Commercial Building Permit (New Construction) in Prescott Valley, Arizona

Required for new commercial building construction in Prescott Valley, reviewed against the 2018 IBC and Town of Prescott Valley amendments (Chapter 7 of the Town Code, effective January 1, 2020) plus ANSI A117.1-2009/2010 ADA accessibility standards. Applications use the Town's dedicated 'New Commercial Application' (part of the New Commercial Application Checklist packet, updated 12/2024), which is genuinely distinct from the Town's separate 'Commercial T.I. Application' used for interior tenant improvements to existing commercial space (see the Commercial Tenant Improvement Permit entry) — the two use different application forms, different submittal-deposit amounts ($321.00 New Commercial vs. $107.00 T.I.), and different document checklists (New Commercial requires a prior Engineering Permit, Special Inspections Agreement, Temporary Utility Agreement, and Water Meter/Water Tap applications that T.I. does not).

Verified 2026-08-01 · Source

When you need this permit

  • Building permit required for new commercial building construction within Prescott Valley town limits, submitted on the Town's New Commercial Application
  • Reviewed against the 2018 IBC and Town of Prescott Valley amendments, plus ANSI A117.1-2009 and the 2010 ADA Standards for Accessible Design
  • Per the New Commercial Application Checklist (updated 12/2024), this step must start ONLY after a separate Engineering Permit has already been approved; applicants must contact the Permitting Office (928-759-5535) to discuss project permitting requirements and phasing — one New Commercial Application is required per building
  • Plans (site plan, landscape plan, plumbing, electrical, lighting, mechanical) must be Architect- or Engineer-stamped if the project is over 3,000 square feet OR has an occupant load over 20
  • A $321.00 non-refundable application deposit must be paid to the Permitting Office (928-759-5535) before the application proceeds, per the New Commercial Application Checklist and the Town of Prescott Valley Comprehensive Fee Schedule ('Deposits - Commercial/Industrial - New Construction')
  • Per the Town's Temporary Utility for Construction Agreement (New Commercial/Residential Projects), the applicant must complete construction and obtain a Certificate of Occupancy within 365 calendar days of permit issuance, and may not allow 180 days to elapse without an inspection, per Chapter 7 of the Town of Prescott Valley ordinances
  • Proof of Valid Contractor's License required (A.R.S. Title 32, Chapter 11, §§ 32-1168-1169) Contractor
  • Apply via the Town's GoPost ePlan online portal (gopost-prescottvalley.eplansoftreview.com)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 11 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Based on Total ValuationTown of Prescott Valley Comprehensive Fee Schedule, Development Services: Building Permit Fees; confirmed by direct read of the Fee Schedule PDF — no separate commercial-only valuation table exists, the same six-tier table applies to commercial construction
Same six-tier Total Valuation schedule as new residential construction ($26.75 minimum at $1-$500 valuation, scaling per the valuation brackets)
Plan Review Fee — CommercialTown of Prescott Valley Comprehensive Fee Schedule, Development Services: Building Permit Fees — listed as its own 'Plan Review Fee - Commercial' line item, distinct from (but numerically identical to) the Tier III Residential rate
65% of the Building Permit Fee, including Electrical, Plumbing, and Mechanical Fees
New Commercial Application DepositTown of Prescott Valley Comprehensive Fee Schedule ('Deposits - Commercial/Industrial - New Construction') and New Commercial Application Checklist (updated 12/2024), which directs applicants to pay this amount to the Permitting Office before the application proceeds
$321.00
Mechanical / Electrical / Plumbing Permit Fees (in addition to Building Permit Fee)Town of Prescott Valley Comprehensive Fee Schedule, Development Services: Mechanical, Electrical, and Plumbing Fees — same trade-permit fee structure used for residential
Mechanical: greater of $26.75 or $0.02/sq ft; Electrical: greater of $32.10 or $0.04/sq ft; Plumbing: greater of $53.50 or $0.03/sq ft
Water Meter & Water Tap Fees (utility-side, in addition to building permit fees)Town of Prescott Valley Water Meter & Utility Service Application and Commercial Water Tap Installation Application (rev. 07/25); billed by the Customer Accounts Division, separate from Development Services building permit fees
Water meter charge by size ($537-$1,844) plus system capacity charge and water resource fee; water tap labor cost $445 (3/4"-2") or $745 (4"-12")

Review timeline

Plan reviewPrescott Valley’s published plan-review target
40–75 business days

How long did your Commercial Building Permit (New Construction) permit actually take in Prescott Valley?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Special Inspections (if required)

    Continuous on-site inspection per IBC Chapter 17 for projects with an approved Special Inspections and Testing Agreement

  2. 2

    Foundation/Footing

    Before concrete pour

  3. 3

    Rough-In (Structural / MEP)

    Framing, structural connections, and mechanical/electrical/plumbing rough-in before concealment

  4. 4

    Final / Certificate of Occupancy

    All work complete per approved plans; Certificate of Occupancy issued once Building, Public Works, Engineering, and Planning and Zoning requirements are met

See the full Prescott Valley inspection guide — scheduling & re-inspection fees →

Tips

  • The Town's Standard, Fast Track, and Expedited Plan Review: Turnaround Times for 2026 (rev. 1/1/26) tiers 'Commercial Building Plans' strictly by SQUARE FOOTAGE, not by new-construction vs. tenant-improvement scope: Small (under 5,000 sf) is 40 business days SPR Goal / 45 SPR Average; Medium (5,000-50,000 sf) is 55/65; Large (50,000 sf and greater) is 65/75. Expedited Plan Review (EXPR) is a flat 15 business days across ALL three size tiers, but Fast Track (FTR) is listed as 'N/A' for every commercial tier — unlike residential, Prescott Valley does not offer an in-house Fast Track option for any commercial building permit regardless of size.
  • All review timeframes operate within the outer statutory ceiling of the Town's A.R.S. § 9-835 Required Timeframe Posting (30 days Administrative Completeness / 60 days Substantive Review / 90-day overall statutory ceiling from submittal to final approval or denial).
  • This permit type is for NEW commercial building construction and requires a prior approved Engineering Permit before the New Commercial Application can even be started — interior alterations to an EXISTING commercial building/tenant space use the separate, lighter-weight Commercial T.I. Application instead (lower $107 deposit, no Engineering Permit prerequisite, no Special Inspections/Temporary Utility/Water Meter-Tap forms).
  • The $321.00 application deposit is paid directly to the Permitting Office by phone (928-759-5535), not through the GoPost portal itself.
  • Per the Temporary Utility for Construction Agreement, failing to complete construction and obtain a Certificate of Occupancy within 365 calendar days, or allowing 180 days to elapse without an inspection, can result in penalties and permit expiration under Chapter 7 of the Town Code.

Frequently asked questions

Prescott Valley requires a commercial building permit (new construction) for: Building permit required for new commercial building construction within Prescott Valley town limits, submitted on the Town's New Commercial Application; Reviewed against the 2018 IBC and Town of Prescott Valley amendments, plus ANSI A117.1-2009 and the 2010 ADA Standards for Accessible Design; Per the New Commercial Application Checklist (updated 12/2024), this step must start ONLY after a separate Engineering Permit has already been approved; applicants must contact the Permitting Office (928-759-5535) to discuss project permitting requirements and phasing — one New Commercial Application is required per building; Plans (site plan, landscape plan, plumbing, electrical, lighting, mechanical) must be Architect- or Engineer-stamped if the project is over 3,000 square feet OR has an occupant load over 20; A $321.00 non-refundable application deposit must be paid to the Permitting Office (928-759-5535) before the application proceeds, per the New Commercial Application Checklist and the Town of Prescott Valley Comprehensive Fee Schedule ('Deposits - Commercial/Industrial - New Construction'); Per the Town's Temporary Utility for Construction Agreement (New Commercial/Residential Projects), the applicant must complete construction and obtain a Certificate of Occupancy within 365 calendar days of permit issuance, and may not allow 180 days to elapse without an inspection, per Chapter 7 of the Town of Prescott Valley ordinances; Proof of Valid Contractor's License required (A.R.S. Title 32, Chapter 11, §§ 32-1168-1169); Apply via the Town's GoPost ePlan online portal (gopost-prescottvalley.eplansoftreview.com). If your project isn't listed, confirm with Town of Prescott Valley Development Services Department — Building Safety / Permitting at 928-759-3050 (Development Services main); 928-759-5535 (Permitting); 928-759-3060 (Inspection scheduling/IVR) before starting work.

In Prescott Valley, the published Building Permit Fee — Based on Total Valuation is: Same six-tier Total Valuation schedule as new residential construction ($26.75 minimum at $1-$500 valuation, scaling per the valuation brackets). Additional published fees: Plan Review Fee — Commercial — 65% of the Building Permit Fee, including Electrical, Plumbing, and Mechanical Fees; New Commercial Application Deposit — $321.00; Mechanical / Electrical / Plumbing Permit Fees (in addition to Building Permit Fee) — Mechanical: greater of $26.75 or $0.02/sq ft; Electrical: greater of $32.10 or $0.04/sq ft; Plumbing: greater of $53.50 or $0.03/sq ft; Water Meter & Water Tap Fees (utility-side, in addition to building permit fees) — Water meter charge by size ($537-$1,844) plus system capacity charge and water resource fee; water tap labor cost $445 (3/4"-2") or $745 (4"-12"). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Per the Town's 2026 Turnaround Times document, review is tiered by square footage: Small projects (under 5,000 sf) have a 40-business-day SPR Goal / 45-day SPR Average; Medium (5,000-50,000 sf) is 55/65 business days; Large (50,000 sf or more) is 65/75 business days. Expedited Plan Review is a flat 15 business days for any size; Fast Track is not offered for commercial projects. All review operates within the Town's A.R.S. § 9-835 90-day overall statutory ceiling.

You'll need: New Commercial Application (Commercial Construction Application Page); Proof of Valid Contractor's License; Special Inspections and Testing Agreement; Temporary Utility for Construction Agreement; Water Meter & Utility Service Application; Commercial Water Tap Installation Application; Plans (Site Plan, Landscape Plan, Plumbing, Electrical, Lighting, Mechanical); Survey or Site Plan Stamped by Licensed Architect, Engineer, or Surveyor; Structural Calculations and Layout Sheet; Engineered Soils Report; Engineered Truss Specifications, Calculations, and Layout Sheet. Depending on your project, Prescott Valley may also ask for: Agent Letter / Letter of Authorization. See the required-documents checklist on this page for details on each.

Prescott Valley requires 4 inspection(s) for a commercial building permit (new construction), in order: Special Inspections (if required), Foundation/Footing, Rough-In (Structural / MEP), Final / Certificate of Occupancy. Schedule each through Town of Prescott Valley Development Services Department — Building Safety / Permitting (928-759-3050 (Development Services main); 928-759-5535 (Permitting); 928-759-3060 (Inspection scheduling/IVR)).

Apply through Town of Prescott Valley Development Services Department — Building Safety / Permitting at 7501 E. Skoog Blvd. (Civic Center), Prescott Valley, AZ 86314. Phone: 928-759-3050 (Development Services main); 928-759-5535 (Permitting); 928-759-3060 (Inspection scheduling/IVR), email: permitting@prescottvalley-az.gov (permit applications); devserv@prescottvalley-az.gov (general Development Services). Office hours: Monday - Friday, 8 a.m. - 5 p.m. (Development Services Counter payment window 8 a.m. - 4 p.m.; permit pickup 8 a.m. - 5 p.m.). Applications are submitted through the Town's GoPost ePlan online portal (gopost-prescottvalley.eplansoftreview.com); walk-in/paper submittal is not the standard path.. Official information: https://www.prescottvalley-az.gov/departments/development_services/permit_center.php.

Yes. The Town publishes a distinct 'Commercial T.I. Application' and 'Commercial T.I. Application Checklist' for interior alterations to existing commercial buildings, separate from the 'New Commercial Application' used for ground-up construction — with a lower $107.00 deposit (vs. $321.00) and a lighter submittal packet. See the Commercial Tenant Improvement Permit entry for details.

A $321.00 non-refundable application deposit, paid to the Permitting Office (928-759-5535), per the Town's New Commercial Application Checklist and Comprehensive Fee Schedule ('Deposits - Commercial/Industrial - New Construction').

Sources & verification

Verified against official sources. Last reviewed 2026-08-01.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Prescott Valley building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter