Residential Rooftop Solar Photovoltaic (PV) Self-Issue Permit in Tusayan, Arizona

Coconino County (the agency that processes Tusayan building permits under the Town-County IGA) offers a Self-Issue Residential Rooftop Solar Permit for professional installations on rooftops of grid-tied properties. All other solar installations (e.g., ground-mount, off-grid) use the Residential Miscellaneous permit category. Applicable within Tusayan town limits subject to the statewide baseline of A.R.S. § 9-468.

Verified 2026-07-20 · Source

When you need this permit

  • Residential rooftop, grid-tied PV installations by a professional installer qualify for Coconino County's Self-Issue Residential Rooftop Solar Permit — a streamlined track bypassing full plan review
  • All other solar permits (ground-mount, off-grid, non-professional installs) must use the Residential Miscellaneous permit category instead
  • Must meet the minimum standards of Arizona Revised Statutes § 9-468 (Solar construction permits; standards; definition), the statewide baseline applicable to all Arizona municipalities including Tusayan
  • Town of Tusayan Pre-Application Checklist endorsement required before County-side review
  • Electrical work must comply with the 2017 NEC as adopted by the Town of Tusayan (Ordinance 2021-03)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Photovoltaic systems up to 10 kilowatt (kW)Coconino County Building Permitting Fees schedule (effective 09/01/2021), Table IV, Electrical section. RE-VERIFIED 2026-07-20 by fetching the live PDF and re-extracting text with reading order preserved (the earlier 'column misalignment' was an artifact of a different extraction mode) — the clean, unambiguous line reads 'Photovoltaic systems up to 10 kilowatt (kw) $75.00'. Applies to Tusayan permits, which Coconino County processes under the Town-County IGA.
$75.00
Photovoltaic systems over 10 kilowatt (kW)Coconino County Building Permitting Fees schedule (effective 09/01/2021), Table IV, Electrical section. RE-VERIFIED 2026-07-20 by direct re-extraction of the live PDF: 'Photovoltaic systems over 10 kilowatt (kw) $75.00 each plus $5.00 for each additional kw over 10'.
$75.00 each plus $5.00 for each additional kW over 10

Review timeline

Plan review
Not published — contact the department

How long did your Residential Rooftop Solar Photovoltaic (PV) Self-Issue Permit permit actually take in Tusayan?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final

    Panel mounting, racking attachment, roof penetration sealing, electrical connections, and interconnection point verified per 2017 NEC

See the full Tusayan inspection guide — scheduling & re-inspection fees →

Tips

  • Coconino County's 'Self-Issue' solar track is specifically for professional installations on rooftops of grid-tied properties — ground-mount systems, off-grid systems, or owner-installed systems do not qualify and must instead use the Residential Miscellaneous permit category (subject to the general 63-day Residential Projects review ceiling).
  • At minimum, Arizona municipalities including Tusayan must comply with A.R.S. § 9-468's baseline requirements for residential solar construction permits (plan content and review standards).
  • As with all Tusayan permits, the Town's Pre-Application Checklist step precedes County processing even for a self-issue solar permit.

Frequently asked questions

Tusayan requires a residential rooftop solar photovoltaic (pv) self-issue permit for: Residential rooftop, grid-tied PV installations by a professional installer qualify for Coconino County's Self-Issue Residential Rooftop Solar Permit — a streamlined track bypassing full plan review; All other solar permits (ground-mount, off-grid, non-professional installs) must use the Residential Miscellaneous permit category instead; Must meet the minimum standards of Arizona Revised Statutes § 9-468 (Solar construction permits; standards; definition), the statewide baseline applicable to all Arizona municipalities including Tusayan; Town of Tusayan Pre-Application Checklist endorsement required before County-side review; Electrical work must comply with the 2017 NEC as adopted by the Town of Tusayan (Ordinance 2021-03). If your project isn't listed, confirm with Town of Tusayan Engineering & Development (permit administration) with plan review and inspections performed by Coconino County Community Development Department, Building and Safety Division, under an intergovernmental agreement at 928-638-9909 (Town of Tusayan); 928-679-8850 (Coconino County Building and Safety) before starting work.

In Tusayan, the published Photovoltaic systems up to 10 kilowatt (kW) is: $75.00. Additional published fees: Photovoltaic systems over 10 kilowatt (kW) — $75.00 each plus $5.00 for each additional kW over 10. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Tusayan does not publish a plan-review timeline for this permit. Contact Town of Tusayan Engineering & Development (permit administration) with plan review and inspections performed by Coconino County Community Development Department, Building and Safety Division, under an intergovernmental agreement at 928-638-9909 (Town of Tusayan); 928-679-8850 (Coconino County Building and Safety) for current turnaround.

You'll need: Town of Tusayan Pre-Application Checklist; Coconino County Self-Issue Residential Rooftop Solar Permit application; PV Construction Plans (roof plan, elevation, racking/mounting details, electrical diagram). See the required-documents checklist on this page for details on each.

Tusayan requires 1 inspection(s) for a residential rooftop solar photovoltaic (pv) self-issue permit, in order: Final. Schedule each through Town of Tusayan Engineering & Development (permit administration) with plan review and inspections performed by Coconino County Community Development Department, Building and Safety Division, under an intergovernmental agreement (928-638-9909 (Town of Tusayan); 928-679-8850 (Coconino County Building and Safety)).

Apply through Town of Tusayan Engineering & Development (permit administration) with plan review and inspections performed by Coconino County Community Development Department, Building and Safety Division, under an intergovernmental agreement at Town of Tusayan: 845 Mustang Drive / PO Box 709, Tusayan, AZ 86023. Coconino County Building and Safety Division: 2500 N. Fort Valley Road, Building 1, Flagstaff, AZ 86001. Phone: 928-638-9909 (Town of Tusayan); 928-679-8850 (Coconino County Building and Safety), email: tusayantownmanager@tusayan-az.gov (Town of Tusayan, for pre-application meetings); plansubmittals@coconino.az.gov (Coconino County Building and Safety). Office hours: Town of Tusayan Town Hall and Coconino County Building and Safety Division: Monday-Friday, 8:00 a.m.-5:00 p.m. Applicants must first submit a completed Pre-Application Checklist to the Town of Tusayan and are strongly encouraged to schedule a pre-application meeting with the Town Manager before beginning the permit process, because multiple agencies are typically involved. Building/civil plan review and inspections are then conducted by Coconino County via its Online Permit Applications portal (co-coconino-az.smartgovcommunity.com); once County review is complete, the Town of Tusayan issues the final signed building permit. Per the Town's own published guidance: 'No construction may begin until the Town has issued its final signed building permit.'. Official information: https://tusayan-az.gov/engineering-development/.

Tusayan, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities, A.R.S. Title 11 for counties). The Town of Tusayan is a small (2020 Census population 561), recently incorporated (2010) gateway town that does NOT run an independent, self-staffed building department: it adopted its own local building-code ordinance but contracted the actual plan-review and inspection FUNCTION to Coconino County via an intergovernmental agreement (IGA), retaining only final permit issuance and pre-application/zoning gatekeeping in-house. Source: Town of Tusayan Engineering & Development page (tusayan-az.gov/engineering-development/) — 'Building permits are handled through an intergovernmental agreement with Coconino County... No construction may begin until the Town has issued its final signed building permit.'; Town of Tusayan Ordinance No. 2021-03 ('AN ORDINANCE OF THE COUNCIL OF THE TOWN OF TUSAYAN, ARIZONA, ADOPTING THE CODE OF TUSAYAN, ARIZONA, BUILDINGS AND CONSTRUCTION, UNIFORM CONSTRUCTION CODES ADOPTED, ADOPTION BY REFERENCE'), passed and adopted September 22, 2021, adopts by reference: International Building Code (IBC) 2018 Edition; International Residential Code (IRC) 2018 Edition; International Mechanical Code (IMC) 2018 Edition; International Fuel Gas Code (IFGC) 2018 Edition; International Plumbing Code (IPC) 2018 Edition; International Energy Conservation Code (IECC) 2018 Edition; International Existing Building Code (IEBC) 2018 Edition; International Swimming Pool and Spa Code (ISPSC) 2018 Edition; National Electrical Code (NEC) 2017 Edition (as published by the National Fire Protection Association); AND the Coconino County Building Code Amendments and Standards dated June 18, 2019 — all adopted by reference in full. This is the identical 2018 ICC suite / 2017 NEC combination that Coconino County's own Building Division uses countywide, confirming Tusayan's code baseline is deliberately harmonized with the County's rather than independently authored. Source: Town of Tusayan Ordinance No. 2021-03 (PDF, scanned/rendered and read directly, tusayan-az.gov/wp-content/uploads/2021/10/Ordinance-2021-03.pdf), Section I.; Ordinance 2021-03 also repeals and replaces Sections 1-10, Parts X-XII of the Coconino County Building Code Amendments and Standards (June 18, 2019) with a 'New Amendment: INNOVATIVE MATERIALS AND SYSTEMS PILOT PROGRAM, Sections 1-28' — mirroring Coconino County's own 'Innovative Materials and Systems Pilot Program' that allows owner-builders to seek an exemption from standard code provisions for alternative building methods/materials under certain circumstances. Source: Town of Tusayan Ordinance No. 2021-03, Section I; Coconino County Building Codes, Ordinances, Design Criteria page (coconino.az.gov/2391/Building-Codes-Ordinances-Design-Criteri), '2019-10 Coconino County Building Ordinance.'; As of July 2026, Coconino County's own Building Division still lists the 2018 International Code Council suite (IRC, IBC, IMC, IFGC, IPC, IECC, IEBC) plus the 2017 NEC as its CURRENT adopted codes (per the County's 'Current Codes and Ordinances' list), adopted via County Ordinance 2019-10. The County has begun a public process (open house held March 23, 2026) toward adopting the 2024 ICC suite and 2023 NEC, but as of this record's lastVerified date that update had NOT yet been formally adopted — the 2018/2017 baseline remains controlling for both the County and, by Ordinance 2021-03's adoption-by-reference, for Tusayan. Source: Coconino County Building Codes, Ordinances, Design Criteria page (coconino.az.gov/2391/Building-Codes-Ordinances-Design-Criteri), 'Current Codes and Ordinances' and 'Building Code Adoption' sections.; Town of Tusayan Zoning Code, Chapter 9, §9.3(B): 'A building permit, as required by the Building Code, shall be obtained prior to the construction, reconstruction, alteration or change in use of any building or other structure' — the Zoning Code's own building-permit trigger clause, applicable in the G (General), AR (Agricultural-Residential), and RR (Rural Residential) zones. Source: Town of Tusayan Zoning Code § 9.3, Property Development Standards: G, AR and RR Zones (codelibrary.amlegal.com/codes/tusayan/latest/tusayan_az_zone/0-0-0-3764).; Manufactured homes and factory-built buildings are licensed and permitted through a joint state/local structure: the Arizona Department of Fire, Building and Life Safety (Office of Manufactured Housing) sets manufacturer/installer/retailer licensing and issues State/IGA installation permits, while local site/foundation/utility compliance for a manufactured home placed within Tusayan town limits is handled through the same Town-Coconino County IGA building-permit pathway as other structures. Source: Coconino County Online Permit Applications page (coconino.az.gov/2390/Online-Permit-Applications), 'Manufactured Homes and Factory Built Projects' section; Coconino County Building Permitting Fees PDF, Part III, 'Manufactured Homes and Factory Built Building Permit Fees.'; Applicants must first submit a Pre-Application Checklist to the Town of Tusayan and receive the Town's endorsement before proceeding to civil or building permit review; the Town strongly encourages scheduling a pre-application meeting with the Town Manager given the number of agencies potentially involved (Coconino County Community Development, Coconino County Flood Control District, Tusayan Sanitary District, Tusayan Fire District, Arizona State Fire Marshal, Grand Canyon Unified School District). Source: Town of Tusayan Engineering & Development page; Town of Tusayan Pre-Application Checklist (tusayan-az.gov/wp-content/uploads/2025/10/Town-of-Tusayan-Pre-Applicaton-Checklist-103025.pdf).. Local amendments apply — see the Tusayan overview page for the full list.

Coconino County (which processes Tusayan's building permits under the Town-County intergovernmental agreement) offers a Self-Issue Residential Rooftop Solar Permit for professional installations on rooftops of grid-tied properties, bypassing full plan review. No exact published turnaround time was found for this specific self-issue track; other solar installations use the general Residential Miscellaneous permit category (63-day ceiling per the County's Permit Review Timeframes document). Confirm eligibility and current turnaround with Coconino County Building and Safety (928-679-8850).