Required for room additions, decks, patio covers, fences/walls, and accessory structures (sheds) to existing dwellings in Jerome. All such projects are listed under Design Review Board jurisdiction (Zoning Ordinance Section 304.B) because the entire town is within the Historic Overlay District — only like-for-like repair/maintenance using the same materials is exempt.

Verified 2026-07-07 · Source

When you need this permit

  • Design Review Board approval required for: additions and exterior modifications; decks; fences and walls; sheds and accessory structures (Zoning Ordinance Section 304.B.2,3,5,8)
  • Lighter Zoning Administrator (staff-level) review applies instead of full Board review for: patios; certain roof material/color changes with limited reflectivity; and window/door replacement that replicates the same size and style (Section 304.C)
  • Exempt from Design Review: landscaping (not including accessory structures like gazebos/pergolas/sheds) and repair/replacement/maintenance of existing structures using the same materials (Section 304.D)
  • Retaining walls over 4 feet high require a building permit valued at $10.00 per square foot above 4 ft (or the Valuation and Fee Schedule, whichever governs)
  • Building permit application, plot plan, and construction drawings filed with the Building Inspector after Design Review/Zoning Administrator clearance

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Based on Valuation (Schedule A-1)Town of Jerome Official Fee Schedule, Schedule A-1
Same Valuation and Fee Schedule as new construction ($50.00 minimum, scaling to $5,041.25 + $2.75/$1,000 above $1,000,000)
Retaining Walls Over 4 Feet HighTown of Jerome Official Fee Schedule, Schedule A-1, Specific Fees
$10.00 per square foot above 4 ft. high (or per the Valuation and Fee Schedule)
Design Review Board Fee — New Construction of Accessory Features (Section 304.F.I)Town of Jerome Official Fee Schedule, Design Review Board section
$50
Design Review Board Fee — Large AlterationsTown of Jerome Official Fee Schedule, Design Review Board section
Under $500 in value: $50; $501-$10,000 in value: $100; over $10,001 in value: 1% of value

Review timeline

Plan review
Not published — contact the department

How long did your Residential Addition / Remodel / Accessory Structure Permit permit actually take in Jerome?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation/Footing

    Required before concrete pour for additions and accessory structures with foundations

  2. 2

    Framing

    Structural connections to existing structure

  3. 3

    Final

    Completed work verified against approved plans

See the full Jerome inspection guide — scheduling & re-inspection fees →

Tips

  • Sheds and accessory structures require FULL Design Review Board review in Jerome (Section 304.B.8) — there is no small-shed size exemption comparable to what some other Arizona towns publish (e.g., Buckeye's 200 sq ft exemption or Clarkdale's 50 sq ft exemption); only like-for-like repair/maintenance is exempt from Design Review here.
  • Retaining walls over 4 feet are billed at a distinctive flat rate ($10.00/sq ft above 4 ft) rather than straight ICC valuation — get this figure from the Building Inspector before budgeting a hillside retaining-wall project, common given Jerome's steep mining-district terrain.
  • Patios and certain roof/window/door replacements get the lighter Zoning-Administrator-only review track (Section 304.C) instead of a full Design Review Board hearing — ask which track applies before assuming a full Board hearing is required.

Frequently asked questions

Yes — sheds and accessory structures are explicitly listed as requiring Design Review Board review (Zoning Ordinance Section 304.B.8) regardless of size, because the entire town is within the Historic Overlay District. There is no small-shed size exemption from Design Review in Jerome, unlike some other Arizona towns.

In Jerome, the published Building Permit Fee — Based on Valuation (Schedule A-1) is: Same Valuation and Fee Schedule as new construction ($50.00 minimum, scaling to $5,041.25 + $2.75/$1,000 above $1,000,000). Additional published fees: Retaining Walls Over 4 Feet High — $10.00 per square foot above 4 ft. high (or per the Valuation and Fee Schedule); Design Review Board Fee — New Construction of Accessory Features (Section 304.F.I) — $50; Design Review Board Fee — Large Alterations — Under $500 in value: $50; $501-$10,000 in value: $100; over $10,001 in value: 1% of value. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Jerome does not publish a plan-review timeline for this permit. Contact Town of Jerome Building Department (Planning & Zoning Dept.) — Building Inspector at 928-634-7943 for current turnaround.

You'll need: Building Permit Application; Design Review Application / General Land Use Application; Plot Plan. See the required-documents checklist on this page for details on each.

Jerome requires 3 inspection(s) for a residential addition / remodel / accessory structure permit, in order: Foundation/Footing, Framing, Final. Schedule each through Town of Jerome Building Department (Planning & Zoning Dept.) — Building Inspector (928-634-7943).

Apply through Town of Jerome Building Department (Planning & Zoning Dept.) — Building Inspector at 600 Clark Street, P.O. Box 335, Jerome, AZ 86331. Phone: 928-634-7943, email: b.wolstencroft@jerome.az.gov. Office hours: Town Hall: Monday - Thursday, 8:00 a.m. to 5:00 p.m. Building Inspector: Barry Wolstencroft (b.wolstencroft@jerome.az.gov, 928-634-7943, fax 928-634-0715). Building permit applications are filed at Town Hall (PO Box 335 / 600 Clark St.) only AFTER the project has received required approval from the Design Review Board and/or Zoning Administrator; inspections are scheduled approximately one week in advance and the Town states it is not liable for work delays due to inspection scheduling.. Official information: https://jerome.az.gov/building-inspection.

Jerome, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). Despite its very small size (population approximately 450), the Town of Jerome runs its own genuinely independent Building Department with a named Building Inspector (Barry Wolstencroft), its own adopted code chapter (Town Code Chapter 7, Building and Safety Codes), and its own Council-adopted fee schedule (Schedule A-1) — it does NOT defer building-permit administration to Yavapai County. Source: Town of Jerome Building Inspection page (jerome.az.gov/building-inspection) and Building Codes page (jerome.az.gov/building-codes).; 2012 International Building Code (IBC), adopted by Resolution 544. Source: Town of Jerome Building Codes page (jerome.az.gov/building-codes).; 2012 International Residential Code for One- and Two-Family Dwellings (IRC), adopted by Resolution 545. Source: Town of Jerome Building Codes page.; 2012 International Plumbing Code (IPC), including Appendices B, C, D, and E, adopted by Resolution 547. Source: Town of Jerome Building Codes page.; 2011 National Electrical Code (NEC), adopted by Resolution 548 — notably TWO editions behind the electrical-code cycle used by most other AZ jurisdictions reviewed in this dataset (which have generally moved to the 2023 NEC); confirmed as currently listed on the Town's own Building Codes page, not assumed. Source: Town of Jerome Building Codes page.; 2012 International Mechanical Code (IMC), adopted by Resolution 546. Source: Town of Jerome Building Codes page.; 2012 International Fuel Gas Code (IFGC), including Appendices A, B, C, and D, adopted by Resolution 549. Source: Town of Jerome Building Codes page.; 2012 International Property Maintenance Code (IPMC), adopted by Resolution 550 and Ordinance 430. Source: Town of Jerome Building Codes page.; Appendix 33 of the 1997 Uniform Building Code (UBC), serving as the Town's Grading Ordinance, adopted by Ordinance 358. Source: Town of Jerome Building Codes page.; Town of Jerome Administrative Code (2003 Edition), adopted by Ordinance 358 — governs local permit administration provisions layered on top of the ICC codes (e.g., the Section 108.8 reinspection-fee citation used in the Town's own Fee Schedule). Source: Town of Jerome Building Codes page.; 2018 International Fire Code (IFC), adopted by Resolution 635 — notably a much newer edition than the 2012-vintage building/residential/plumbing/mechanical/fuel-gas code set, and the only code in Jerome's adopted set current within the last decade. Source: Town of Jerome Building Codes page.; IMPORTANT — Historic Overlay District (Jerome Zoning Ordinance Section 511.C): the Historic Overlay District boundary 'shall include all areas within the corporate limits of the Town of Jerome' — i.e., the ENTIRE town is inside the Historic Overlay District, not just a subset of downtown parcels. As a result, Design Review Board (or, for minor listed items, Zoning Administrator) approval under Zoning Ordinance Section 304 is a mandatory prerequisite BEFORE a building permit application can even be submitted to the Building Inspector, for nearly every exterior construction project Town-wide. Source: Jerome Zoning Ordinance (current through July 2024), Sections 304 and 511 (jerome.az.gov/documents/76/Zoning_Ordinance_updated_thru_July_2024.pdf); Building Permit Application Packet ('We provide the following information to assist you in applying for a permit once the Design Review Board has approved your project.').. Local amendments apply — see the Jerome overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-07.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Jerome building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.