Residential Building Permit (New Construction, Additions, Remodels) in Springerville, Arizona

Required for new single-family residential construction, additions, remodels involving plumbing/electrical/foundation/structural changes, porches, and garages in the Town of Springerville. Requires a preceding Plan/Design Review approval and is reviewed against the 2015 IRC/IBC as adopted by the Town, with Springerville's own climatic/geographic design criteria (7,000 ft elevation, 90 mph wind Exposure B, Seismic Design Category B, 4°F winter design temperature, 32-36 PSF snow loads).

Verified 2026-07-07 · Source

When you need this permit

  • A Plan/Design Review application resulting in a building permit and inspections is required for most residential projects: anything having to do with structural, electrical, plumbing, or foundations (including remodeling, porches, additions, accessory buildings, and equipment such as air conditioners, heat sources, and water heaters)
  • Plans must comply with the 2015 IRC/IBC as adopted by the Town of Springerville and the Town's own Climate and Geographic Design Criteria (90 mph wind, Exposure B; Seismic Design Category B; 4°F winter design temperature; 32-36 PSF snow loads depending on roof pitch)
  • It is the homeowner/property owner's responsibility to provide acceptable plans or information to obtain a building permit; the Planning & Zoning Department reviews submitted plans but does not design them
  • A licensed general contractor may have to oversee the project, with additional subcontractors for electrical, plumbing, or HVAC installations, OR an owner-builder/owner-developer exemption under A.R.S. §32-1121A.5 or A.R.S. §32-1121A.6 Owner-builderContractor
  • Metal buildings and some pre-assembled buildings require stamped engineered plans
  • Detached accessory structures over 200 square feet require a building permit
  • Rental units are considered commercial property and require a commercial-licensed contractor Contractor
  • Work completed without first obtaining a permit may be charged double the original permitting fee

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Plan Design Review Fee — ResidentialTown of Springerville Fee Schedule, effective January 15, 2025
$100.00
Building Permit FeeTown of Springerville Fee Schedule, effective January 15, 2025 — not a flat fee; based on project valuation
Varies in accordance with ICC/Building Valuation Data — February 2015 Charts and Formulas, adopted in Ordinance 2016-005
3rd Party Review of any plan or designTown of Springerville Fee Schedule, effective January 15, 2025
Applicant pays the difference in review costs
Mandatory Inspections (2)Town of Springerville Fee Schedule, effective January 15, 2025
$100.00
Additional InspectionsTown of Springerville Fee Schedule, effective January 15, 2025
$50.00
Extension Fee (6 months)Town of Springerville Fee Schedule, effective January 15, 2025
$85.00
Certificate of OccupancyTown of Springerville Fee Schedule, effective January 15, 2025
$30.00

Review timeline

Plan reviewSpringerville’s published plan-review target
10–10 business days

How long did your Residential Building Permit (New Construction, Additions, Remodels) permit actually take in Springerville?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation/Footing

    Before concrete pour

  2. 2

    Rough-In (Framing, Electrical, Plumbing, Mechanical)

    Structural framing and rough trade work before closing walls

  3. 3

    Final / Certificate of Occupancy

    All work complete per approved plans; Certificate of Occupancy issued (sent upon request)

See the full Springerville inspection guide — scheduling & re-inspection fees →

Tips

  • Per the Town's Plan Review Checklist (Municipal Code Chapter 17.88): 'The zoning administrator shall have ten (10) working days from submission of the plan application to review and approve, conditionally approve or reject said plan.' If the zoning administrator obtains the Planning & Zoning Commission's opinion, a decision must be rendered within five (5) days of Commission review.
  • This 10-working-day figure is independently corroborated by direct Municipal Code citation (Chapter 17.28.070, Walls and Fences) as well as by the boilerplate 'Review Procedure' section restated verbatim on every Building Department permit application checklist (Plan/Design Review, Sign, Solar, Wall/Fence, Utility/Mechanical, Shed/Storage) — a consistent Town-wide standard, not an estimate.
  • Plan/Design Review approval becomes void six months after approval if a building permit has not been issued; an extension may be granted if requested prior to expiration.
  • Building Permit Fees themselves (as opposed to the Plan Design Review fee) are valuation-based per ICC/Building Valuation Data (Feb. 2015 charts, adopted by Ordinance 2016-005) rather than a flat dollar figure — exact valuation-tier dollar amounts were not published as a standalone table on the Town's fee schedule or site as of this review; contact the Building Department for a project-specific quote.

Frequently asked questions

Springerville requires a residential building permit (new construction, additions, remodels) for: A Plan/Design Review application resulting in a building permit and inspections is required for most residential projects: anything having to do with structural, electrical, plumbing, or foundations (including remodeling, porches, additions, accessory buildings, and equipment such as air conditioners, heat sources, and water heaters); Plans must comply with the 2015 IRC/IBC as adopted by the Town of Springerville and the Town's own Climate and Geographic Design Criteria (90 mph wind, Exposure B; Seismic Design Category B; 4°F winter design temperature; 32-36 PSF snow loads depending on roof pitch); It is the homeowner/property owner's responsibility to provide acceptable plans or information to obtain a building permit; the Planning & Zoning Department reviews submitted plans but does not design them; A licensed general contractor may have to oversee the project, with additional subcontractors for electrical, plumbing, or HVAC installations, OR an owner-builder/owner-developer exemption under A.R.S. §32-1121A.5 or A.R.S. §32-1121A.6; Metal buildings and some pre-assembled buildings require stamped engineered plans; Detached accessory structures over 200 square feet require a building permit; Rental units are considered commercial property and require a commercial-licensed contractor; Work completed without first obtaining a permit may be charged double the original permitting fee. If your project isn't listed, confirm with Town of Springerville Planning & Zoning Department — Building Department at 928-333-2656 ext. 227 (Building Department); 928-333-2656 (Planning & Zoning main line); fax 928-333-5598 before starting work.

In Springerville, the published Plan Design Review Fee — Residential is: $100.00. Additional published fees: Building Permit Fee — Varies in accordance with ICC/Building Valuation Data — February 2015 Charts and Formulas, adopted in Ordinance 2016-005; 3rd Party Review of any plan or design — Applicant pays the difference in review costs; Mandatory Inspections (2) — $100.00; Additional Inspections — $50.00; Extension Fee (6 months) — $85.00; Certificate of Occupancy — $30.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

The Plan/Design Review step (required before a building permit is issued) has a published 10-working-day review timeline per Town of Springerville Municipal Code Chapter 17.88, confirmed on the Town's own Plan Review Checklist and independently corroborated in Municipal Code Chapter 17.28.070 (Walls and Fences). If the zoning administrator elects to route the application through the Planning & Zoning Commission, an additional 5 days applies after Commission review.

You'll need: Plan/Design Review Application; Exemptions from Licensing Supplement; Construction Plans and Specifications. See the required-documents checklist on this page for details on each.

Springerville requires 3 inspection(s) for a residential building permit (new construction, additions, remodels), in order: Foundation/Footing, Rough-In (Framing, Electrical, Plumbing, Mechanical), Final / Certificate of Occupancy. Schedule each through Town of Springerville Planning & Zoning Department — Building Department (928-333-2656 ext. 227 (Building Department); 928-333-2656 (Planning & Zoning main line); fax 928-333-5598).

Apply through Town of Springerville Planning & Zoning Department — Building Department at 418 E. Main St., Springerville, AZ 85938. Phone: 928-333-2656 ext. 227 (Building Department); 928-333-2656 (Planning & Zoning main line); fax 928-333-5598, email: Publicly listed on the Town's Building Department page as an obfuscated/masked address; no plain-text department email address was recoverable from the live site. Contact by phone at 928-333-2656 ext. 227, or via the Town's online contact form at springervilleaz.gov/contact-us.. Office hours: Not published on the Town's Building Department page as of this review (no explicit hours-of-operation statement was found on the Building Department, Community Development, or Contact Us pages). Applicants must contact the Building Department a minimum of twenty-four (24) hours in advance to schedule an inspection, per the Town's own permit application forms.. Official information: https://www.springervilleaz.gov/building-department.

Springerville, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The Town of Springerville runs its own Planning & Zoning Department / Building Department and independently adopts and administers its own construction codes and fee schedule; it does NOT defer building permitting to Apache County or to the neighboring Town of Eagar — Springerville's own permit applications, fee schedule, and Municipal Code sections (e.g., Chapter 17.28 Walls and Fences, Chapter 17.88 Plan Review) are self-contained and administered entirely by Springerville's own Planning & Zoning/Building staff. This is confirmed independently from Springerville's own primary sources, not inferred from the Eagar precedent.; 2015 edition of the International Residential Code (IRC), as adopted by the Town of Springerville. Source: Town of Springerville 'Building Health and Safety' reference document (springervilleaz.gov, Building Department Forms), restated verbatim on multiple Town permit application checklists (Manufactured Home, Shed/Storage, Plan/Design Review).; 2015 International Building Code (IBC), as adopted by the Town of Springerville for commercial/non-residential construction. Source: Town of Springerville 'Building Health and Safety' reference document.; 2015 International Fire Code (IFC), as adopted by the Town of Springerville as its uniform fire code. Source: Town of Springerville 'Building Health and Safety' reference document.; 2015 International Mechanical Code (IMC), as adopted by the Town of Springerville. Source: Town of Springerville 'Building Health and Safety' reference document.; 2015 International Plumbing Code (IPC), as adopted by the Town of Springerville. Source: Town of Springerville 'Building Health and Safety' reference document.; 2015 International Green Building Code (IgCC), as adopted by the Town of Springerville. Source: Town of Springerville 'Building Health and Safety' reference document.; 2014 National Electrical Code (NEC), as adopted by the Town of Springerville (electrical code cycle predates the 2015 ICC set). Source: Town of Springerville 'Building Health and Safety' reference document.; Manufactured homes, mobile homes, and factory-built buildings (FBB) are regulated directly by the State of Arizona (Arizona Department of Fire, Building and Life Safety, Office of Manufactured Housing, 1110 West Washington, Suite 100, Phoenix, AZ 85007) for construction/installation standards, including HUD federal preemption under 24 CFR §3280 (construction) and §3285 (installation, non-preemptive — local jurisdictions MAY set stricter local snow-load/installation standards per the Department's own May 24, 2010 clarification letter); the Town of Springerville issues a separate local Manufactured Home Installation Permit for site installation, utility connections, accessory structures, and inspections. Source: Town of Springerville Manufactured Home Installation Permit Application (Department of Fire, Building and Life Safety letterhead) and Arizona Department of Fire, Building and Life Safety letter re: Design Roof Load Zone 'South' in Arizona (May 24, 2010).; Flood Hazards: the National Flood Insurance Program (NFIP) as adopted by the Town Council of Springerville on 10/2/2007, administered by the Apache County Engineer. Source: Town of Springerville 'Building Health and Safety' / Climate and Geographic Design reference document.; Note on code-text access: the Town's Code of Ordinances is hosted on Municode Library (library.municode.com/az/springerville) which returned HTTP 403 Forbidden on direct fetch attempts; the specific adopted code edition years above are instead sourced directly from the Town's own (non-Municode) 'Building Health and Safety' reference PDF, a primary town-published, non-mirror source, cross-confirmed as identical text appearing on at least three separate Town permit-application PDFs (Manufactured Home, Shed/Storage, and the standalone Building Health and Safety document).. Local amendments apply — see the Springerville overview page for the full list.

No. The Town of Springerville operates its own Planning & Zoning Department / Building Department, with its own permit applications, fee schedule (effective January 15, 2025), adopted code editions (2015 IRC/IBC/IFC/IMC/IPC/IgCC, 2014 NEC), and Municipal Code sections, entirely independent of the neighboring Town of Eagar's Building Department. The two towns' fire/EMS response is jointly provided by the Round Valley Fire & Medical Department, but that arrangement is limited to fire/EMS and does not extend to building-code adoption or permit issuance for either town.

Sources & verification

Verified against official sources. Last reviewed 2026-07-07.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Springerville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.