EV Charger / EVSE Permit (Billed as General Electrical Permit) — El Mirage, Arizona · Requirements sheet
Verified 2026-07-20 · Source: https://www.elmirageaz.gov/291/Residential-Property-Improvements
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit (Billed as General Electrical Permit) in El Mirage, Arizona
Required for installation of a Level 2 (or higher) electric vehicle charger/EVSE in the City of El Mirage, governed by the 2017 National Electrical Code (NEC) as adopted and amended by the City. El Mirage has no dedicated EV-charger permit type, fee line, or checklist (unlike its dedicated PV System Permit Requirement Checklist for solar) — the City's own Residential Property Improvements page does not list EV chargers as a distinct improvement category, and the FY25-26 Adopted Fee Schedule has no EV-specific line item. An EV charger circuit is billed under the same Fees Based on Value (BOV) electrical permit schedule used for panel replacement/repair and other electrical work.
Verified 2026-07-20 · Source
When you need this permit
- Electrical permit required for the EV charger circuit installation, same as for other electrical repair/panel work
- Materials and installation must comply with the 2017 NEC (Article 625, Electric Vehicle Power Transfer System) as adopted and amended by the City of El Mirage
- Manufactured cut sheet for the EVSE unit/equipment required at submittal, following the same practice as panel/equipment permits
- Fees are based on the valuation of the project (BOV) and are due at the time of permit issuance
- No dedicated EV-charger checklist was found published — unlike the City's dedicated PV System Permit Requirement Checklist for solar, EV chargers are not called out as their own improvement category
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Electrical Rough (if concealed wiring)
Charger circuit wiring before concealment, if applicable
- 2
Clearance or Final
EVSE installed, GFCI/disconnect and connections verified per 2017 NEC Article 625 as amended
See the full El Mirage inspection guide — scheduling & re-inspection fees →
Tips
- El Mirage has no separate EV-charger fee line or checklist — a manufactured cut sheet for the EVSE unit is required at submittal, and the fee is calculated on the same valuation-based (BOV) electrical permit table used for panel replacement/repair.
- Unlike solar PV (which has a dedicated PV System Permit Requirement Checklist and PV System Inspection Checklist), EV chargers are not called out as their own improvement category on the City's Residential Property Improvements page — apply under the general Electrical Permit process.
- The same 10-15 business day review timeline verified for the general Electrical Permit applies, since EV charger work is processed under that same permit type.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the El Mirage building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in El Mirage
EV Charger / EVSE Permit (Billed as General Electrical Permit) in other cities
Compare ev charger / evse permit (billed as general electrical permit) fees across Arizona →
Look up this fee in a different city →