Required for new single-family residential construction in the City of San Luis. Reviewed against the 2018 IRC as adopted and amended by City of San Luis Ordinance No. 390. Applications are submitted to the Development Services Department, Building Safety Division.

Verified 2026-07-06 · Source

When you need this permit

  • Building permit required for new single-family residential construction within San Luis city limits
  • Plans must comply with the 2018 IRC as adopted and amended by City of San Luis Ordinance No. 390
  • Complete Building Permit Application with project address, subdivision name, APN, and valuation
  • Complete set of construction plans/drawings showing full scope of work; electronic PDF preferred, or 2 hard-copy sets for residential
  • Site Plan required
  • Work must be performed by a duly licensed Arizona contractor unless the owner will solely occupy the structure (owner-builder exception, subject to A.R.S. §§ 32-1151/32-1154 penalties if violated) Owner-builder
  • Permit becomes null and void if work does not begin within 180 days of issuance, or is suspended/abandoned for 180 days

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Based on ValuationCity of San Luis Development Services and Public Works Application and Permit — Notice and Proposed Fees, Schedule of Building Permit Fees (IBC/IRC/IEBC/IPMC); valuation determined using ICC Building Valuation Data published each February in Building Safety Magazine
$50 (valuation $1-$500); $50 + $4 per additional $100 to $2,000; $80 + $16 per additional $1,000 to $25,000; $450 + $12 per additional $1,000 to $50,000; $740 + $8 per additional $1,000 to $100,000; $1,140 + $6 per additional $1,000 to $500,000; $3,720 + $6 per additional $1,000 to $1,000,000; $6,450 + $4 per additional $1,000 above $1,000,000
Plan Check Fee (Residential)City of San Luis Development Services and Public Works Application and Permit — Notice and Proposed Fees; paid at time of application submittal; includes up to 3 resubmittals
65% of Building Permit Fee
Deposit for Residential Plan Check (remodel/addition)Credited toward the Plan Check fee when the Building Permit is purchased
$75
Reissue Certificate of OccupancyCity of San Luis Development Services and Public Works Application and Permit — Notice and Proposed Fees
$50

Review timeline

Plan reviewSan Luis’s published plan-review target
6–11 business days

How long did your Residential Building Permit (New Construction) permit actually take in San Luis?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation/Footing

    Before concrete pour

  2. 2

    Framing

    Structural framing and connections per 2018 IRC

  3. 3

    Final

    All work complete per approved plans; scheduled via the Inspection Hot Line (928) 341-8564

See the full San Luis inspection guide — scheduling & re-inspection fees →

Tips

  • Per the City's official A.R.S. § 9-835 Building Permit Processing Time Frames document, 'Residential Building – New' carries a 1-business-day Administrative Completeness Review, 5 business days for 1st plan review, and 5 more for 2nd review if needed — 11 business days overall (6 days minimum if no 2nd review is required).
  • The Fee for all Permits includes the Plan Check (up to 3 resubmittals) and 2 inspections per phase — additional resubmittals or re-inspections beyond that are billed at $50/hour (1/2-hour minimum).
  • Building valuation is refreshed at the start of each fiscal year using the February ICC Building Safety Magazine valuation data, so the exact dollar breakpoints in the Building Permit Fee table can shift year to year.

Frequently asked questions

San Luis requires a residential building permit (new construction) for: Building permit required for new single-family residential construction within San Luis city limits; Plans must comply with the 2018 IRC as adopted and amended by City of San Luis Ordinance No. 390; Complete Building Permit Application with project address, subdivision name, APN, and valuation; Complete set of construction plans/drawings showing full scope of work; electronic PDF preferred, or 2 hard-copy sets for residential; Site Plan required; Work must be performed by a duly licensed Arizona contractor unless the owner will solely occupy the structure (owner-builder exception, subject to A.R.S. §§ 32-1151/32-1154 penalties if violated); Permit becomes null and void if work does not begin within 180 days of issuance, or is suspended/abandoned for 180 days. If your project isn't listed, confirm with City of San Luis Development Services Department — Building Safety Division at 928-341-8565 before starting work.

In San Luis, the published Building Permit Fee — Based on Valuation is: $50 (valuation $1-$500); $50 + $4 per additional $100 to $2,000; $80 + $16 per additional $1,000 to $25,000; $450 + $12 per additional $1,000 to $50,000; $740 + $8 per additional $1,000 to $100,000; $1,140 + $6 per additional $1,000 to $500,000; $3,720 + $6 per additional $1,000 to $1,000,000; $6,450 + $4 per additional $1,000 above $1,000,000. Additional published fees: Plan Check Fee (Residential) — 65% of Building Permit Fee; Deposit for Residential Plan Check (remodel/addition) — $75; Reissue Certificate of Occupancy — $50. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Per the City of San Luis's A.R.S. § 9-835 Building Permit Processing Time Frames document, a new Residential Building permit has a 1-business-day administrative completeness review, 5 business days for first plan review, and up to 5 more business days for a second review if needed — an overall timeline of 11 business days (6 if no second review is required).

You'll need: Building Permit Application; Construction Plans/Drawings; Site Plan. See the required-documents checklist on this page for details on each.

San Luis requires 3 inspection(s) for a residential building permit (new construction), in order: Foundation/Footing, Framing, Final. Schedule each through City of San Luis Development Services Department — Building Safety Division (928-341-8565).

Apply through City of San Luis Development Services Department — Building Safety Division at P.O. Box 3750 - 1090 E. Union Street, San Luis, AZ 85349. Phone: 928-341-8565, email: jcampa@sanluisaz.gov. Office hours: City Hall general hours Mon-Fri 7 a.m.-6 p.m. Building Safety Division office line (928) 341-8565; dedicated Inspection Line/Hot Line for scheduling inspections is (928) 341-8564 (also available via online inspection scheduling). Building Permit Applications may be submitted with a complete set of plans/drawings (electronic PDF preferred; if hard copy, 2 sets for residential, 3 sets for commercial).. Official information: https://www.sanluisaz.gov/departments/development_services/building_safety/building_permits.php.

San Luis, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The City of San Luis independently adopts and administers its own construction codes through its Development Services Department, Building Safety Division. Source: City of San Luis Building Inspections & Codes page (sanluisaz.gov/departments/development_services/building_safety/building_inspections_codes).; 2018 International Building Code (IBC), adopted by reference as the City's current uniform building code. Source: City of San Luis Building Inspections & Codes page, 'Current Codes' list, verified live July 2026.; 2018 International Residential Code (IRC), adopted by reference as the City's current one- and two-family dwelling code. Source: City of San Luis Building Inspections & Codes page, verified live July 2026.; 2018 International Existing Building Code (IEBC), adopted by reference, governing repair, alteration, addition, and change of occupancy of existing buildings. Source: City of San Luis Building Inspections & Codes page, verified live July 2026.; 2018 International Swimming Pool and Spa Code (ISPSC), adopted by reference, governing swimming pool, spa, and pool barrier construction. Source: City of San Luis Building Inspections & Codes page, verified live July 2026.; 2018 International Property Maintenance Code (IPMC), adopted by reference, governing maintenance of existing structures and premises. Source: City of San Luis Building Inspections & Codes page, verified live July 2026.; 2014 National Electrical Code (NEC), as published by the National Fire Protection Association, adopted by reference — one edition behind the current 2023 NEC cycle used by several neighboring Arizona cities; independently confirmed still listed as current on the City's live Building Inspections & Codes page as of July 2026 (not simply carried over from a stale directory). Source: City of San Luis Building Inspections & Codes page, verified live July 2026.; 2012 International Mechanical Code (IMC), adopted by reference — independently confirmed still listed as current on the City's live Building Inspections & Codes page as of July 2026. Source: City of San Luis Building Inspections & Codes page, verified live July 2026.; 2012 International Plumbing Code (IPC), adopted by reference — independently confirmed still listed as current on the City's live Building Inspections & Codes page as of July 2026. Source: City of San Luis Building Inspections & Codes page, verified live July 2026.; 2009 International Energy Conservation Code (IECC), adopted by reference — independently confirmed still listed as current on the City's live Building Inspections & Codes page as of July 2026; this is a notably older energy-code edition than most Arizona municipalities' current adoptions. Source: City of San Luis Building Inspections & Codes page, verified live July 2026.; All of the above codes (2018 IBC, IRC, IEBC, ISPSC, IPMC; 2014 NEC; 2012 IMC, IPC; 2009 IECC) are amended by City of San Luis Ordinance No. 390, per the City's Building Inspections & Codes page. The full text of Ordinance No. 390 was not separately located on the live site as a standalone downloadable document during this verification pass; the codes-adopted list itself is sourced directly to the City's official Building Inspections & Codes webpage, which is the authoritative live citation. Source: City of San Luis Building Inspections & Codes page (sanluisaz.gov/departments/development_services/building_safety/building_inspections_codes).; Manufactured homes and mobile homes: the City's Development Services fee schedule notes Manufactured Home (MH) Permit Fees for pit-set and ground-set installations are now referred to the 'State of AZ' rather than a City-set flat fee (Arizona Department of Fire, Building and Life Safety / Office of Manufactured Housing regulates factory-built construction/installation standards per A.R.S. § 41-4001 et seq.); the City separately issues a Building Permit Processing Time Frame track for 'Manufactured Home' and 'Park Model' placement (2 business days 1st review, 2 business days 2nd review, 5 business days overall). Source: City of San Luis Development Services and Public Works Application and Permit — Notice and Proposed Fees document; City of San Luis Building Permit Processing Time Frames (A.R.S. § 9-835 compliance document).. Local amendments apply — see the San Luis overview page for the full list.

The 2018 International Residential Code (IRC), as adopted and amended by City of San Luis Ordinance No. 390, per the City's Building Inspections & Codes page.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the San Luis building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.