Commercial Tenant Improvement (T.I.) Permit in Prescott Valley, Arizona

Required for interior alterations, build-outs, and upgrades to existing commercial buildings/tenant spaces in Prescott Valley. This is a genuinely distinct permit from new commercial construction: the Town publishes a separate 'Commercial T.I. Application' and 'Commercial T.I. Application Checklist' (both updated 12/2024), with its own lower $107.00 application deposit (vs. $321.00 for New Commercial) and a lighter submittal packet that omits the Engineering-Permit prerequisite, Special Inspections and Testing Agreement, Temporary Utility for Construction Agreement, and Water Meter/Water Tap applications required for ground-up new commercial construction. Reviewed against the same 2018 IBC and Town amendments as new commercial construction; the Town's 2026 Turnaround Times document has no separate 'Tenant Improvement' review row — T.I. submittals are reviewed under the same square-footage-tiered 'Commercial Building Plans' timeline table used for new construction.

Verified 2026-08-01 · Source

When you need this permit

  • Building permit required for changes, alterations, upgrades, and interior build-outs to existing commercial buildings/tenant spaces, submitted on the Town's dedicated Commercial T.I. Application — a separate form from the New Commercial Application used for ground-up construction
  • Reviewed against the 2018 IBC and Town of Prescott Valley amendments (Chapter 7 of the Town Code, effective January 1, 2020)
  • Unlike New Commercial Application, there is no prerequisite Engineering Permit approval step and no Special Inspections Agreement, Temporary Utility Agreement, or Water Meter/Water Tap application in the Commercial T.I. Application Checklist
  • Plans (site plan, landscape plan, civils, plumbing, electrical, mechanical, parking, lighting, floor plan) must be Architect- or Engineer-stamped if the project is over 3,000 square feet OR has an occupant load over 20 — the identical stamping threshold used for new commercial construction
  • Structural Calculations and Layout Sheet required only if applicable to the scope of work
  • A $107.00 non-refundable application deposit must be paid to the Permitting Office (928-759-5535), per the Commercial T.I. Application Checklist (updated 12/2024)
  • Proof of Valid Contractor's License required (A.R.S. Title 32, Chapter 11, §§ 32-1168-1169) Contractor
  • Apply via the Town's GoPost ePlan online portal (gopost-prescottvalley.eplansoftreview.com)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Based on Total Valuation of T.I. workTown of Prescott Valley Comprehensive Fee Schedule, Development Services: Building Permit Fees; no separate T.I.-only valuation table exists — the same six-tier table applies
Same six-tier Total Valuation schedule as new residential/commercial construction ($26.75 minimum at $1-$500 valuation, scaling per the valuation brackets)
Plan Review Fee — CommercialTown of Prescott Valley Comprehensive Fee Schedule, Development Services: Building Permit Fees — same 'Plan Review Fee - Commercial' line item used for new commercial construction; no separate lower rate for T.I. was found
65% of the Building Permit Fee, including Electrical, Plumbing, and Mechanical Fees
Commercial T.I. Application DepositPer the Commercial T.I. Application Checklist (updated 12/2024), which directs applicants to pay this amount to the Permitting Office. NOTE — this matches the Fee Schedule's 'Deposits - Commercial/Industrial - Additions/Remodels' line ($107.00), not the Fee Schedule's separate, lower 'Deposits - Commercial/Industrial - Small Tenant Improvements' line ($32.10); the Town's own documents do not explain the distinction between 'Small Tenant Improvements' and standard Tenant Improvements, or which deposit line the $32.10 figure is meant to apply to. Both figures are reproduced here verbatim rather than silently resolved — the $107.00 figure is the one actually collected per the current (12/2024) application checklist and should be treated as authoritative pending confirmation with the Permitting Office.
$107.00
Mechanical / Electrical / Plumbing Permit Fees (in addition to Building Permit Fee)Town of Prescott Valley Comprehensive Fee Schedule, Development Services: Mechanical, Electrical, and Plumbing Fees — same trade-permit fee structure used for residential and new commercial construction
Mechanical: greater of $26.75 or $0.02/sq ft; Electrical: greater of $32.10 or $0.04/sq ft; Plumbing: greater of $53.50 or $0.03/sq ft

Review timeline

Plan reviewPrescott Valley’s published plan-review target
40–75 business days

How long did your Commercial Tenant Improvement (T.I.) Permit permit actually take in Prescott Valley?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In (Electrical / Plumbing / Mechanical, as applicable)

    Applicable trade rough-in inspections before concealment, scoped to the T.I. work performed

  2. 2

    Final / Certificate of Occupancy

    All work complete per approved plans; Certificate of Occupancy issued once Building, Public Works, Engineering, and Planning and Zoning requirements are met

See the full Prescott Valley inspection guide — scheduling & re-inspection fees →

Tips

  • The Town's 2026 Turnaround Times document has no dedicated 'Tenant Improvement' or 'Commercial T.I.' row — T.I. submittals fall under the same square-footage-tiered 'Commercial Building Plans' table used for new construction: Small (under 5,000 sf) 40/45 business days (SPR Goal/Average); Medium (5,000-50,000 sf) 55/65; Large (50,000 sf+) 65/75. Most single-tenant retail T.I. build-outs along the SR-69 corridor will typically fall in the Small tier, but the applicable tier is driven by the submitted plans' square footage, not by the T.I.-vs-new-construction distinction.
  • Expedited Plan Review (EXPR) is a flat 15 business days across all three size tiers; Fast Track (FTR) is listed as 'N/A' for every commercial tier, including T.I. — Prescott Valley does not offer an in-house Fast Track option for commercial permits of any kind.
  • All review timeframes operate within the outer statutory ceiling of the Town's A.R.S. § 9-835 Required Timeframe Posting (30 days Administrative Completeness / 60 days Substantive Review / 90-day overall statutory ceiling).
  • The Commercial T.I. Application Checklist is materially lighter than the New Commercial Application Checklist: no prior Engineering Permit is required, and the packet omits the Special Inspections and Testing Agreement, Temporary Utility for Construction Agreement, Water Meter & Utility Service Application, and Commercial Water Tap Installation Application that new-construction submittals must include.
  • The Fee Schedule's 'Deposits - Commercial/Industrial - Small Tenant Improvements' line ($32.10) does not match the $107.00 deposit actually specified on the current (12/2024) Commercial T.I. Application Checklist, which instead matches the Fee Schedule's 'Additions/Remodels' deposit line — confirm the applicable deposit amount with the Permitting Office (928-759-5535) before submitting.

Frequently asked questions

Prescott Valley requires a commercial tenant improvement (t.i.) permit for: Building permit required for changes, alterations, upgrades, and interior build-outs to existing commercial buildings/tenant spaces, submitted on the Town's dedicated Commercial T.I. Application — a separate form from the New Commercial Application used for ground-up construction; Reviewed against the 2018 IBC and Town of Prescott Valley amendments (Chapter 7 of the Town Code, effective January 1, 2020); Unlike New Commercial Application, there is no prerequisite Engineering Permit approval step and no Special Inspections Agreement, Temporary Utility Agreement, or Water Meter/Water Tap application in the Commercial T.I. Application Checklist; Plans (site plan, landscape plan, civils, plumbing, electrical, mechanical, parking, lighting, floor plan) must be Architect- or Engineer-stamped if the project is over 3,000 square feet OR has an occupant load over 20 — the identical stamping threshold used for new commercial construction; Structural Calculations and Layout Sheet required only if applicable to the scope of work; A $107.00 non-refundable application deposit must be paid to the Permitting Office (928-759-5535), per the Commercial T.I. Application Checklist (updated 12/2024); Proof of Valid Contractor's License required (A.R.S. Title 32, Chapter 11, §§ 32-1168-1169); Apply via the Town's GoPost ePlan online portal (gopost-prescottvalley.eplansoftreview.com). If your project isn't listed, confirm with Town of Prescott Valley Development Services Department — Building Safety / Permitting at 928-759-3050 (Development Services main); 928-759-5535 (Permitting); 928-759-3060 (Inspection scheduling/IVR) before starting work.

In Prescott Valley, the published Building Permit Fee — Based on Total Valuation of T.I. work is: Same six-tier Total Valuation schedule as new residential/commercial construction ($26.75 minimum at $1-$500 valuation, scaling per the valuation brackets). Additional published fees: Plan Review Fee — Commercial — 65% of the Building Permit Fee, including Electrical, Plumbing, and Mechanical Fees; Commercial T.I. Application Deposit — $107.00; Mechanical / Electrical / Plumbing Permit Fees (in addition to Building Permit Fee) — Mechanical: greater of $26.75 or $0.02/sq ft; Electrical: greater of $32.10 or $0.04/sq ft; Plumbing: greater of $53.50 or $0.03/sq ft. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

The Town's 2026 Turnaround Times document does not list a separate Tenant Improvement row; T.I. submittals are reviewed under the same square-footage-tiered Commercial Building Plans table as new construction: Small (under 5,000 sf) is 40/45 business days (Goal/Average), Medium (5,000-50,000 sf) is 55/65, and Large (50,000 sf+) is 65/75. Expedited Plan Review is a flat 15 business days regardless of size; Fast Track is not offered for commercial projects.

You'll need: Commercial T.I. Application; Proof of Valid Contractor's License; Plans (Site Plan, Landscape Plan, Civils, Plumbing, Electrical, Mechanical, Parking, Lighting, Floor Plan). Depending on your project, Prescott Valley may also ask for: Structural Calculations and Layout Sheet; Agent Letter / Letter of Authorization. See the required-documents checklist on this page for details on each.

Prescott Valley requires 2 inspection(s) for a commercial tenant improvement (t.i.) permit, in order: Rough-In (Electrical / Plumbing / Mechanical, as applicable), Final / Certificate of Occupancy. Schedule each through Town of Prescott Valley Development Services Department — Building Safety / Permitting (928-759-3050 (Development Services main); 928-759-5535 (Permitting); 928-759-3060 (Inspection scheduling/IVR)).

Apply through Town of Prescott Valley Development Services Department — Building Safety / Permitting at 7501 E. Skoog Blvd. (Civic Center), Prescott Valley, AZ 86314. Phone: 928-759-3050 (Development Services main); 928-759-5535 (Permitting); 928-759-3060 (Inspection scheduling/IVR), email: permitting@prescottvalley-az.gov (permit applications); devserv@prescottvalley-az.gov (general Development Services). Office hours: Monday - Friday, 8 a.m. - 5 p.m. (Development Services Counter payment window 8 a.m. - 4 p.m.; permit pickup 8 a.m. - 5 p.m.). Applications are submitted through the Town's GoPost ePlan online portal (gopost-prescottvalley.eplansoftreview.com); walk-in/paper submittal is not the standard path.. Official information: https://www.prescottvalley-az.gov/departments/development_services/permit_center.php.

Yes. The Town's Commercial T.I. Application and Commercial T.I. Application Checklist (both updated 12/2024) are distinct from the New Commercial Application: T.I. has a lower $107.00 deposit (vs. $321.00), no prerequisite Engineering Permit, and a lighter document checklist that omits the Special Inspections Agreement, Temporary Utility Agreement, and Water Meter/Tap applications required for new construction.

$107.00, per the Commercial T.I. Application Checklist (updated 12/2024), paid to the Permitting Office (928-759-5535). This matches the Fee Schedule's 'Deposits - Commercial/Industrial - Additions/Remodels' line rather than its separate, lower 'Small Tenant Improvements' line ($32.10) — confirm the exact figure with the Permitting Office.

Sources & verification

Verified against official sources. Last reviewed 2026-08-01.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Prescott Valley building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Prescott Valley.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.