EV Charger / EVSE Permit (Electrical Permit) — San Luis, Arizona · Requirements sheet
Reviewed 2026-08-16 · Source: https://www.sanluisaz.gov/departments/development_services/building_safety/building_permits.php
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit (Electrical Permit) in San Luis, Arizona
The City of San Luis has no dedicated EV charger/EVSE permit type or fee line — unlike solar PV, which received a dedicated flat-fee tier explicitly labeled '(NEW) Solar Photovoltaic System Permit Fees' on the City's Development Services fee schedule, no equivalent EV-charger line exists on that same document. An EV charging station (Level 2 or DC fast charger) installation is instead processed and billed as a standard Electrical Permit, governed by the 2014 National Electrical Code (NEC) as adopted and amended by City of San Luis Ordinance No. 390, using the same itemized component fee schedule (base issuance fee plus per-circuit/per-panel add-ons) documented in the electrical-permit entry.
Reviewed 2026-08-16 · Source
When you need this permit
- Electrical permit required for the EV charger's dedicated circuit (branch circuit), any feeder circuit, and any service panel upgrade needed to support the charger's load
- Governed by the 2014 NEC as adopted by City of San Luis Ordinance No. 390
- Complete the Building/Electrical Permit Application listing the electrical subcontractor's name, phone, and license number
- Contractor must hold a City of San Luis Business License and Arizona ROC license number Contractor
- If the EV charger installation requires a service panel upgrade (e.g., to accommodate a new 40-60A circuit), that scope is billed under the same electrical permit's per-panel-size fee tier
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
City of San Luis Resolution No. 2306, Exhibit A (adopted by Mayor and Council 2024-05-22), Development Services Department / Building Safety Division fee schedule, council packet page 239 within… Show full citationHide
City of San Luis Resolution No. 2306, Exhibit A (adopted by Mayor and Council 2024-05-22), Development Services Department / Building Safety Division fee schedule, council packet page 239 within pages 236-241 of https://public.destinyhosted.com/sanludocs/2024/CC/20240522_1882/AGENDApacket__05-22-24_0636_1881.pdf. Read the figures from the packet page as published rather than from a copy-paste. No EV/EVSE-specific line exists; an EV charger circuit is billed under the standard electrical schedule.City of San Luis Resolution No. 2306, Exhibit A (adopted by Mayor and Council 2024-05-22), Development Services Department / Building Safety Division fee schedule, council packet pages 236-241 of… Show full citationHide
City of San Luis Resolution No. 2306, Exhibit A (adopted by Mayor and Council 2024-05-22), Development Services Department / Building Safety Division fee schedule, council packet pages 236-241 of https://public.destinyhosted.com/sanludocs/2024/CC/20240522_1882/AGENDApacket__05-22-24_0636_1881.pdf, packet page 240. A dedicated EV charger circuit draws this charge.City of San Luis Resolution No. 2306, Exhibit A (adopted by Mayor and Council 2024-05-22), Development Services Department / Building Safety Division fee schedule, council packet pages 236-241 of… Show full citationHide
City of San Luis Resolution No. 2306, Exhibit A (adopted by Mayor and Council 2024-05-22), Development Services Department / Building Safety Division fee schedule, council packet pages 236-241 of https://public.destinyhosted.com/sanludocs/2024/CC/20240522_1882/AGENDApacket__05-22-24_0636_1881.pdf. Packet page 239. Read the figures from the pages as published rather than from a copy-paste.City of San Luis Resolution No. 2306, Exhibit A (adopted by Mayor and Council 2024-05-22), Development Services Department / Building Safety Division fee schedule, council packet pages 236-241 of… Show full citationHide
City of San Luis Resolution No. 2306, Exhibit A (adopted by Mayor and Council 2024-05-22), Development Services Department / Building Safety Division fee schedule, council packet pages 236-241 of https://public.destinyhosted.com/sanludocs/2024/CC/20240522_1882/AGENDApacket__05-22-24_0636_1881.pdf; this line sits on packet page 239. Read the figures from the page as published rather than from a copy-paste. Applies where a panel upgrade accompanies the charger.City of San Luis Resolution No. 2306, Exhibit A (adopted by Mayor and Council 2024-05-22), Development Services Department / Building Safety Division fee schedule, council packet page 239 within… Show full citationHide
City of San Luis Resolution No. 2306, Exhibit A (adopted by Mayor and Council 2024-05-22), Development Services Department / Building Safety Division fee schedule, council packet page 239 within pages 236-241 of https://public.destinyhosted.com/sanludocs/2024/CC/20240522_1882/AGENDApacket__05-22-24_0636_1881.pdf.Review timeline
Inspection process
- 1
Rough-In
Circuit wiring, box placement, and panel connections before walls are closed, if applicable
- 2
Final
Charger mounted, connections verified, panel labeled, verified per 2014 NEC before energizing
See the full San Luis inspection guide — scheduling & re-inspection fees →
Tips
- Unlike solar PV, which has its own dedicated flat-fee tier ($150 or $350 by system size), San Luis has no dedicated EV-charger fee line — an EV charger circuit is billed under the standard Electrical Permit's itemized component fees (base $50 issuance plus per-circuit/per-panel add-ons).
- Per the A.R.S. § 9-835 timeframes document, 'Residential Building – Elec./Plumb./Mech.' is 1/5/5 business days (11 total, 6 if no 2nd review needed) — the same timeframe category the electrical-permit entry documents, applied here since EV chargers fall under the same permit type.
- If a panel upgrade is needed to support the EV charger's circuit, budget for the separate service-entrance-panel fee tier ($20-$60 depending on amperage) in addition to the base issuance and branch-circuit fees.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-08-16.
Fee schedules
Online permit portal
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the San Luis building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
San Luis's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for San Luis yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when San Luis lands. Privacy.
Other permits in San Luis
EV Charger / EVSE Permit (Electrical Permit) in other cities
Compare ev charger / evse permit (electrical permit) fees across Arizona →
Look up this fee in a different city →