EV Charger / EVSE Permit — Prescott, Arizona · Requirements sheet
Verified 2026-07-20 · Source: https://prescott-az.gov/wp-content/uploads/2025/09/FIN-City-Wide-Fee-Schedule_All-Departments-20250909.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Prescott, Arizona
The City of Prescott has no EV-charger-specific permit type or fee. Per the City's 'What Needs a Permit' matrix, 'ELECTRICAL ADDITION/MOVE/DEMO' requires a permit, and an EV charger circuit is filed under the standard 'Electrical Only' permit's 'Adding Circuits or Outlets' scope (Electrical Only Checklist), governed by the 2023 NEC as adopted by the City. Direct review of the City's Fast Track Permit Checklist confirms the program covers exactly seven scopes — HVAC like-for-like, Water Heater like-for-like, Accessory Structure Demolition, Re-Roof Non-Structural, Window and Door like-for-like, Interior plumbing repair/replace, and Electrical Panel Replacement up to 200 amps — and an EV charger circuit addition is NOT among them, so it does not qualify for the Fast Track program's flat $66 issue fee and must go through standard Electrical Only review. The City's Building Valuation and Fee Estimator publishes electrical fees primarily in a new-construction context, but the City's own Council-adopted FY2026 Citywide Fee Schedule confirms the governing rate: an 'E/M/P Permit Residential - Electrical' line of $0.0396 per square foot, with the parallel Commercial E/M/P Electrical line explicitly labeled 'Valuation/min $66.00' -- establishing a $66.00 practical minimum permit fee that applies across the E/M/P schedule. A typical EV charger circuit retrofit (small scope, valuation far below the City's $14,000 building-permit-fee threshold) is billed at this $66.00 minimum.
Verified 2026-07-20 · Source
When you need this permit
- Electrical permit required for an EV charger circuit — filed under the Electrical Only permit's 'Adding Circuits or Outlets' scope
- Governed by the 2023 NEC as adopted by the City of Prescott
- Electrical Schematic / Floor Plan required, showing locations of new and existing circuits or outlets, circuit amperage, GFCI/AFCI requirements, and appliance requirements for specialized equipment
- NOT eligible for the Fast Track Permit (FTP) program — the FTP's seven eligible scopes do not include EV chargers or general circuit additions (only 'Electrical Panel Replacement up to 200 amps' is FTP-eligible among electrical work)
- If the installation requires a new service entrance/upgrade, additional documentation (one-line diagram, panel schedule, load calculations, or full engineered stamped documents for 600+ amp services) is required per the Electrical Only Checklist
- Submit via the PrescottPermits.com online portal
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
EVSE circuit wiring, box placement, and panel connections before walls are closed
- 2
Final
Charger installed, panel labeled, protections verified per 2023 NEC
See the full Prescott inspection guide — scheduling & re-inspection fees →
Tips
- An EV charger circuit does NOT qualify for Prescott's Fast Track Permit (FTP) program — only 'Electrical Panel Replacement up to 200 amps' is FTP-eligible among electrical scopes; a new EVSE circuit must go through the standard Electrical Only Checklist ('Adding Circuits or Outlets' section).
- The City's published Building Valuation and Fee Estimator is oriented around new construction (square-footage-based multipliers); it does not clearly price a standalone retrofit circuit-addition permit — call Building Safety to confirm the exact fee before applying.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Prescott building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Prescott
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Arizona →
Look up this fee in a different city →