Residential Building Permit (New Construction, incl. SFD / ADU / Tiny House) in Tusayan, Arizona

Required for new single-family dwelling, accessory dwelling unit (ADU), lot-specific model home, or Appendix-Q tiny house construction within Tusayan town limits. Reviewed against the 2018 IRC and Coconino County Building Code Amendments and Standards (June 18, 2019) as adopted by the Town via Ordinance 2021-03. Applicants must first obtain the Town's Pre-Application Checklist endorsement; plan review and inspections are then performed by Coconino County Community Development (Building and Safety Division) via its Online Permit Applications portal, after which the Town of Tusayan issues the final signed building permit.

Verified 2026-07-07 · Source

When you need this permit

  • Town of Tusayan Pre-Application Checklist must be submitted and endorsed by the Town before applying for civil or building permit review; a pre-application meeting with the Town Manager is strongly recommended
  • Building permit required for new single-family dwelling, ADU, lot-specific model home, or tiny house (per IRC Appendix Q) construction within Tusayan town limits, per Zoning Code § 9.3(B) and Ordinance 2021-03
  • Plans must comply with the 2018 IRC and Coconino County Building Code Amendments and Standards (June 18, 2019), as adopted by reference by the Town
  • Submitted via Coconino County's Online Permit Applications portal (co-coconino-az.smartgovcommunity.com); only properly rotated, unlocked PDF files are accepted for electronic plan review
  • A geotechnical report (soils analysis) is recommended prior to submittal for new structures and may be required during the inspection process if not submitted upfront
  • If a complete set of plans meeting the County's minimum plan requirements is not received within ten working days of the submittal date, the permit application is canceled and must be re-submitted
  • Coordination with concurrent agencies is required as applicable: Coconino County Flood Control District, Tusayan Sanitary District (wastewater), Tusayan Fire District, Arizona State Fire Marshal, and Grand Canyon Unified School District
  • No construction may begin until the Town of Tusayan has issued its final signed building permit, even after County plan review/approval is complete

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 6 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Plan Review Deposit (New Single-Family Dwelling, Townhouse and Condominium, by size)Coconino County Building Permitting Fees schedule (effective 09/01/2021), Part II, Table I — the source PDF's deposit-tier dollar figures rendered with column misalignment on text extraction (a known artifact of this document's layout); the tiered-by-size deposit structure itself is confirmed, but exact per-tier dollar amounts should be re-confirmed directly against the live PDF or by phone (928-679-8850) before quoting a specific number
Deposit tiers apply by square footage (up to 1,000 sq ft; 1,000-2,500 sq ft; 2,500-5,000 sq ft; over 5,000 sq ft), collected at plan submittal and deducted from the total fee due at permit issuance
Building Permit Fee — Valuation-Based (Table II, ICC Building Valuation Data, or Table III, National Construction Estimator)Coconino County Building Permitting Fees schedule (effective 09/01/2021), Part I and Part II/Table III; the minimum fee for any single permit is $50.00 and all fees include the plan review fee unless a separate plan review fee is charged per Part I(D)
Calculated from building gross area x Square Foot Construction Cost (by occupancy group/construction type per 2018 IBC) x a 0.010 permit fee multiplier (Table II); or, per Table III's valuation bands: $79.00 for the first $500 (plus $4.24 per additional $100) up to $2,000; $142.68 for the first $2,000 (plus $28.00 per additional $1,000) up to $25,000; $786.85 for the first $25,000 (plus $20.19 per additional $1,000) up to $50,000; $1,291.77 for the first $50,000 (plus $13.98 per additional $1,000) up to $100,000; $1,991.17 for the first $100,000 (plus $11.20 per additional $1,000) up to $500,000; $6,471.49 for the first $500,000 (plus $9.49 per additional $1,000) up to $1,000,000; $10,787.59 plus $6.03 per additional $1,000 above $1,000,000
Plan Review FeeCoconino County Building Permitting Fees schedule (effective 09/01/2021), Part I, Section D — a separate fee in addition to the building permit fee itself; additional plan review (incomplete/changed plans) is billed at the rate specified in the fee schedule
65% of the calculated Building Permit Fee

Review timeline

Plan reviewTusayan’s published plan-review target
36–56 business days

How long did your Residential Building Permit (New Construction, incl. SFD / ADU / Tiny House) permit actually take in Tusayan?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation/Footing

    Before concrete pour; performed by Coconino County Building Inspectors under the Town-County IGA

  2. 2

    Framing

    Structural framing, connections, egress per 2018 IRC and Coconino County Building Code Amendments and Standards

  3. 3

    Final

    All work complete per approved plans; final inspection required before the Town of Tusayan will issue its final signed building permit / allow occupancy

See the full Tusayan inspection guide — scheduling & re-inspection fees →

Tips

  • Tusayan does not have its own building official or in-house plan-review staff — the actual technical review and inspections are performed by Coconino County under an intergovernmental agreement; the Town's role is the Pre-Application Checklist gatekeeping step at the front end and final permit issuance at the back end. Budget time for BOTH steps, not just the County's review.
  • Per Coconino County Community Development Substantive Policy 2025-01 (effective 4/28/25, updated 5/29/26), which SUPERSEDES the older June 2020 Permit Review Timeframes document this file previously cited: the governing timeline for Residential Building/Engineering permits is 36 days total (15 business days intake + 21 calendar days substantive review). However, the department own current homepage notice states that, due to staffing and permitting volume, Building and Engineering permits are currently on a 6-to-8-week (42-56 day) review timeline. This reviewTimelineDays range (36-56) reflects the formal 36-day policy target as the min and the department own published real-world ceiling (56 days = 8 weeks) as the max — both are governing, cited figures, not estimates. This 36-56 day range is the County process Tusayan contracts its plan review to; the Town own separate Pre-Application Checklist gatekeeping step at the front end is NOT included in this range — budget time for both steps.
  • If a building application remains administratively incomplete for 10 days, Coconino County denies it as incomplete and all deposits become non-refundable — get a complete submittal in on the first attempt.
  • Issued permits are valid for 180 days (resetting with each completed inspection); permits not picked up/paid for within 180 days of notification are deemed 'ABANDONED' per IRC § R105.3.2 as adopted.

Frequently asked questions

Tusayan requires a residential building permit (new construction, incl. sfd / adu / tiny house) for: Town of Tusayan Pre-Application Checklist must be submitted and endorsed by the Town before applying for civil or building permit review; a pre-application meeting with the Town Manager is strongly recommended; Building permit required for new single-family dwelling, ADU, lot-specific model home, or tiny house (per IRC Appendix Q) construction within Tusayan town limits, per Zoning Code § 9.3(B) and Ordinance 2021-03; Plans must comply with the 2018 IRC and Coconino County Building Code Amendments and Standards (June 18, 2019), as adopted by reference by the Town; Submitted via Coconino County's Online Permit Applications portal (co-coconino-az.smartgovcommunity.com); only properly rotated, unlocked PDF files are accepted for electronic plan review; A geotechnical report (soils analysis) is recommended prior to submittal for new structures and may be required during the inspection process if not submitted upfront; If a complete set of plans meeting the County's minimum plan requirements is not received within ten working days of the submittal date, the permit application is canceled and must be re-submitted; Coordination with concurrent agencies is required as applicable: Coconino County Flood Control District, Tusayan Sanitary District (wastewater), Tusayan Fire District, Arizona State Fire Marshal, and Grand Canyon Unified School District; No construction may begin until the Town of Tusayan has issued its final signed building permit, even after County plan review/approval is complete. If your project isn't listed, confirm with Town of Tusayan Engineering & Development (permit administration) with plan review and inspections performed by Coconino County Community Development Department, Building and Safety Division, under an intergovernmental agreement at 928-638-9909 (Town of Tusayan); 928-679-8850 (Coconino County Building and Safety) before starting work.

In Tusayan, the published Plan Review Deposit (New Single-Family Dwelling, Townhouse and Condominium, by size) is: Deposit tiers apply by square footage (up to 1,000 sq ft; 1,000-2,500 sq ft; 2,500-5,000 sq ft; over 5,000 sq ft), collected at plan submittal and deducted from the total fee due at permit issuance. Additional published fees: Building Permit Fee — Valuation-Based (Table II, ICC Building Valuation Data, or Table III, National Construction Estimator) — Calculated from building gross area x Square Foot Construction Cost (by occupancy group/construction type per 2018 IBC) x a 0.010 permit fee multiplier (Table II); or, per Table III's valuation bands: $79.00 for the first $500 (plus $4.24 per additional $100) up to $2,000; $142.68 for the first $2,000 (plus $28.00 per additional $1,000) up to $25,000; $786.85 for the first $25,000 (plus $20.19 per additional $1,000) up to $50,000; $1,291.77 for the first $50,000 (plus $13.98 per additional $1,000) up to $100,000; $1,991.17 for the first $100,000 (plus $11.20 per additional $1,000) up to $500,000; $6,471.49 for the first $500,000 (plus $9.49 per additional $1,000) up to $1,000,000; $10,787.59 plus $6.03 per additional $1,000 above $1,000,000; Plan Review Fee — 65% of the calculated Building Permit Fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Per Coconino County's official Permit Review Timeframes document (A.R.S. §§ 11-1604 to 11-1607), the county-side process for Residential Projects has a total timeframe of 63 days: a 15-business-day administrative completeness review followed by a 21-calendar-day substantive administrative/plan review, all of which the County document caps at 63 days overall (with the possibility of an applicant-agreed time extension for substantive plan review under A.R.S. § 11-1605(H)). This 63-day figure covers only the County's plan-review/inspection role — it does not include the separate, non-time-boxed Town of Tusayan Pre-Application Checklist endorsement step that must occur first, or the Town's final-signature step at the end.

You'll need: Town of Tusayan Pre-Application Checklist; Coconino County Building and Safety Application (HOUSE: SFD/ADU/Model Home/Tiny House Permit Information Sheet); Building Contractor Information Form; Utility Service Provider Acknowledgement (Building Permit Utility Sign Off Application); Site/Plot Plan; Construction Drawings and Structural Calculations. See the required-documents checklist on this page for details on each.

Tusayan requires 3 inspection(s) for a residential building permit (new construction, incl. sfd / adu / tiny house), in order: Foundation/Footing, Framing, Final. Schedule each through Town of Tusayan Engineering & Development (permit administration) with plan review and inspections performed by Coconino County Community Development Department, Building and Safety Division, under an intergovernmental agreement (928-638-9909 (Town of Tusayan); 928-679-8850 (Coconino County Building and Safety)).

Apply through Town of Tusayan Engineering & Development (permit administration) with plan review and inspections performed by Coconino County Community Development Department, Building and Safety Division, under an intergovernmental agreement at Town of Tusayan: 845 Mustang Drive / PO Box 709, Tusayan, AZ 86023. Coconino County Building and Safety Division: 2500 N. Fort Valley Road, Building 1, Flagstaff, AZ 86001. Phone: 928-638-9909 (Town of Tusayan); 928-679-8850 (Coconino County Building and Safety), email: tusayantownmanager@tusayan-az.gov (Town of Tusayan, for pre-application meetings); plansubmittals@coconino.az.gov (Coconino County Building and Safety). Office hours: Town of Tusayan Town Hall and Coconino County Building and Safety Division: Monday-Friday, 8:00 a.m.-5:00 p.m. Applicants must first submit a completed Pre-Application Checklist to the Town of Tusayan and are strongly encouraged to schedule a pre-application meeting with the Town Manager before beginning the permit process, because multiple agencies are typically involved. Building/civil plan review and inspections are then conducted by Coconino County via its Online Permit Applications portal (co-coconino-az.smartgovcommunity.com); once County review is complete, the Town of Tusayan issues the final signed building permit. Per the Town's own published guidance: 'No construction may begin until the Town has issued its final signed building permit.'. Official information: https://tusayan-az.gov/engineering-development/.

No. Tusayan adopted its own building-code ordinance (2021-03) but does not operate an independent, in-house plan-review/inspection staff. Building permit plan review and inspections for projects in Tusayan are performed by Coconino County Community Development (Building and Safety Division) under an intergovernmental agreement; the Town of Tusayan issues only the final signed building permit after County review is complete, and requires its own Pre-Application Checklist endorsement before that County review can begin.

The 2018 IRC and 2018 IBC (for any non-residential portions), plus the Coconino County Building Code Amendments and Standards dated June 18, 2019, all adopted by reference by the Town of Tusayan via Ordinance 2021-03 — the identical code baseline used by Coconino County itself.