Required for plumbing installation, alteration, or repair work in Jerome, governed by the 2012 International Plumbing Code (IPC), including Appendices B, C, D, and E, as adopted by the Town (Resolution 547).

Verified 2026-07-07 · Source

When you need this permit

  • Plumbing permit required for installation, alteration, or repair of plumbing systems and fixtures
  • Governed by the 2012 IPC as adopted by the Town of Jerome (Resolution 547), including Appendices B, C, D, and E
  • Combination permits covering plumbing, electrical, or mechanical trades together are available for valuations up to $3,000 at a flat per-trade rate; above $3,000, the general Valuation and Fee Schedule applies
  • Additional application forms may be required for septic and public works per the Building Permit Application

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Combination Permit (plumbing, electrical, or mechanical), valuation up to $3,000Town of Jerome Official Fee Schedule, Schedule A-1
$50.00 for each trade
Combination Permit (plumbing, electrical, or mechanical), valuation over $3,000Town of Jerome Official Fee Schedule, Schedule A-1
Use Valuation and Fee Schedule

Review timeline

Plan review
Not published — contact the department

How long did your Plumbing Permit permit actually take in Jerome?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In

    After pipes installed, before walls closed

  2. 2

    Final

    Fixtures connected, no leaks, per 2012 IPC

See the full Jerome inspection guide — scheduling & re-inspection fees →

Tips

  • Septic systems require additional application forms beyond the standard Building Permit Application, per the Town's own Building Permit Application instructions — confirm with Yavapai County Environmental Services whether septic permitting itself is a County, not Town, function, as is common elsewhere in Yavapai County.
  • No itemized per-fixture plumbing fee table (comparable to Cottonwood's or Buckeye's per-water-heater dollar figures) is published in Jerome's Fee Schedule; plumbing work is billed either via the flat $50/trade combination-permit rate (valuation up to $3,000) or the general Valuation and Fee Schedule above that threshold.

Frequently asked questions

Jerome requires a plumbing permit for: Plumbing permit required for installation, alteration, or repair of plumbing systems and fixtures; Governed by the 2012 IPC as adopted by the Town of Jerome (Resolution 547), including Appendices B, C, D, and E; Combination permits covering plumbing, electrical, or mechanical trades together are available for valuations up to $3,000 at a flat per-trade rate; above $3,000, the general Valuation and Fee Schedule applies; Additional application forms may be required for septic and public works per the Building Permit Application. If your project isn't listed, confirm with Town of Jerome Building Department (Planning & Zoning Dept.) — Building Inspector at 928-634-7943 before starting work.

For combined trade work (plumbing bundled with electrical and/or mechanical) valued up to $3,000, the fee is a flat $50.00 per trade. Above $3,000 in valuation, the plumbing permit is billed per the Town's general Valuation and Fee Schedule (Schedule A-1). No separate itemized per-fixture plumbing fee table was found in the Town's published Fee Schedule.

Jerome does not publish a plan-review timeline for this permit. Contact Town of Jerome Building Department (Planning & Zoning Dept.) — Building Inspector at 928-634-7943 for current turnaround.

You'll need: Building/Plumbing Permit Application; Plumbing Plan. See the required-documents checklist on this page for details on each.

Jerome requires 2 inspection(s) for a plumbing permit, in order: Rough-In, Final. Schedule each through Town of Jerome Building Department (Planning & Zoning Dept.) — Building Inspector (928-634-7943).

Apply through Town of Jerome Building Department (Planning & Zoning Dept.) — Building Inspector at 600 Clark Street, P.O. Box 335, Jerome, AZ 86331. Phone: 928-634-7943, email: b.wolstencroft@jerome.az.gov. Office hours: Town Hall: Monday - Thursday, 8:00 a.m. to 5:00 p.m. Building Inspector: Barry Wolstencroft (b.wolstencroft@jerome.az.gov, 928-634-7943, fax 928-634-0715). Building permit applications are filed at Town Hall (PO Box 335 / 600 Clark St.) only AFTER the project has received required approval from the Design Review Board and/or Zoning Administrator; inspections are scheduled approximately one week in advance and the Town states it is not liable for work delays due to inspection scheduling.. Official information: https://jerome.az.gov/building-inspection.

Jerome, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). Despite its very small size (population approximately 450), the Town of Jerome runs its own genuinely independent Building Department with a named Building Inspector (Barry Wolstencroft), its own adopted code chapter (Town Code Chapter 7, Building and Safety Codes), and its own Council-adopted fee schedule (Schedule A-1) — it does NOT defer building-permit administration to Yavapai County. Source: Town of Jerome Building Inspection page (jerome.az.gov/building-inspection) and Building Codes page (jerome.az.gov/building-codes).; 2012 International Building Code (IBC), adopted by Resolution 544. Source: Town of Jerome Building Codes page (jerome.az.gov/building-codes).; 2012 International Residential Code for One- and Two-Family Dwellings (IRC), adopted by Resolution 545. Source: Town of Jerome Building Codes page.; 2012 International Plumbing Code (IPC), including Appendices B, C, D, and E, adopted by Resolution 547. Source: Town of Jerome Building Codes page.; 2011 National Electrical Code (NEC), adopted by Resolution 548 — notably TWO editions behind the electrical-code cycle used by most other AZ jurisdictions reviewed in this dataset (which have generally moved to the 2023 NEC); confirmed as currently listed on the Town's own Building Codes page, not assumed. Source: Town of Jerome Building Codes page.; 2012 International Mechanical Code (IMC), adopted by Resolution 546. Source: Town of Jerome Building Codes page.; 2012 International Fuel Gas Code (IFGC), including Appendices A, B, C, and D, adopted by Resolution 549. Source: Town of Jerome Building Codes page.; 2012 International Property Maintenance Code (IPMC), adopted by Resolution 550 and Ordinance 430. Source: Town of Jerome Building Codes page.; Appendix 33 of the 1997 Uniform Building Code (UBC), serving as the Town's Grading Ordinance, adopted by Ordinance 358. Source: Town of Jerome Building Codes page.; Town of Jerome Administrative Code (2003 Edition), adopted by Ordinance 358 — governs local permit administration provisions layered on top of the ICC codes (e.g., the Section 108.8 reinspection-fee citation used in the Town's own Fee Schedule). Source: Town of Jerome Building Codes page.; 2018 International Fire Code (IFC), adopted by Resolution 635 — notably a much newer edition than the 2012-vintage building/residential/plumbing/mechanical/fuel-gas code set, and the only code in Jerome's adopted set current within the last decade. Source: Town of Jerome Building Codes page.; IMPORTANT — Historic Overlay District (Jerome Zoning Ordinance Section 511.C): the Historic Overlay District boundary 'shall include all areas within the corporate limits of the Town of Jerome' — i.e., the ENTIRE town is inside the Historic Overlay District, not just a subset of downtown parcels. As a result, Design Review Board (or, for minor listed items, Zoning Administrator) approval under Zoning Ordinance Section 304 is a mandatory prerequisite BEFORE a building permit application can even be submitted to the Building Inspector, for nearly every exterior construction project Town-wide. Source: Jerome Zoning Ordinance (current through July 2024), Sections 304 and 511 (jerome.az.gov/documents/76/Zoning_Ordinance_updated_thru_July_2024.pdf); Building Permit Application Packet ('We provide the following information to assist you in applying for a permit once the Design Review Board has approved your project.').. Local amendments apply — see the Jerome overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-07.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Jerome building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.