Re-Roofing Permit in Prescott Valley, Arizona

Required for residential and commercial re-roofing in Prescott Valley. Governed by the 2018 IRC/IBC roofing provisions and the Town's Re-Roof Application (updated 12/2024).

Verified 2026-07-06 · Source

When you need this permit

  • Building permit required for re-roofing; the Re-Roof Application requires the site location and approximate value (valuation of labor and materials) of the re-roof project
  • Application must state whether the roof material type is changing, whether any detached buildings are also being re-roofed (and if so, how many), and whether the structure is a mobile/manufactured home
  • If the structure is a mobile/manufactured home AND the roof type is changing, engineering approval must be provided
  • Proof of Valid Contractor's License required at submittal Contractor
  • Apply via the Town's GoPost ePlan online portal

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Based on Total Valuation of re-roof labor and materialsTown of Prescott Valley Comprehensive Fee Schedule, Development Services: Building Permit Fees; the Re-Roof Application itself collects 'Valuation of labor and materials' as the fee basis
Same six-tier Total Valuation schedule as new residential construction ($26.75 minimum at $1-$500 valuation, scaling per the valuation brackets)

Review timeline

Plan reviewPrescott Valley’s published plan-review target
30–90 business days

How long did your Re-Roofing Permit permit actually take in Prescott Valley?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Roofing & Shear Inspection

    Verifies sheathing, flashing, underlayment, and proposed roofing material/weight per the Town's Roofing & Shear Inspection Form before final cover

See the full Prescott Valley inspection guide — scheduling & re-inspection fees →

Tips

  • Re-Roofing is not separately itemized on the Town's 2026 Plan Review Turnaround Times document; as a Miscellaneous/Building permit type it is bound by the Town's A.R.S. § 9-835 Required Timeframe Posting (30 days Administrative Completeness / 60 days Substantive Review / 90-day overall statutory ceiling).
  • If you are changing roof material type on any structure, or re-roofing a mobile/manufactured home, disclose this on the Re-Roof Application — a manufactured/mobile home with a changing roof type additionally requires engineering approval.
  • The Town's fee for re-roofing is not a flat dollar figure — it is charged against the same six-tier Total Valuation Building Permit Fee schedule used for new construction, based on the stated valuation of labor and materials for the re-roof project.

Frequently asked questions

Yes. The Town's Re-Roof Application requires disclosure of project valuation, whether the roofing material type is changing, and whether any detached buildings are also being re-roofed. Mobile/manufactured homes with a changing roof type additionally require engineering approval.

In Prescott Valley, the published Building Permit Fee — Based on Total Valuation of re-roof labor and materials is: Same six-tier Total Valuation schedule as new residential construction ($26.75 minimum at $1-$500 valuation, scaling per the valuation brackets). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Re-Roofing is not separately itemized in the Town's plan-review turnaround document, so review is governed by the Town's A.R.S. § 9-835 Required Timeframe Posting: 30 days for administrative completeness, 60 days for substantive review after completeness, and no greater than 90 days total from submittal to final approval or denial.

You'll need: Re-Roof Application (updated 12/2024); Proof of Valid Contractor's License. Depending on your project, Prescott Valley may also ask for: Engineering Approval. See the required-documents checklist on this page for details on each.

Prescott Valley requires 1 inspection(s) for a re-roofing permit, in order: Roofing & Shear Inspection. Schedule each through Town of Prescott Valley Development Services Department — Building Safety / Permitting (928-759-3050 (Development Services main); 928-759-5535 (Permitting); 928-759-3060 (Inspection scheduling/IVR)).

Apply through Town of Prescott Valley Development Services Department — Building Safety / Permitting at 7501 E. Skoog Blvd. (Civic Center), Prescott Valley, AZ 86314. Phone: 928-759-3050 (Development Services main); 928-759-5535 (Permitting); 928-759-3060 (Inspection scheduling/IVR), email: permitting@prescottvalley-az.gov (permit applications); devserv@prescottvalley-az.gov (general Development Services). Office hours: Monday - Friday, 8 a.m. - 5 p.m. (Development Services Counter payment window 8 a.m. - 4 p.m.; permit pickup 8 a.m. - 5 p.m.). Applications are submitted through the Town's GoPost ePlan online portal (gopost-prescottvalley.eplansoftreview.com); walk-in/paper submittal is not the standard path.. Official information: https://www.prescottvalley-az.gov/departments/development_services/permit_center.php.

Prescott Valley, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-jurisdiction authority under state enabling statutes (A.R.S. Title 9 for municipalities). The Town of Prescott Valley runs its own Development Services Department and independently adopts and administers its own construction codes under Chapter 7 (Building Regulations) of the Town Code; it does not defer permitting to Yavapai County. Source: Town of Prescott Valley Development Services Department page and 2018 Code Design Requirements memo (Building Safety - Plans Examination, Senior Certified Plans Examiner Russ Harsh).; 2018 International Building Code (IBC), as published by the International Code Council, adopted by the Town of Prescott Valley effective January 1, 2020, under Chapter 7 of the Town Code, with Town amendments. Source: Town of Prescott Valley Development Services Department page (prescottvalley-az.gov) and 2018 Code Design Requirements memo.; 2018 International Residential Code (IRC), adopted effective January 1, 2020, with Town amendments. Source: 2018 Code Design Requirements memo, Town of Prescott Valley Development Services Department — Building Safety, Plans Examination.; 2018 International Plumbing Code (IPC), adopted effective January 1, 2020. Source: 2018 Code Design Requirements memo.; 2018 International Mechanical Code (IMC), adopted effective January 1, 2020. Source: 2018 Code Design Requirements memo.; 2018 International Fuel Gas Code (IFGC), adopted effective January 1, 2020. Source: 2018 Code Design Requirements memo.; 2017 National Electrical Code (NEC), as published by the National Fire Protection Association, adopted effective January 1, 2020 (one code cycle behind the 2018 ICC set, consistent with the NEC's separate 3-year publication cycle). Source: 2018 Code Design Requirements memo.; 2006 International Energy Conservation Code (IECC), Residential Only — the Town has NOT adopted a newer IECC edition; the 2006 edition remains the current residential energy code baseline as of this review. Source: 2018 Code Design Requirements memo (explicitly lists '2006 International Energy Conservation Code (Residential Only)').; ANSI A117.1-2009 American National Standard (Accessible and Usable Buildings and Facilities) and the 2010 ADA Standards for Accessible Design are adopted as the Town's accessibility standards. Source: 2018 Code Design Requirements memo.; As of this review, the Town has NOT adopted the 2024 ICC code suite. The Town's own Permit Center document library includes a form titled 'Acknowledging 2024 ICC Codes Not Yet Adopted,' confirming the 2018-cycle codes listed above remain current and in force; applicants must sign this acknowledgment on certain submittals. Source: Town of Prescott Valley Permit Center page (Acknowledging 2024 ICC Codes Not Yet Adopted.pdf).; Manufactured/mobile homes are regulated directly by the State of Arizona (A.R.S. § 41-4001 et seq., Arizona Department of Fire, Building and Life Safety / Office of Manufactured Housing) for construction/installation standards; the Town issues its own separate Manufactured/Mobile Home permit for placement, foundation/tie-down, and site improvements (listed among the Town's Building Permit categories). Source: Town of Prescott Valley Permit Center page (Manufactured Mobile Permit Application.pdf).. Local amendments apply — see the Prescott Valley overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Prescott Valley building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.