EV Charger / Electric Vehicle Charging Station Permit — Glendale, Arizona · Requirements sheet
Verified 2026-07-20 · Source: https://www.glendaleaz.gov/Business/Building-Safety-Codes-Services/Building-Permits/Fee-Schedule
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / Electric Vehicle Charging Station Permit in Glendale, Arizona
The City of Glendale's Community Development Fee Schedule (effective 5/10/2019, still the current posted schedule) has no dedicated 'EV charger,' 'EVSE,' or 'electric vehicle' line item -- unlike solar PV, which has its own submittal checklist and is billed via the same itemized Electric Permit fee table. Installing a Level 2 (240V) home or commercial EV charging station requires a standard City of Glendale Electric Permit, billed under the fee schedule's per-component residential electrical items (base permit fee plus whichever of sub-panel, service-upgrade, or miscellaneous-circuit fees apply to the specific job), governed by NEC Article 625 (Electric Vehicle Power Transfer System) as adopted via the 2023 NEC.
Verified 2026-07-20 · Source
When you need this permit
- A City of Glendale Electric Permit is required for installation of a Level 2 (240V, 50A+) EV charging circuit or dedicated EVSE branch circuit; per Arizona statewide practice and NEC Article 625 as adopted with the City's 2023 NEC, any new dedicated EV charger circuit requires electrical permitting and inspection
- If the installation requires a new sub-panel, the fee schedule's flat Sub Panel fee applies in addition to the Electric Permit base fee
- If the installation requires an electrical service upgrade (e.g., upsizing to accommodate charger load), the amperage-based Electrical Service fee tiers (200A or less vs. over 200A) apply instead of/in addition to the base fee
- If a utility clearance is required to energize new service for the charger, the Electrical Clearance fee applies
- Multi-family or commercial EV charging installations may require full plan review (one-line diagram, load calculation, site layout) rather than an over-the-counter residential permit -- coordinate with Development Services and, for service capacity questions, Glendale's utility provider (APS or SRP, depending on the parcel; Glendale itself does not operate the electric utility, unlike its water utility)
- No dedicated EV-charger submittal checklist analogous to the City's Residential Photovoltaic System Submittal Checklist was found published; applicants should use the standard residential electrical permit submittal process
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Electrical Inspection
City of Glendale inspector verifies the new circuit, breaker sizing, disconnect (if required), and NEC Article 625 compliance before the charger is energized
See the full Glendale inspection guide — scheduling & re-inspection fees →
Tips
- Glendale's fee schedule has no EV-charger-specific line item, unlike solar PV which has its own dedicated submittal checklist -- an EV charger circuit is billed through the same itemized Electric Permit components (base fee, sub-panel, service upgrade) used for any other new residential circuit or panel work.
- If your existing panel has spare capacity for a new 240V circuit, budget for just the base Electric Permit fee plus inspection; if a panel upgrade or new service is needed, budget for the amperage-based service fee tiers instead.
- Glendale (AZ) does not operate the electric utility for most of the city -- APS or SRP territory depends on the specific parcel, so utility-side coordination (metering, clearance) is separate from the City permit itself.
- This differs from City of Glendale, California entirely -- confirm you are working with City of Glendale, Arizona's Development Services and glendaleaz.gov, not glendaleca.gov.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Glendale building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Glendale
EV Charger / Electric Vehicle Charging Station Permit in other cities
Compare ev charger / electric vehicle charging station permit fees across Arizona →
Look up this fee in a different city →