Residential Addition / Remodel / Accessory Structure Permit — Prescott Valley, Arizona · Requirements sheet
Verified 2026-07-06 · Source: https://www.prescottvalley-az.gov/departments/development_services/permit_center.php
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Addition / Remodel / Accessory Structure Permit in Prescott Valley, Arizona
Required for room additions, remodels, and new accessory structures over 200 square feet on existing one- and two-family dwellings in Prescott Valley. Reviewed against the 2018 IRC as adopted and amended by the Town.
Verified 2026-07-06 · Source
When you need this permit
- Building permit required for new additions, remodels, and accessory structures larger than 144 square feet (Zoning) / 200 square feet (Building)
- New Additions require: site plan, working drawings and specifications, floor plan
- New Accessory Building requires a site plan, and if larger than 144 square feet, working drawings and specifications (Zoning Fee applies at $16.05-$160.50 per Site Plan Review tier for accessory buildings 144 sq ft or less)
- A remodel is defined by the Town as work done to improve an existing single-family home
- Plans must comply with Town of Prescott Valley Design Criteria (115 mph wind, IRC; Exposure C; Seismic Design Category C; 30 psf roof snow load)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation/Footing
Required before concrete pour for additions and accessory structures
- 2
Framing
Structural connections to existing structure
- 3
Final
Completed work verified against approved plans
See the full Prescott Valley inspection guide — scheduling & re-inspection fees →
Tips
- Per the 2026 Turnaround Times document, Additions & Remodels carry an SPR Goal of 30 business days / SPR Average of 25 business days for first review (Expedited Review 15 days, Fast Track 7 days); Accessory Structures (single-family home plot plans in Master Planned Communities) carry a lower SPR Goal/Average of 15 business days (Fast Track 5 days, no Expedited track).
- New accessory buildings 144 square feet or less only need a Zoning site-plan review (no full Building Permit); over 144 sq ft (Zoning threshold) up to the Building Permit's 200 sq ft threshold, working drawings and specifications are required.
- A deposit tied to project valuation may be required at time of application, in addition to the standard valuation-based Building Permit Fee and 65% Tier III Plan Review Fee.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Prescott Valley building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Prescott Valley
Residential Addition / Remodel / Accessory Structure Permit in other cities
Compare residential addition / remodel / accessory structure permit fees across Arizona →
Look up this fee in a different city →