EV Charger / EVSE Permit in Prescott Valley, Arizona

Prescott Valley has no EV-charger-specific permit type or fee line. An EV charger (EVSE) circuit is electrical work governed by the 2017 NEC as adopted by the Town, filed on the same Miscellaneous Electrical Application used for any other electrical addition/alteration, and billed under the Town's general Electrical Permit fee. No EV charger, electric vehicle, or EVSE line item was found on the Town's Comprehensive Fee Schedule, the Electrical Application, or its Permit Center page.

Verified 2026-07-20 · Source

When you need this permit

  • Electrical permit required for the EV charger circuit installation (adding/altering electric service)
  • Governed by the 2017 NEC as adopted by the Town of Prescott Valley (Chapter 7 of the Town Code, effective January 1, 2020)
  • A Site Plan with 1-Line Diagram is required for the standard scope of adding, removing, or altering electric
  • Electrical services greater than 400 amps require a Site Plan with 1-Line Diagram plus engineering approval/calculations (relevant if a panel/service upgrade is needed to support the charger)
  • Proof of Valid Contractor's License and Electric Service Entrance Verification Sheet (if applicable) required at submittal Contractor
  • Apply via the Town's GoPost ePlan online portal

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical Permit Fee (no EV-specific line item found)Town of Prescott Valley Comprehensive Fee Schedule, Development Services: Mechanical, Electrical, and Plumbing Fees; the same fee used for any other electrical addition/alteration. No EV-charger-specific fee category was found.
Greater of $32.10 or $0.04 per square foot

Review timeline

Plan reviewPrescott Valley’s published plan-review target
30–90 business days

How long did your EV Charger / EVSE Permit permit actually take in Prescott Valley?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In

    EVSE circuit wiring, box placement, and panel connections before walls are closed

  2. 2

    Final

    Charger installed, panel labeled, protections verified per 2017 NEC; scheduled via IVR inspection line

See the full Prescott Valley inspection guide — scheduling & re-inspection fees →

Tips

  • There is no standalone EV-charger permit in Prescott Valley — apply using the Miscellaneous Electrical Application, the same as any other electrical addition or alteration.
  • As a stand-alone Miscellaneous permit type, an EV charger electrical permit is bound by the Town's A.R.S. § 9-835 Required Timeframe Posting: 30 days for Administrative Completeness Verification, 60 days for Substantive Review after completeness, and no greater than 90 days total from submittal to final approval/denial.

Frequently asked questions

Prescott Valley requires an ev charger / evse permit for: Electrical permit required for the EV charger circuit installation (adding/altering electric service); Governed by the 2017 NEC as adopted by the Town of Prescott Valley (Chapter 7 of the Town Code, effective January 1, 2020); A Site Plan with 1-Line Diagram is required for the standard scope of adding, removing, or altering electric; Electrical services greater than 400 amps require a Site Plan with 1-Line Diagram plus engineering approval/calculations (relevant if a panel/service upgrade is needed to support the charger); Proof of Valid Contractor's License and Electric Service Entrance Verification Sheet (if applicable) required at submittal; Apply via the Town's GoPost ePlan online portal. If your project isn't listed, confirm with Town of Prescott Valley Development Services Department — Building Safety / Permitting at 928-759-3050 (Development Services main); 928-759-5535 (Permitting); 928-759-3060 (Inspection scheduling/IVR) before starting work.

No. Prescott Valley has no EV-charger-specific permit type or fee. An EV charger circuit is permitted the same as any other electrical work, on the Miscellaneous Electrical Application, billed at the greater of $32.10 or $0.04 per square foot per the Town's Comprehensive Fee Schedule.

Prescott Valley's published plan-review target for an ev charger / evse permit is 30–90 business days.

You'll need: Electrical Application / Miscellaneous Electrical Application; Site Plan with 1-Line Diagram; Proof of Valid Contractor's License. See the required-documents checklist on this page for details on each.

Prescott Valley requires 2 inspection(s) for an ev charger / evse permit, in order: Rough-In, Final. Schedule each through Town of Prescott Valley Development Services Department — Building Safety / Permitting (928-759-3050 (Development Services main); 928-759-5535 (Permitting); 928-759-3060 (Inspection scheduling/IVR)).

Apply through Town of Prescott Valley Development Services Department — Building Safety / Permitting at 7501 E. Skoog Blvd. (Civic Center), Prescott Valley, AZ 86314. Phone: 928-759-3050 (Development Services main); 928-759-5535 (Permitting); 928-759-3060 (Inspection scheduling/IVR), email: permitting@prescottvalley-az.gov (permit applications); devserv@prescottvalley-az.gov (general Development Services). Office hours: Monday - Friday, 8 a.m. - 5 p.m. (Development Services Counter payment window 8 a.m. - 4 p.m.; permit pickup 8 a.m. - 5 p.m.). Applications are submitted through the Town's GoPost ePlan online portal (gopost-prescottvalley.eplansoftreview.com); walk-in/paper submittal is not the standard path.. Official information: https://www.prescottvalley-az.gov/departments/development_services/permit_center.php.

Prescott Valley, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-jurisdiction authority under state enabling statutes (A.R.S. Title 9 for municipalities). The Town of Prescott Valley runs its own Development Services Department and independently adopts and administers its own construction codes under Chapter 7 (Building Regulations) of the Town Code; it does not defer permitting to Yavapai County. Source: Town of Prescott Valley Development Services Department page and 2018 Code Design Requirements memo (Building Safety - Plans Examination, Senior Certified Plans Examiner Russ Harsh).; 2018 International Building Code (IBC), as published by the International Code Council, adopted by the Town of Prescott Valley effective January 1, 2020, under Chapter 7 of the Town Code, with Town amendments. Source: Town of Prescott Valley Development Services Department page (prescottvalley-az.gov) and 2018 Code Design Requirements memo.; 2018 International Residential Code (IRC), adopted effective January 1, 2020, with Town amendments. Source: 2018 Code Design Requirements memo, Town of Prescott Valley Development Services Department — Building Safety, Plans Examination.; 2018 International Plumbing Code (IPC), adopted effective January 1, 2020. Source: 2018 Code Design Requirements memo.; 2018 International Mechanical Code (IMC), adopted effective January 1, 2020. Source: 2018 Code Design Requirements memo.; 2018 International Fuel Gas Code (IFGC), adopted effective January 1, 2020. Source: 2018 Code Design Requirements memo.; 2017 National Electrical Code (NEC), as published by the National Fire Protection Association, adopted effective January 1, 2020 (one code cycle behind the 2018 ICC set, consistent with the NEC's separate 3-year publication cycle). Source: 2018 Code Design Requirements memo.; 2006 International Energy Conservation Code (IECC), Residential Only — the Town has NOT adopted a newer IECC edition; the 2006 edition remains the current residential energy code baseline as of this review. Source: 2018 Code Design Requirements memo (explicitly lists '2006 International Energy Conservation Code (Residential Only)').; ANSI A117.1-2009 American National Standard (Accessible and Usable Buildings and Facilities) and the 2010 ADA Standards for Accessible Design are adopted as the Town's accessibility standards. Source: 2018 Code Design Requirements memo.; As of this review, the Town has NOT adopted the 2024 ICC code suite. The Town's own Permit Center document library includes a form titled 'Acknowledging 2024 ICC Codes Not Yet Adopted,' confirming the 2018-cycle codes listed above remain current and in force; applicants must sign this acknowledgment on certain submittals. Source: Town of Prescott Valley Permit Center page (Acknowledging 2024 ICC Codes Not Yet Adopted.pdf).; Manufactured/mobile homes are regulated directly by the State of Arizona (A.R.S. § 41-4001 et seq., Arizona Department of Fire, Building and Life Safety / Office of Manufactured Housing) for construction/installation standards; the Town issues its own separate Manufactured/Mobile Home permit for placement, foundation/tie-down, and site improvements (listed among the Town's Building Permit categories). Source: Town of Prescott Valley Permit Center page (Manufactured Mobile Permit Application.pdf).. Local amendments apply — see the Prescott Valley overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Prescott Valley building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.