville's own climatic/geographic design criteria (7,000 ft elevation, 90 mph wind Exposure B, Seismic Design Category B, 4°F winter design temperature, 32-36 PSF snow loads).
Verified 2026-07-07 · Source
When you need this permit
- A Plan/Design Review application resulting in a building permit and inspections is required for most residential projects: anything having to do with structural, electrical, plumbing, or foundations (including remodeling, porches, additions, accessory buildings, and equipment such as air conditioners, heat sources, and water heaters)
- Plans must comply with the 2015 IRC/IBC as adopted by the Town of Springerville and the Town's own Climate and Geographic Design Criteria (90 mph wind, Exposure B; Seismic Design Category B; 4°F winter design temperature; 32-36 PSF snow loads depending on roof pitch)
- It is the homeowner/property owner's responsibility to provide acceptable plans or information to obtain a building permit; the Planning & Zoning Department reviews submitted plans but does not design them
- A licensed general contractor may have to oversee the project, with additional subcontractors for electrical, plumbing, or HVAC installations, OR an owner-builder/owner-developer exemption under A.R.S. §32-1121A.5 or A.R.S. §32-1121A.6 Owner-builderContractor
- Metal buildings and some pre-assembled buildings require stamped engineered plans
- Detached accessory structures over 200 square feet require a building permit
- Rental units are considered commercial property and require a commercial-licensed contractor Contractor
- Work completed without first obtaining a permit may be charged double the original permitting fee
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation/Footing
Before concrete pour
- 2
Rough-In (Framing, Electrical, Plumbing, Mechanical)
Structural framing and rough trade work before closing walls
- 3
Final / Certificate of Occupancy
All work complete per approved plans; Certificate of Occupancy issued (sent upon request)
See the full Springerville inspection guide — scheduling & re-inspection fees →
Tips
- Per the Town's Plan Review Checklist (Municipal Code Chapter 17.88): 'The zoning administrator shall have ten (10) working days from submission of the plan application to review and approve, conditionally approve or reject said plan.' If the zoning administrator obtains the Planning & Zoning Commission's opinion, a decision must be rendered within five (5) days of Commission review.
- This 10-working-day figure is independently corroborated by direct Municipal Code citation (Chapter 17.28.070, Walls and Fences) as well as by the boilerplate 'Review Procedure' section restated verbatim on every Building Department permit application checklist (Plan/Design Review, Sign, Solar, Wall/Fence, Utility/Mechanical, Shed/Storage) — a consistent Town-wide standard, not an estimate.
- Plan/Design Review approval becomes void six months after approval if a building permit has not been issued; an extension may be granted if requested prior to expiration.
- Building Permit Fees themselves (as opposed to the Plan Design Review fee) are valuation-based per ICC/Building Valuation Data (Feb. 2015 charts, adopted by Ordinance 2016-005) rather than a flat dollar figure — exact valuation-tier dollar amounts were not published as a standalone table on the Town's fee schedule or site as of this review; contact the Building Department for a project-specific quote.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-07.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Springerville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Springerville
Residential Building Permit (New Construction, Additions, Remodels) in other cities
Compare residential building permit (new construction, additions, remodels) fees across Arizona →
Look up this fee in a different city →
Now live
Build your Springerville project checklist
Describe your project once and get every permit, document, and fee it triggers in Springerville — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →