The Town of Gila Bend does not publish a separate Change-of-Use or Certificate-of-Occupancy permit application, fee line item, or submittal-checklist section — confirmed absent after full-text review of the Town's Fee Schedule, Building Plan Check Submittal Checklist, Turn Around Times document, and Building Safety FAQ. A Certificate of Occupancy is issued as the closing step of whichever underlying building permit governs the work (New Building (Non-Residential), Tenant Improvements, etc.), under the administrative provisions of the 2006 IBC adopted by reference (§ 150.15), which require a Certificate of Occupancy before a building or structure may be used or occupied and whenever the use or occupancy classification changes. This is an honest 'no distinct permit product' finding, not an omission: Gila Bend is a small town whose Community Development function is limited to the general Building Permit Application process administered through Willdan Engineering, with no dedicated CO/change-of-use intake track.

Reviewed 2026-07-23 · Source

When you need this permit

  • No dedicated Change-of-Use or Certificate-of-Occupancy permit application is published by the Town; a change in use or occupancy of an existing building is processed through whichever underlying permit track applies to the proposed work — Tenant Improvements or New Building (Non-Residential) on the Building Plan Check Submittal Checklist (rev. 8.6.16), or the applicable MEP-only track if the change is limited to systems work
  • Per the 2006 IBC as adopted by the Town (§ 150.15), a Certificate of Occupancy is required before a building, structure, or portion thereof may be lawfully used or occupied, and a new Certificate of Occupancy is required whenever the use or occupancy classification of a building changes
  • Per the Town's Zoning Ordinance § 16-5-07(A)(2) (Off-Street Parking Requirements), any change of use or occupancy of a building, including additions, that requires additional off-street parking is not permitted until the additional required parking spaces are furnished — this is a zoning-compliance condition attached to the underlying permit, not a separate standalone permit product
  • Other permit-type entries in this jurisdiction file already reference the Certificate of Occupancy as the closing step of the standard permit/inspection process (e.g., the plumbing-permit entry notes backflow-preventer certified testing 'prior to Certificate of Occupancy if required'), consistent with there being no separate CO permit product distinct from the underlying building permit's final inspection

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

No distinct Certificate-of-Occupancy or Change-of-Use feeThe underlying permit's Building Permit Fee (valuation-based) and Building Plan Review fee (65% of permit fee) apply instead, per the Town of Gila Bend Fee Schedule (last confirmed-amended 06/07/16, on file 5/14/18)
Not applicable as a standalone line item — confirmed absent from the Town's Fee Schedule after full-text search

Review timeline

Plan review
Not published — contact the department

How long did your Certificate of Occupancy / Change of Use permit actually take in Gila Bend?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Inspection (Certificate of Occupancy)

    Verifies compliance with Building, Electrical, Plumbing, and Mechanical Code requirements, approved plans, and zoning conditions (including any additional off-street parking triggered by the change of use) before the Certificate of Occupancy is issued

See the full Gila Bend inspection guide — scheduling & re-inspection fees →

Tips

  • Gila Bend has no dedicated Certificate of Occupancy or Change of Use permit product — this was confirmed as a genuine gap after exhausting the Fee Schedule, Building Plan Check Submittal Checklist, Turn Around Times document, and Building Safety FAQ, rather than assumed. A change of use should instead be submitted through the Tenant Improvements or New Building (Non-Residential) track matching the scope of work involved.
  • A change of use or occupancy that increases required off-street parking cannot proceed until the additional parking spaces are furnished, per Zoning Ordinance § 16-5-07(A)(2) — confirm parking-count impacts with Community Development/Willdan Engineering early in planning a change of use.
  • Because Gila Bend's Building Safety plan review and inspections are administered under contract by Willdan Engineering, confirm current Certificate of Occupancy issuance practice directly with Willdan (BuildingSafetyAZ@willdan.com, 480-489-2463) for any change-of-use project, since no Town-published document details the administrative issuance steps beyond the underlying permit's final inspection.

Frequently asked questions

Gila Bend requires a certificate of occupancy / change of use permit for: No dedicated Change-of-Use or Certificate-of-Occupancy permit application is published by the Town; a change in use or occupancy of an existing building is processed through whichever underlying permit track applies to the proposed work — Tenant Improvements or New Building (Non-Residential) on the Building Plan Check Submittal Checklist (rev. 8.6.16), or the applicable MEP-only track if the change is limited to systems work; Per the 2006 IBC as adopted by the Town (§ 150.15), a Certificate of Occupancy is required before a building, structure, or portion thereof may be lawfully used or occupied, and a new Certificate of Occupancy is required whenever the use or occupancy classification of a building changes; Per the Town's Zoning Ordinance § 16-5-07(A)(2) (Off-Street Parking Requirements), any change of use or occupancy of a building, including additions, that requires additional off-street parking is not permitted until the additional required parking spaces are furnished — this is a zoning-compliance condition attached to the underlying permit, not a separate standalone permit product; Other permit-type entries in this jurisdiction file already reference the Certificate of Occupancy as the closing step of the standard permit/inspection process (e.g., the plumbing-permit entry notes backflow-preventer certified testing 'prior to Certificate of Occupancy if required'), consistent with there being no separate CO permit product distinct from the underlying building permit's final inspection. If your project isn't listed, confirm with Town of Gila Bend Community Development — Building and Safety Division (building safety/plan review/inspections contracted to Willdan Engineering) at 928-235-6362 (Community Development); 480-489-2463 (Willdan Engineering, building safety/inspections) before starting work.

In Gila Bend, the published No distinct Certificate-of-Occupancy or Change-of-Use fee is: Not applicable as a standalone line item — confirmed absent from the Town's Fee Schedule after full-text search. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Gila Bend does not publish a plan-review timeline for this permit. Contact Town of Gila Bend Community Development — Building and Safety Division (building safety/plan review/inspections contracted to Willdan Engineering) at 928-235-6362 (Community Development); 480-489-2463 (Willdan Engineering, building safety/inspections) for current turnaround.

You'll need: Building Permit Application / Project Submittal Form for the underlying scope of work. See the required-documents checklist on this page for details on each.

Yes — if the new use requires more off-street parking than the prior use, Zoning Ordinance § 16-5-07(A)(2) prohibits the change from proceeding until the additional required parking spaces are furnished, in addition to whatever building-code work the change itself requires.

Apply through Town of Gila Bend Community Development — Building and Safety Division (building safety/plan review/inspections contracted to Willdan Engineering) at 644 W. Pima St., P.O. Box A, Gila Bend, AZ 85337. Phone: 928-235-6362 (Community Development); 480-489-2463 (Willdan Engineering, building safety/inspections), email: planning@gilabendaz.org (Community Development); BuildingSafetyAZ@willdan.com (Willdan Engineering, building safety/permit/inspection questions). Office hours: Monday - Friday, 8:00 a.m. - 4:00 p.m. Building plan review, permit issuance, and inspections are administered under contract by Willdan Engineering; the Town's Community and Economic Development office handles zoning/planning intake at the same address.. Official information: https://www.gilabendaz.org/279/Building-and-Safety.

Gila Bend, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-municipality authority under state enabling statutes (A.R.S. Title 9). The Town of Gila Bend adopts and administers its own construction codes through its Community Development Building and Safety Division, which contracts building-safety plan review and inspection services to Willdan Engineering; the Town does not defer permitting to Maricopa County. Source: Town of Gila Bend Code of Ordinances, Chapter 150 (Building Regulations; Construction) and Town of Gila Bend Building and Safety page (gilabendaz.org/279/Building-and-Safety).; 2006 International Building Code (IBC), copyrighted by the International Code Council, adopted by reference as the "Building Code of the Town of Gila Bend" (Gila Bend Code of Ordinances § 150.15; 1996 Code, § 15.08.010; Ord. 95-010-005; Ord. 01-03; Ord. 08-02). At least three copies are required to be filed with the Town Clerk. No adoption of a later ICC edition (e.g., 2018/2021 IBC) was found in the current codified ordinances as of this review — the 2006 edition remains the codified baseline.; 2005 National Electrical Code (NEC), copyrighted by the National Fire Protection Association, adopted by reference as the "Electrical Code for the Town of Gila Bend" (§ 150.16; 1996 Code, § 15.12.010; Ord. 95-010-005; Ord. 01-03; Ord. 08-02).; 2006 International Mechanical Code (IMC), adopted by reference as the "Mechanical Code for the Town of Gila Bend" (§ 150.17; 1996 Code, § 15.16.010; Ord. 95-010-005; Ord. 01-03; Ord. 08-02).; 2006 International Plumbing Code (IPC), adopted by reference as the "Plumbing Code for the Town of Gila Bend" (§ 150.18; 1996 Code, § 15.20.010; Ord. 95-010-005; Ord. 01-03; Ord. 08-02).; 2006 International Fire Code (IFC), adopted by reference and codified under the heading "Uniform Code for the Abatement of Dangerous Buildings" as the "Fire Code for the Town of Gila Bend" (§ 150.19; 1996 Code, § 15.24.010; Ord. 95-010-005; Ord. 08-02).; 2006 International Residential Code (IRC), copyrighted by the International Code Council, adopted by reference as the "Residential Code for the Town of Gila Bend," with a local amendment to IRC Chapter 23 / Section M2301 (Residential Solar Readiness — solar energy systems) (§ 150.20; Ord. 10-12, passed 10-26-2010).; Building permit valuations for fee purposes are determined using the most current building valuation data table published by the International Code Council in Building Safety Journal magazine, as republished from time to time; any valuation not specifically covered is classified by the Building Official by nearest-resembling use/construction type (§ 150.03; Ord. 09-02, passed 2-10-2009). The Town's own Fee Schedule (last confirmed amendment 06/07/16, on file as of 5/14/18) also states valuations are calculated per the 2006 IBC square-foot construction cost tables.; Buildings must conform to the Town's zoning ordinance in addition to Chapter 150 whenever a building permit is issued and inspected (§ 150.01; 1996 Code, § 15.04.010).; The Building Official function (all building, plumbing, electrical, or other inspection matters referenced anywhere in Chapter 150) is vested in the office of the Town Clerk, with Council-authorized deputies as needed (§ 150.02; 1996 Code, § 15.04.020) — in current practice this function is carried out through the Community Development Department's contract with Willdan Engineering.; Manufactured homes and factory-built buildings ("on-site permits") are separately regulated: manufactured home permits require 3 plot plans (8.5x11) and zoning clearance; factory-built buildings require 2 complete plan sets bearing approval of the Arizona State Division of Building Codes. Source: Town of Gila Bend Building Plan Check Submittal Checklist (rev. 8.6.16).. Local amendments apply — see the Gila Bend overview page for the full list.

No. The Town does not publish a distinct Change-of-Use or Certificate-of-Occupancy application, fee, or checklist section. A Certificate of Occupancy is issued as the final-inspection step of whichever underlying building permit (Tenant Improvements, New Building (Non-Residential), etc.) governs the proposed change, under the administrative provisions of the 2006 IBC as adopted by the Town (§ 150.15).