When you need this permit

  • Sheds over 200 sq ft, or any size shed with mechanical/plumbing/electrical service, require a building permit
  • Sheds under 200 sq ft with no mechanical/plumbing/electrical STILL require a building permit in Prescott per the City's 'What Needs a Permit' matrix — there is no size-based exemption as in some other Arizona cities
  • Carports under 200 sq ft and carports over 200 sq ft BOTH require a building permit
  • Accessory Structures Checklist applies for submittal requirements

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Based on ValuationCity of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025)
Valuation-based per the City's Building Valuation and Fee Estimator worksheet (Group U, Utility/Miscellaneous/Garage valuation rates, e.g., $73-$123/sf depending on construction type per the 2026 IBC Valuation Table)
Plan Review/Submittal FeeCity of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025)
Minimum $43 (1-2 unit residential) if total value is under $14,000

Review timeline

Plan reviewPrescott’s published plan-review target
15–15 business days

How long did your Accessory Structures Permit (Sheds, Carports) permit actually take in Prescott?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation/Footing

    Required if the structure has a permanent foundation

  2. 2

    Framing

    Structural framing and connections

  3. 3

    Final

    Completed structure verified against approved plans

See the full Prescott inspection guide — scheduling & re-inspection fees →

Tips

  • Per the City's published Plan Review Timeline table, 'Accessory Structures — Residential' averages 15 business days for round 1 and 7 business days for additional rounds; 'Accessory Structures — Commercial/Multi-Family' is longer at 25 business days round 1 and 12 additional.
  • Unlike Buckeye's 200-sq-ft no-permit exemption for one-story detached accessory structures, Prescott requires a building permit for accessory structures/sheds of essentially any size per its 'What Needs a Permit' matrix.
  • Carports require a permit at any size (both under and over 200 sq ft are explicitly listed as requiring a permit).

Frequently asked questions

Yes, in nearly all cases. Sheds over 200 sq ft (or any size with mechanical, plumbing, or electrical service) require a building permit, and per the City's 'What Needs a Permit' matrix, sheds under 200 sq ft with no utilities also require a permit — Prescott does not have a small-shed permit exemption.

In Prescott, the published Building Permit Fee — Based on Valuation is: Valuation-based per the City's Building Valuation and Fee Estimator worksheet (Group U, Utility/Miscellaneous/Garage valuation rates, e.g., $73-$123/sf depending on construction type per the 2026 IBC Valuation Table). Additional published fees: Plan Review/Submittal Fee — Minimum $43 (1-2 unit residential) if total value is under $14,000. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Prescott's published plan-review target for an accessory structures permit (sheds, carports) is 15–15 business days.

You'll need: Accessory Structures Checklist; Site/Plot Plan. See the required-documents checklist on this page for details on each.

Prescott requires 3 inspection(s) for an accessory structures permit (sheds, carports), in order: Foundation/Footing, Framing, Final. Schedule each through City of Prescott Community Development Department — Building Division / Permit Center (928-777-1371).

Apply through City of Prescott Community Development Department — Building Division / Permit Center at 201 N Montezuma Street, Prescott, AZ 86301. Phone: 928-777-1371, email: buildingpermits@prescott-az.gov. Office hours: Monday - Friday, 8 a.m. - 5 p.m. Applications are submitted online through the PrescottPermits.com portal (all permit types, including plan-reviewed and same-day Fast Track permits). On-site building inspections are performed Monday through Friday, 8 a.m. to 3 p.m., except City holidays; inspections can be scheduled online as early as the next business day (up to 5 business days out) if requested before midnight. Note: the City's Building Permit application checklists (rev. 2023-2024) list an older office address of 201 S Cortez St, Prescott, AZ 86303 — the current Permit Center pages (2025-2026 vintage) consistently list 201 N Montezuma Street, Prescott, AZ 86301, which is used here as the verified current address.. Official information: https://prescott-az.gov/permit-center/.

Prescott, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The City of Prescott's Community Development Department (Building Division) independently adopts and administers its own construction codes and Permit Center program; it does not defer permitting to Yavapai County. Source: City of Prescott Permit Center / Building Permits page (prescott-az.gov/permit-center/permit-categories/building-permits/).; 2024 International Building Code (IBC), as published by the International Code Council, adopted by the City of Prescott with local amendments codified at Prescott City Code Chapter 3, Article 3-1, 3-2, and 3-5. Currently in effect for plan review. Source: City of Prescott Building Permits page, '2024 Codes-Design Criteria' handout (rev. 01/01/2026), and Prescott City Code (codepublishing.com/AZ/Prescott).; 2024 International Residential Code (IRC) for One- and Two-Family Dwellings, adopted by reference with City of Prescott amendments (Prescott City Code Article 3-8). Source: City of Prescott '2024 Codes-Design Criteria' handout (rev. 01/01/2026).; 2024 International Mechanical Code (IMC), adopted with City of Prescott amendments. Source: City of Prescott '2024 Codes-Design Criteria' handout (rev. 01/01/2026); 2024 IMC Significant Changes handout.; 2024 International Plumbing Code (IPC), adopted with City of Prescott amendments (Prescott City Code Article 3-6). Source: City of Prescott '2024 Codes-Design Criteria' handout (rev. 01/01/2026); 2024 IPC Significant Changes handout.; 2023 National Electrical Code (NEC), adopted with City of Prescott amendments (Prescott City Code Article 3-7) — one edition behind the 2024 ICC set, matching the standard NFPA 3-year NEC cycle. Source: City of Prescott '2024 Codes-Design Criteria' handout (rev. 01/01/2026); 2023 NEC Significant Changes handout.; 2024 International Fuel Gas Code (IFGC), adopted with City of Prescott amendments. Source: City of Prescott '2024 Codes-Design Criteria' handout (rev. 01/01/2026).; 2024 International Existing Building Code (IEBC), adopted with City of Prescott amendments. Source: City of Prescott '2024 Codes-Design Criteria' handout (rev. 01/01/2026); 2024 IEBC Significant Changes handout.; 2024 International Fire Code (IFC), adopted by reference (Prescott City Code Article 6-1) as the City's uniform fire code, with a dedicated Urban-Wildland Interface amendment (Article 6-2) administered by the Prescott Fire Department. Source: City of Prescott '2024 Codes-Design Criteria' handout; Prescott City Code Article 6-1/6-2.; 2012 International Energy Conservation Code (IECC), adopted with City of Prescott amendments (Prescott City Code Article 3-18) — the City has NOT moved to a newer IECC edition; energy compliance for the 2024 code cycle is still evaluated under the 2012 IECC Climate Zone 4B tables. Source: City of Prescott '2024 Codes-Design Criteria' handout (rev. 01/01/2026), which explicitly lists '2012 International Energy Conservation Code (IECC)' alongside the otherwise-2024 code set.; City of Prescott Administrative Building Code (Prescott City Code Article 3-17) governs permit administration, application processing, plan review, and issuance procedures citywide, overriding the ICC model codes' own administrative chapters where they conflict. Source: Prescott City Code Article 3-17 (codepublishing.com/AZ/Prescott).. Local amendments apply — see the Prescott overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Prescott building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.