Electric Vehicle (EV) Charging Station Permit — Springerville, Arizona · Requirements sheet
Verified 2026-07-20 · Source: https://www.springervilleaz.gov/media/Documents/Forms-Documents/Building-Department-Forms/Utility%20Mechanical%20App%20.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Electric Vehicle (EV) Charging Station Permit in Springerville, Arizona
Installing a residential or commercial EV charging station (EVSE) in the Town of Springerville is electrical work and is billed under the Town's general Utility/Mechanical Permit (Electrical, Plumbing, Mechanical) — the Town's Fee Schedule and permit application checklists have no distinct EV-charging or EVSE line item. If the installation requires a service panel upgrade, that also falls under the same Utility/Mechanical Permit category.
Verified 2026-07-20 · Source
When you need this permit
- Utility/Mechanical Permit Application required, checking the Electrical scope box, for the EV charger circuit and any associated panel work
- Load and sizing calculations required (the Town's checklist requires load/sizing calcs for both new and replacement equipment, which by the same logic applies to a new EV charging circuit)
- Site plan/building diagram detailing the installation or repair location required
- All applications must conform to the current IBC/UBC/NEC codes adopted by the Town (2014 NEC as of this review)
- Contractor license information required, or a claimed A.R.S. §32-1121A.5/.6 owner-builder exemption Owner-builderContractor
- No dedicated EV-charging-station permit or fee line exists in the Town's January 15, 2025 Fee Schedule or in its Utility/Mechanical Permit Application Checklist
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Wiring/circuit and any panel work before enclosure
- 2
Final
Charging equipment installed and operational, connections verified
See the full Springerville inspection guide — scheduling & re-inspection fees →
Tips
- Springerville has no distinct EV charger or EVSE permit — apply using the standard Utility/Mechanical Permit Application and check the Electrical scope box, the same form used for panel upgrades and other electrical work.
- Budget for the same $50.00 Utility Mechanical Upgrade Permit fee and 10-working-day review timeline that applies to all other electrical work in the Town.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Springerville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Springerville
Electric Vehicle (EV) Charging Station Permit in other cities
Compare electric vehicle (ev) charging station permit fees across Arizona →
Look up this fee in a different city →
Related guides
Now live
Build your Springerville project checklist
Describe your project once and get every permit, document, and fee it triggers in Springerville — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →