Demolition Permit in Guadalupe, Arizona

Required for demolition of any structure in the Town of Guadalupe. The Town's Building Permit Application has a dedicated Demolition section (# of Structures, Sewer cap off).

Verified 2026-07-06 · Source

When you need this permit

  • Building permit required before demolishing a structure within Town limits; the Town's Building Permit Application has a dedicated Demolition section with '# of Structures' and 'Sewer cap off' fields
  • Demolition plans, where applicable, are part of the plan submittal requirements described on the Town's Plan Review / Inspections page
  • Governed generally by the 2012 UBC and the Uniform Code for the Abatement of Dangerous Buildings, most current edition, as adopted by the Town (Town Code § 150.01, § 150.18)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Based on Valuation (same table as new construction)Town of Guadalupe Building Permit Application, attached Fee Schedule exhibit, 'ADOPTED April 23, 2020' — no separate flat demolition fee is published; fees are computed from contract valuation
$50 minimum (valuation $1-$500), scaling per the Town's valuation-based Building Permit Fee table

Review timeline

Plan review
Not published — contact the department

How long did your Demolition Permit permit actually take in Guadalupe?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final

    Verifies demolition complete, utilities/sewer properly capped off; scheduled with the Building Inspector with 2-3 business days' notice

See the full Guadalupe inspection guide — scheduling & re-inspection fees →

Tips

  • As of July 2026, the Town of Guadalupe does not appear to publish permit-specific plan review turnaround times for demolition permits on its public website. The Town publishes a general plan-review timeline (approximately 1-2 weeks initial review, 4-6 weeks for complex full plan review) on its Plan Review / Inspections page, but does not break this out by permit type, and demolition (being typically simpler than new construction) is not separately itemized in either direction. There is no verifiable online source specifically stating a demolition-permit timeline — call the Town of Guadalupe Building Inspector directly at 480-505-5370 to confirm expected turnaround for a specific demolition project.
  • The Town's own Building Permit Application form has a dedicated Demolition section (# of Structures, Sewer cap off), confirming demolition permits are a real, actively-issued permit category — only the review-timeline figure is unverified for this specific type.

Frequently asked questions

Yes — the Town's Building Permit Application has a dedicated Demolition section requiring the number of structures and whether a sewer cap-off is needed.

In Guadalupe, the published Building Permit Fee — Based on Valuation (same table as new construction) is: $50 minimum (valuation $1-$500), scaling per the Town's valuation-based Building Permit Fee table. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

As of July 2026, the Town of Guadalupe does not publish a demolition-specific review timeline. The Town's general published range (1-2 weeks initial review, up to 4-6 weeks for complex projects) applies to plan review generally, but is not broken out by permit type. Call the Building Inspector at 480-505-5370 to confirm timing for a specific demolition project.

You'll need: Permit Application (Town of Guadalupe Building Safety Department). Depending on your project, Guadalupe may also ask for: Demolition Plans. See the required-documents checklist on this page for details on each.

Guadalupe requires 1 inspection(s) for a demolition permit, in order: Final. Schedule each through Town of Guadalupe Building Safety Department / Building Inspector (480-505-5370).

Apply through Town of Guadalupe Building Safety Department / Building Inspector at 9241 S. Avenida del Yaqui, Guadalupe, AZ 85283. Phone: 480-505-5370, email: binspector@guadalupeaz.org. Office hours: Town Hall: Monday - Friday, 8 a.m. - 5 p.m. Completed Building Permit Applications and three (3) sets of plans may be submitted in person at the Town Hall front office or emailed to the Building Inspector at binspector@guadalupeaz.org. Note: the current Building Inspector of record on the Town's live website (guadalupeaz.org) is Bill Hedrix — this supersedes the 2025 Arizona Building Officials (AZBO) Directory listing of a prior inspector, which appears out of date.. Official information: https://www.guadalupeaz.org/1214/Building-Construction-Planning-Zoning.

Guadalupe, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/town authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The Town of Guadalupe is a small incorporated town (population approx. 5,000-5,500) that independently adopts and administers its own construction codes through its Building Safety Department / Building Inspector; it does not defer permitting to Maricopa County. Source: Town of Guadalupe Code of Ordinances, Chapter 150 (Building Codes), via American Legal Publishing code library (codelibrary.amlegal.com/codes/guadalupe), current through Ordinance O2024.02 (passed 11-14-2024) — Chapter 150 itself was last substantively amended by Ord. O2020.08 and O2020.19 (both passed 4-23-2020).; Uniform Building Code, 2012 Edition (UBC 2012), as published by the International Conference of Building Officials, adopted by reference as the Town's Uniform Building Code (Town Code § 150.01(A)). This is notably an older code family (Uniform Codes, not the newer International Codes / ICC family used by most other Maricopa County cities) — confirmed current as of the live Town Code, not merely a stale directory listing. Source: Town of Guadalupe Code of Ordinances § 150.01, ADOPTION OF BUILDING CODE (1989 Code, § 7-1-1; Ord. 2001-01, passed 1-25-2001; Ord. 2006-01, passed 3-9-2006; Ord. 2012-02, passed 7-27-2012; Ord. O2020.08, passed 4-23-2020; Ord. O2020.19, passed 4-23-2020).; National Electrical Code, 2011 Edition (NEC 2011), as published by the National Fire Protection Association, adopted by reference as the Town's Electrical Code (Town Code § 150.15). Source: Town of Guadalupe Code of Ordinances § 150.15 (1989 Code, § 7-2; Ord. 2001-01, passed 1-25-2001; Ord. O2020.08, passed 4-23-2020).; Uniform Mechanical Code, 2012 Edition (UMC 2012), as published by the International Conference of Building Officials, adopted by reference as the Town's Mechanical Code (Town Code § 150.16). Source: Town of Guadalupe Code of Ordinances § 150.16 (1989 Code, § 7-3; Ord. 2001-01, passed 1-25-2001; Ord. O2020.08, passed 4-23-2020).; Uniform Plumbing Code, 2012 Edition (UPC 2012), as published by the International Conference of Building Officials, adopted by reference as the Town's Plumbing Code (Town Code § 150.17). Source: Town of Guadalupe Code of Ordinances § 150.17 (1989 Code, § 7-4; Ord. 2001-01, passed 1-25-2001; Ord. O2020.08, passed 4-23-2020).; Uniform Code for the Abatement of Dangerous Buildings, most current edition, adopted by reference (Town Code § 150.18); three copies on file with the Town Manager/Clerk, made a public record by Resolution 95-17. Source: Town of Guadalupe Code of Ordinances § 150.18 (1989 Code, § 7-7; Ord. 95-02, passed 8-24-1995; Res. 95-17, passed 8-24-1995; Ord. O2020.08, passed 4-23-2020).; The building official / administrative authority for all building, plumbing, electrical, or other inspections under Chapter 150 is vested in the office of the Town Manager, who may authorize deputies (in practice, the Building Inspector) to perform inspection work. Source: Town of Guadalupe Code of Ordinances § 150.19, BUILDING OFFICIAL (1989 Code, § 7-5).; Manufactured homes, mobile homes, modular buildings, and recreational vehicles are separately regulated under Town Code § 150.21 (Dwelling Unit Standards), which incorporates federal manufactured-housing construction standards (National Manufactured Home Construction and Safety Standards Act of 1974) and imposes Town-specific siting, foundation, and occupancy rules; manufactured home placement additionally requires a Conditional Use Permit from the Town Council (approx. 60-day process, $50 application fee, $25 continuance fee) before a building permit can issue. Source: Town of Guadalupe Code of Ordinances § 150.21; Town of Guadalupe Manufactured Home Requirements (rev. 02/07/2020).. Local amendments apply — see the Guadalupe overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Guadalupe building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.