Residential Building Permit (New Construction) in Jerome, Arizona
Required for new single-family and two-family dwelling construction in the Town of Jerome. Reviewed against the 2012 IRC as adopted by the Town. Because the entire town lies within the Historic Overlay District, new construction must first receive Design Review Board approval (Zoning Ordinance Section 304) before a building permit application can be submitted to the Building Inspector.
Verified 2026-07-07 · Source
When you need this permit
- Design Review Board approval required BEFORE building permit submittal — the Historic Overlay District covers the Town's entire corporate limits (Zoning Ordinance Section 511.C), and 'new structures' are explicitly listed among projects requiring full Board review (Section 304.B.6)
- Building permit application, plot plan (drawn to scale, showing existing structures, north arrow, general slope of land, distances between buildings), Valid Contractor's License form (or Owner-Builder/Owner-Developer exemption statement under A.R.S. § 32-1121), and Plan Approval Agreement must be filed with the Building Inspector after Design Review approval Owner-builderContractor
- Two sets of full building plans required, minimum 18-by-24-inch paper, 1/4-inch-per-foot scale, showing floor plan, electrical plan, foundation plan, floor framing plan, roof framing layout, and a cross-section of materials from foundation through roof
- Plans reviewed against the 2012 IRC (Resolution 545) and 2012 IBC (Resolution 544) as adopted by the Town
- Progress requiring an inspection must occur at least every six months or the permit becomes invalid
- Commercial zoning requires commercially licensed contractors; owner-occupants may self-perform under the A.R.S. § 32-1121 Item 5 owner-builder exemption if the structure is not for sale/rent within one year Owner-builderContractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 6 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation/Footing
Before concrete pour
- 2
Framing
Structural framing per approved plans and 2012 IRC
- 3
Progress Inspection (6-month minimum)
An inspection showing construction progress must occur at least every six months or the permit becomes invalid; inspections are scheduled approximately one week in advance
- 4
Final
All work complete per approved plans
See the full Jerome inspection guide — scheduling & re-inspection fees →
Tips
- Because the Historic Overlay District covers the Town's ENTIRE corporate limits (Zoning Ordinance Section 511.C), Design Review Board approval is required before you can even submit a building permit application for new construction — plan for this as a separate, sequential front-end approval step, not a parallel or optional one. The Building Permit Application Packet states plainly: 'We provide the following information to assist you in applying for a permit once the Design Review Board has approved your project.'
- The only numerically published Jerome review-timeframe figure anywhere in this research is the Design Review completeness check: 15 days from submission (Zoning Ordinance Section 304.E.1). No day-count is published for the Design Review Board's substantive hearing (it runs on the Board's meeting calendar) or for the Building Inspector's own plan review after Design Review clears.
- Design Review Board review criteria for new construction (Section 304.H.1) are unusually detailed for a town this size: proportion, openings, pattern, spacing, entrances/porches/decks, materials/texture/color, roofs, architectural details, accessory buildings, accessory features, landscaping, and screening must ALL be satisfied, referencing photographs/lithographs of historic Jerome or recognized historic-preservation authorities where photographic evidence is unavailable.
- Solar installations on new construction must additionally follow the Town's 'Solar Energy System Design Guidelines' (approved by Town Council, June 2015), which apply Department of the Interior best practices for solar on historic buildings (Zoning Ordinance Section 304.H.1.m).
- A permit lapses if no inspection showing progress occurs within six months — a real risk on a hillside historic-district lot where construction can stall for permitting/funding reasons.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-07.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Jerome building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Jerome
Residential Building Permit (New Construction) in other cities
Compare residential building permit (new construction) fees across Arizona →
Look up this fee in a different city →
Now live
Build your Jerome project checklist
Describe your project once and get every permit, document, and fee it triggers in Jerome — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →