Required for plumbing installation, alteration, or repair work in Prescott, governed by the 2024 International Plumbing Code (IPC) as adopted and amended by the City of Prescott. Interior plumbing repair/replacement and water heater like-for-like replacement both qualify for the Fast Track expedited program.

Verified 2026-07-06 · Source

When you need this permit

  • Plumbing permit required for interior plumbing repair/replacement, new/repaired/replaced gas yardlines, and water heater changes (including change of fuel type)
  • Governed by the 2024 IPC as adopted by the City of Prescott
  • Interior Plumbing Repair or Replace requires an Interior Plumbing Plan showing water/sewer/gas line locations, piping length/material/size, and (for gas repairs) BTUs and total developed piping length
  • New Gas Yardline or Gas Yardline Repair/Replace requires a full site plan showing meter location, connection point, dielectric union and shut-off, existing yardlines, and piping material/length/size
  • Water Heater Change of Fuel Type requires a sealed structural plan/calculations (if applicable) plus a site plan with water and sewer service details per City Standard Details 316P and 440P-3
  • Interior plumbing repair/replace and like-for-like water heater replacement qualify for the Fast Track Permit (FTP) program
  • Submit via the PrescottPermits.com online portal

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Plumbing Fee (new construction context), 3+ Unit/CommercialCity of Prescott Building Valuation and Fee Estimator, 3+ Unit/Commercial worksheet (the 1-2 Unit Residential worksheet groups Plumbing into the combined M,P,FG&E $0.0396/sf rate)
Total building square footage × $0.0792
Fast Track Permit (FTP) FeeCity of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025); applies to Water Heater like-for-like and Interior Plumbing Repair or Replace
$66.00
Fast Track Permit (FTP) Issue FeeCity of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025)
$66.00

Review timeline

Plan reviewPrescott’s published plan-review target
0–5 business days

How long did your Plumbing Only Permit permit actually take in Prescott?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Underground/Slab

    Before concrete pour — verify pipe slope, materials, cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed

  3. 3

    Final

    Fixtures connected, water heater and gas connections verified, no leaks

See the full Prescott inspection guide — scheduling & re-inspection fees →

Tips

  • Water Heater like-for-like replacement and Interior Plumbing Repair or Replace are both Fast Track-eligible (no plan review round, on-site verified), while plumbing fixture replacement alone needs no permit at all per the City's 'What Needs a Permit' matrix — but any plumbing addition, move, or demolition does require a standard permit.
  • Water Heater Change of Fuel Type is NOT Fast Track-eligible — it requires sealed structural plans/calculations and full site-plan documentation of water/sewer service details.
  • Gas yardline work must show dielectric union and house-side shut-off placement, plus all existing and proposed yardline routing on the site plan.

Frequently asked questions

Yes. A like-for-like water heater replacement qualifies for the City's Fast Track Permit (FTP) program (no plans required, on-site verified), but a water heater change of fuel type requires the full Plumbing Only Checklist with sealed structural plans/calculations if applicable.

In Prescott, the published Plumbing Fee (new construction context), 3+ Unit/Commercial is: Total building square footage × $0.0792. Additional published fees: Fast Track Permit (FTP) Fee — $66.00; Fast Track Permit (FTP) Issue Fee — $66.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Fast Track-eligible plumbing work (water heater like-for-like, interior plumbing repair/replace) has no plan-review round — it is verified on-site. Plumbing scope requiring plan review is not separately itemized on the City's Plan Review Timeline table, so it defaults to at least the 5-business-day Administrative Completeness Check that applies to all permits.

You'll need: Plumbing Only Checklist. Depending on your project, Prescott may also ask for: Fast Track Permit Checklist. See the required-documents checklist on this page for details on each.

Prescott requires 3 inspection(s) for a plumbing only permit, in order: Underground/Slab, Rough-In, Final. Schedule each through City of Prescott Community Development Department — Building Division / Permit Center (928-777-1371).

Apply through City of Prescott Community Development Department — Building Division / Permit Center at 201 N Montezuma Street, Prescott, AZ 86301. Phone: 928-777-1371, email: buildingpermits@prescott-az.gov. Office hours: Monday - Friday, 8 a.m. - 5 p.m. Applications are submitted online through the PrescottPermits.com portal (all permit types, including plan-reviewed and same-day Fast Track permits). On-site building inspections are performed Monday through Friday, 8 a.m. to 3 p.m., except City holidays; inspections can be scheduled online as early as the next business day (up to 5 business days out) if requested before midnight. Note: the City's Building Permit application checklists (rev. 2023-2024) list an older office address of 201 S Cortez St, Prescott, AZ 86303 — the current Permit Center pages (2025-2026 vintage) consistently list 201 N Montezuma Street, Prescott, AZ 86301, which is used here as the verified current address.. Official information: https://prescott-az.gov/permit-center/.

Prescott, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The City of Prescott's Community Development Department (Building Division) independently adopts and administers its own construction codes and Permit Center program; it does not defer permitting to Yavapai County. Source: City of Prescott Permit Center / Building Permits page (prescott-az.gov/permit-center/permit-categories/building-permits/).; 2024 International Building Code (IBC), as published by the International Code Council, adopted by the City of Prescott with local amendments codified at Prescott City Code Chapter 3, Article 3-1, 3-2, and 3-5. Currently in effect for plan review. Source: City of Prescott Building Permits page, '2024 Codes-Design Criteria' handout (rev. 01/01/2026), and Prescott City Code (codepublishing.com/AZ/Prescott).; 2024 International Residential Code (IRC) for One- and Two-Family Dwellings, adopted by reference with City of Prescott amendments (Prescott City Code Article 3-8). Source: City of Prescott '2024 Codes-Design Criteria' handout (rev. 01/01/2026).; 2024 International Mechanical Code (IMC), adopted with City of Prescott amendments. Source: City of Prescott '2024 Codes-Design Criteria' handout (rev. 01/01/2026); 2024 IMC Significant Changes handout.; 2024 International Plumbing Code (IPC), adopted with City of Prescott amendments (Prescott City Code Article 3-6). Source: City of Prescott '2024 Codes-Design Criteria' handout (rev. 01/01/2026); 2024 IPC Significant Changes handout.; 2023 National Electrical Code (NEC), adopted with City of Prescott amendments (Prescott City Code Article 3-7) — one edition behind the 2024 ICC set, matching the standard NFPA 3-year NEC cycle. Source: City of Prescott '2024 Codes-Design Criteria' handout (rev. 01/01/2026); 2023 NEC Significant Changes handout.; 2024 International Fuel Gas Code (IFGC), adopted with City of Prescott amendments. Source: City of Prescott '2024 Codes-Design Criteria' handout (rev. 01/01/2026).; 2024 International Existing Building Code (IEBC), adopted with City of Prescott amendments. Source: City of Prescott '2024 Codes-Design Criteria' handout (rev. 01/01/2026); 2024 IEBC Significant Changes handout.; 2024 International Fire Code (IFC), adopted by reference (Prescott City Code Article 6-1) as the City's uniform fire code, with a dedicated Urban-Wildland Interface amendment (Article 6-2) administered by the Prescott Fire Department. Source: City of Prescott '2024 Codes-Design Criteria' handout; Prescott City Code Article 6-1/6-2.; 2012 International Energy Conservation Code (IECC), adopted with City of Prescott amendments (Prescott City Code Article 3-18) — the City has NOT moved to a newer IECC edition; energy compliance for the 2024 code cycle is still evaluated under the 2012 IECC Climate Zone 4B tables. Source: City of Prescott '2024 Codes-Design Criteria' handout (rev. 01/01/2026), which explicitly lists '2012 International Energy Conservation Code (IECC)' alongside the otherwise-2024 code set.; City of Prescott Administrative Building Code (Prescott City Code Article 3-17) governs permit administration, application processing, plan review, and issuance procedures citywide, overriding the ICC model codes' own administrative chapters where they conflict. Source: Prescott City Code Article 3-17 (codepublishing.com/AZ/Prescott).. Local amendments apply — see the Prescott overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Prescott building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.