Electric Vehicle (EV) Charger / EVSE Permit — Chino Valley, Arizona · Requirements sheet
Verified 2026-07-20 · Source: https://www.chinovalleyaz.gov/200/Building
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Electric Vehicle (EV) Charger / EVSE Permit in Chino Valley, Arizona
The Town of Chino Valley has no dedicated EV charger/EVSE permit type or fee line -- confirmed directly against the Town's Consolidated Fee Schedule (effective 03-01-2026) and Building Division page, neither of which contain an EV-specific application, checklist, or fee. An EVSE circuit installation is billed under the Town's flat-rate Electrical Permit fee, governed by the 2023 National Electrical Code as adopted (Chino Valley Town Code Section 150.004).
Verified 2026-07-20 · Source
When you need this permit
- Electrical permit required for EVSE circuit installation, alteration, or repair work in the Town of Chino Valley
- Governed by the 2023 National Electrical Code (NFPA 70) as adopted and amended as the Town's standalone electrical code (Town Code Section 150.004)
- No EV-charger-specific application, checklist, or fee line was located; apply using the Town's standard electrical permit process
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Electrical Inspection
Town electrical inspection of the EVSE circuit and connection, consistent with the general electrical-permit inspection process
See the full Chino Valley inspection guide — scheduling & re-inspection fees →
Tips
- Chino Valley bills EV charger/EVSE installs under the same flat $110.00 Electrical Permit fee used for any other electrical-only scope -- no separate application or checklist exists.
- Budget the 65% Plan Review Fee on top of the $110.00 base electrical fee.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Chino Valley building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Chino Valley
Electric Vehicle (EV) Charger / EVSE Permit in other cities
Compare electric vehicle (ev) charger / evse permit fees across Arizona →
Look up this fee in a different city →
Related guides
Now live
Build your Chino Valley project checklist
Describe your project once and get every permit, document, and fee it triggers in Chino Valley — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →