Electric Vehicle (EV) Charger / EVSE Permit in Jerome, Arizona

Jerome has no dedicated EV charger/EVSE fee line or standalone permit category. EV charger installation is electrical work governed by the 2011 National Electrical Code (NEC) as adopted by the Town (Resolution 548) and billed under the same flat-rate/combination-permit structure used for any other electrical work — the Town's itemized $50.00 'New Electrical Service' fee, or the $50.00-per-trade Combination Permit rate for projects valued up to $3,000. Because the Historic Overlay District covers the Town's entire corporate limits (Zoning Ordinance Section 511.C), an exterior-visible charger installation (e.g., a pedestal or wall unit visible from a public way) as part of a broader exterior modification could separately trigger Design Review Board or Zoning Administrator review under Section 304 — the same layered process that applies to other exterior electrical fixtures — though routine like-for-like electrical work alone does not trigger Design Review.

Verified 2026-07-20 · Source

When you need this permit

  • Electrical permit required for EV charger/EVSE circuit installation, governed by the 2011 NEC as adopted by the Town of Jerome (Resolution 548)
  • No EV-specific fee line exists; billed as either the itemized New Electrical Service fee or the Combination Permit rate (for a project bundling electrical with plumbing/mechanical work valued up to $3,000), or the general valuation-based Schedule A-1 table for larger installations
  • An exterior-visible charger unit (pedestal, wall-mount visible from a public way) installed as part of a broader exterior modification may require Design Review Board or Zoning Administrator approval BEFORE the electrical/building permit is issued, since the entire Town lies within the Historic Overlay District
  • Contractor licensing information (ROC license/class) or Owner-Builder exemption required at application Owner-builderContractor

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

New Electrical ServiceNo distinct EV charger/EVSE fee line exists; a standalone EV charger circuit is billed under the same flat New Electrical Service fee used for other electrical work. Town of Jerome Official Fee Schedule, Schedule A-1, Specific Fees (current as of July 1, 2026) -- directly re-verified 2026-07-20 against the downloaded PDF, which lists 'New Electrical Service: $50.00' and 'Combination permits for electrical, plumbing or mechanical -- valuations up to $3,000.00: $50.00 for each trade' exactly as cited here.
$50.00
Combination Permit (electrical, plumbing, or mechanical), valuation up to $3,000Town of Jerome Official Fee Schedule, Schedule A-1
$50.00 for each trade

Review timeline

Plan review
Not published — contact the department

How long did your Electric Vehicle (EV) Charger / EVSE Permit permit actually take in Jerome?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In

    Wiring and circuit connections before concealment, if applicable

  2. 2

    Final

    Charger mounted, circuit labeled, and installation verified per the adopted 2011 NEC

See the full Jerome inspection guide — scheduling & re-inspection fees →

Tips

  • Jerome does not price EV chargers separately from other electrical work — expect the flat $50.00 New Electrical Service fee (or the $50.00-per-trade Combination Permit rate) rather than an EV-specific fee.
  • Because the Historic Overlay District covers the Town's ENTIRE corporate limits, confirm with the Building Inspector or Zoning Administrator whether an exterior-visible charger unit needs Design Review approval before applying for the electrical permit — this is easy to overlook since it is not a purely electrical-code question.
  • Jerome's adopted 2011 NEC is two editions behind the 2023 NEC used by many nearby Yavapai County jurisdictions — confirm with the Building Inspector whether current NEC Article 625 (Electric Vehicle Charging System) provisions are being applied in practice despite the formally older adopted edition.

Frequently asked questions

Jerome requires an electric vehicle (ev) charger / evse permit for: Electrical permit required for EV charger/EVSE circuit installation, governed by the 2011 NEC as adopted by the Town of Jerome (Resolution 548); No EV-specific fee line exists; billed as either the itemized New Electrical Service fee or the Combination Permit rate (for a project bundling electrical with plumbing/mechanical work valued up to $3,000), or the general valuation-based Schedule A-1 table for larger installations; An exterior-visible charger unit (pedestal, wall-mount visible from a public way) installed as part of a broader exterior modification may require Design Review Board or Zoning Administrator approval BEFORE the electrical/building permit is issued, since the entire Town lies within the Historic Overlay District; Contractor licensing information (ROC license/class) or Owner-Builder exemption required at application. If your project isn't listed, confirm with Town of Jerome Building Department (Planning & Zoning Dept.) — Building Inspector at 928-634-7943 before starting work.

No. Jerome has no dedicated EV charger/EVSE permit category or fee line. Installing a charger is billed under the Town's standard electrical permit fees — the flat $50.00 New Electrical Service fee, or the $50.00-per-trade Combination Permit rate for smaller bundled projects.

Jerome does not publish a plan-review timeline for this permit. Contact Town of Jerome Building Department (Planning & Zoning Dept.) — Building Inspector at 928-634-7943 for current turnaround.

You'll need: Building/Electrical Permit Application; Electrical Plan / Load Calculation. See the required-documents checklist on this page for details on each.

Jerome requires 2 inspection(s) for an electric vehicle (ev) charger / evse permit, in order: Rough-In, Final. Schedule each through Town of Jerome Building Department (Planning & Zoning Dept.) — Building Inspector (928-634-7943).

Apply through Town of Jerome Building Department (Planning & Zoning Dept.) — Building Inspector at 600 Clark Street, P.O. Box 335, Jerome, AZ 86331. Phone: 928-634-7943, email: b.wolstencroft@jerome.az.gov. Office hours: Town Hall: Monday - Thursday, 8:00 a.m. to 5:00 p.m. Building Inspector: Barry Wolstencroft (b.wolstencroft@jerome.az.gov, 928-634-7943, fax 928-634-0715). Building permit applications are filed at Town Hall (PO Box 335 / 600 Clark St.) only AFTER the project has received required approval from the Design Review Board and/or Zoning Administrator; inspections are scheduled approximately one week in advance and the Town states it is not liable for work delays due to inspection scheduling.. Official information: https://jerome.az.gov/building-inspection.

Jerome, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). Despite its very small size (population approximately 450), the Town of Jerome runs its own genuinely independent Building Department with a named Building Inspector (Barry Wolstencroft), its own adopted code chapter (Town Code Chapter 7, Building and Safety Codes), and its own Council-adopted fee schedule (Schedule A-1) — it does NOT defer building-permit administration to Yavapai County. Source: Town of Jerome Building Inspection page (jerome.az.gov/building-inspection) and Building Codes page (jerome.az.gov/building-codes).; 2012 International Building Code (IBC), adopted by Resolution 544. Source: Town of Jerome Building Codes page (jerome.az.gov/building-codes).; 2012 International Residential Code for One- and Two-Family Dwellings (IRC), adopted by Resolution 545. Source: Town of Jerome Building Codes page.; 2012 International Plumbing Code (IPC), including Appendices B, C, D, and E, adopted by Resolution 547. Source: Town of Jerome Building Codes page.; 2011 National Electrical Code (NEC), adopted by Resolution 548 — notably TWO editions behind the electrical-code cycle used by most other AZ jurisdictions reviewed in this dataset (which have generally moved to the 2023 NEC); confirmed as currently listed on the Town's own Building Codes page, not assumed. Source: Town of Jerome Building Codes page.; 2012 International Mechanical Code (IMC), adopted by Resolution 546. Source: Town of Jerome Building Codes page.; 2012 International Fuel Gas Code (IFGC), including Appendices A, B, C, and D, adopted by Resolution 549. Source: Town of Jerome Building Codes page.; 2012 International Property Maintenance Code (IPMC), adopted by Resolution 550 and Ordinance 430. Source: Town of Jerome Building Codes page.; Appendix 33 of the 1997 Uniform Building Code (UBC), serving as the Town's Grading Ordinance, adopted by Ordinance 358. Source: Town of Jerome Building Codes page.; Town of Jerome Administrative Code (2003 Edition), adopted by Ordinance 358 — governs local permit administration provisions layered on top of the ICC codes (e.g., the Section 108.8 reinspection-fee citation used in the Town's own Fee Schedule). Source: Town of Jerome Building Codes page.; 2018 International Fire Code (IFC), adopted by Resolution 635 — notably a much newer edition than the 2012-vintage building/residential/plumbing/mechanical/fuel-gas code set, and the only code in Jerome's adopted set current within the last decade. Source: Town of Jerome Building Codes page.; IMPORTANT — Historic Overlay District (Jerome Zoning Ordinance Section 511.C): the Historic Overlay District boundary 'shall include all areas within the corporate limits of the Town of Jerome' — i.e., the ENTIRE town is inside the Historic Overlay District, not just a subset of downtown parcels. As a result, Design Review Board (or, for minor listed items, Zoning Administrator) approval under Zoning Ordinance Section 304 is a mandatory prerequisite BEFORE a building permit application can even be submitted to the Building Inspector, for nearly every exterior construction project Town-wide. Source: Jerome Zoning Ordinance (current through July 2024), Sections 304 and 511 (jerome.az.gov/documents/76/Zoning_Ordinance_updated_thru_July_2024.pdf); Building Permit Application Packet ('We provide the following information to assist you in applying for a permit once the Design Review Board has approved your project.').. Local amendments apply — see the Jerome overview page for the full list.

It can, if the installation is exterior-visible (e.g., a pedestal or wall unit visible from a public way) as part of a broader exterior modification, because the Town's entire corporate limits lie within the Historic Overlay District under Zoning Ordinance Section 511.C. Routine like-for-like electrical repair alone does not trigger Design Review; confirm scope with the Zoning Administrator.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Jerome building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.