Change of Use / Certificate of Occupancy Permit in Prescott, Arizona
Required in the City of Prescott whenever the use of an existing building changes to a different Use Category. Prescott Land Development Code Sec. 9.2.1.B makes a certificate of occupancy mandatory for a 'change in use of an existing building to a different Use Category as set forth in Sec. 11.1', alongside the ordinary new-construction trigger at Sec. 9.2.1.A. The Building Official issues the certificate and the Community Development Director reviews every request to confirm the intended use, building or structure complies with all applicable Code regulations and standards and with the approved building and site plan. Prescott files this as its own CERTIFICATE OF OCCUPANCY permit type (prefix B), which the City lists as NOT available for online submittal - applicants must contact the Building Division directly.
Reviewed 2026-08-15 · Source
When you need this permit
- A certificate of occupancy is required for (A) occupancy and use of a building hereafter erected or enlarged, and (B) change in use of an existing building to a different Use Category as set forth in Land Development Code Sec. 11.1 (Prescott LDC Sec. 9.2.1)
- The Building Official holds the authority to issue building permits meeting the International Building Codes, the City of Prescott General Engineering Standards, and the Land Development Code, and is vested with authority to approve certificates of occupancy for projects completed in accordance with approved plans (LDC Sec. 9.2.2, citing Prescott City Code Titles III and VI)
- When the contractor believes a structure or use is ready for occupancy, a final inspection for a certificate of occupancy must be requested of the Building Official or designee (LDC Sec. 9.2.3.A)
- The Community Development Director or designee reviews all certificate of occupancy requests to determine whether intended uses, buildings or structures comply with all applicable Code regulations and standards and with the approved building and site plan (LDC Sec. 9.2.3.B)
- The Building Official inspects the use or structure and issues the certificate of occupancy only if it complies with all applicable provisions of the building code, the City of Prescott General Engineering Standards, and the Land Development Code (LDC Sec. 9.2.3.C)
- A temporary certificate of occupancy may be issued pending the permanent certificate, valid for a period established by the Building Official and the Community Development Director, pending completion of improvements or during partial occupancy; bonding at 125 percent of the estimated improvement costs may be required for outstanding improvements (LDC Sec. 9.2.4)
- It is unlawful to occupy any building that does not have a valid certificate of occupancy or temporary certificate of occupancy, except where the building was constructed or occupied before LDC Sec. 9.2 took effect (LDC Sec. 9.2.5)
- The CERTIFICATE OF OCCUPANCY permit type (permit prefix B) is NOT available for online submittal through the PrescottPermits.com portal - the City directs applicants to contact the Building Division at buildingpermits@prescott-az.gov or 928-777-1371 (City of Prescott Permit Type & Subtype Descriptions handout, page 10 of 10)
- Depending on the new Use Category, a use change may also require a separate zoning approval with its own fee - for example a Conditional Use Permit under LDC Sec. 9.3 ($1,302.28), a Special Use Permit under LDC Sec. 9.9 ($1,803.15 general), or a Temporary Use Permit under LDC Sec. 9.11 ($200.35)
- Where the change of use changes water demand, the City charges a separate Water Service Agreement - Change Of Use fee ($203.94)
- A change of use accompanied by construction work is permitted separately as a Commercial Tenant Improvement and Remodel building permit, which carries its own published review timeline of 25 business days for round 1 and 12 business days for additional rounds
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Final Occupancy Inspection
Requested of the Building Official or designee when the contractor believes the structure or use is ready for occupancy; the Building Official inspects the use or structure and issues the certificate of occupancy only on determining that it complies with all applicable provisions of the building code, the City of Prescott General Engineering Standards, and the Land Development Code (Prescott LDC Sec. 9.2.3.A and 9.2.3.C)
See the full Prescott inspection guide — scheduling & re-inspection fees →
Tips
- Prescott's change-of-use trigger is the Use Category, not the tenant. Land Development Code Sec. 9.2.1.B requires a new certificate of occupancy only when the use of an existing building changes to a DIFFERENT Use Category as set forth in LDC Sec. 11.1 - so a like-for-like tenant swap within the same category is a different situation from, say, retail moving to assembly. Check your proposed use against Sec. 11.1 before assuming which applies.
- This permit type cannot be filed online. The City's Permit Type & Subtype Descriptions handout lists CERTIFICATE OF OCCUPANCY (prefix B) in its 'NOT AVAILABLE FOR ONLINE PERMITTING' table on page 10, directing applicants to the Building Division at buildingpermits@prescott-az.gov or 928-777-1371. Do not expect to find it as a selectable type in the PrescottPermits.com portal.
- A temporary certificate of occupancy in Prescott has no fixed statutory duration - LDC Sec. 9.2.4 leaves the validity period to be established by the Building Official and the Community Development Director, and permits bonding at 125 percent of estimated improvement costs for outstanding work. Budget $802.00 (commercial) or $401.00 (residential) for it.
- Occupying without a valid certificate is expressly unlawful under LDC Sec. 9.2.5, with the only carve-out being buildings constructed or occupied before Sec. 9.2 took effect.
- Budget for the zoning side separately. If the new Use Category is not permitted by right, a Conditional Use Permit ($1,302.28) or a general Special Use Permit ($1,803.15) is a separate Planning application on top of the certificate of occupancy, and a use change that alters water service adds a $203.94 Water Service Agreement - Change Of Use fee.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-08-15.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Prescott building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Prescott
Change of Use / Certificate of Occupancy Permit in other cities
Compare change of use / certificate of occupancy permit fees across Arizona →
Look up this fee in a different city →
Now live
Build your Prescott project checklist
Describe your project once and get every permit, document, and fee it triggers in Prescott — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →