Required whenever an existing building's use or occupancy classification changes in Brighton — for example, converting a retail space to a restaurant. Brighton does not publish a single consolidated 'Change of Occupancy' guidance page the way some peer Colorado cities (e.g., Aurora) do; the same underlying requirement is instead enforced through three real, distinct City mechanisms: the 2021 IBC (Section 111, as adopted) makes it unlawful to occupy a building under a use different from its most recent Certificate of Occupancy; a Business License (Municipal Code Chapter 5) is required of any business with a physical location in the City and is the practical front door that surfaces a use change for review; and the City's own Commercial CO checklist requires sign-off from Brighton Fire, Public Works, and the Development Services Manager (Planning) plus Building final inspections before a new or amended CO is issued.

Verified 2026-08-13 · Source

When you need this permit

  • The 2021 IBC (Section 111), as adopted by the City of Brighton, makes it unlawful to use or occupy a building or portion thereof for a purpose other than that shown on its most recent Certificate of Occupancy; a new or amended CO is required whenever the use or occupancy classification changes, whether or not construction work accompanies the change
  • Any business with a physical location within the City of Brighton is required to hold an active Business License (Municipal Code Chapter 5), filed through the City's Munirevs portal (brightonco.munirevs.com); renewal and new applications 'are subject to review and approval to ensure compliance with the City's code,' and additional licenses, permits, or approvals may be required depending on business type
  • Confirmation that the newly proposed use is allowed within the property's zoning district should be obtained from the Planning Division via a Zoning Verification Letter (planner@brightonco.gov, or the Planner on Duty at 303-655-2072) before proceeding with a lease or business license application
  • Where the change of use involves construction, remodeling, or tenant-improvement work, this file's Commercial Tenant Improvement / Nonresidential Permit entry applies (2021 IBC-governed building permit, Permit Checklist: Com, Ind, MF document set)
  • Issuance of a new or amended Certificate of Occupancy — whether or not construction work is involved — follows the same multi-department sign-off documented on the City's own Commercial CO checklist: approval/final inspection from Brighton Fire (Brighton Fire Rescue District, logged in OpenGov), approval from Public Works, approval from the Development Services Manager (Planning), all passed Building final inspections (permit card uploaded to the portal), and closure of all related permits (sprinkler, alarm, retaining wall, landscape, etc.)
  • A Temporary Certificate of Occupancy (TCO) requires written approval from Fire, Public Works, and Planning, with all life-health-safety concerns addressed; TCOs are NOT available for Group R (residential) occupancies
  • Certificate-of-Occupancy requests and related comments are processed via OpenGov and cannot be handled at the permit counter

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Business License (general business and sales tax license)Per the City's own Business Licensing page: 'no fee to apply for a general business and sales tax license.' Additional license types/fees may apply depending on business category (Municipal Code Chapter 5 / Specialty Licensing)
No fee to apply
Request for Information / Zoning Verification2026 Community Development Fee Schedule, Attachment 3 — covers zoning verification, allowed uses/non-conforming use determination, and written code interpretation
$50.00 for the first hour, $25.00 per hour for each additional hour in the same request
Building Permit Fee and Plan Review Fee (only if construction/TI work accompanies the change of use)Follows this file's Commercial Tenant Improvement / Nonresidential Permit fee basis; not charged for a use change involving zero construction
$23.50 minimum, scaling per the valuation tiers in the 2026 Community Development Fee Schedule

Review timeline

Plan review
Not published — contact the department

How long did your Change of Occupancy / Change of Use Permit permit actually take in Brighton?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Zoning Use-Conformance Review

    Planning Division confirms, via a Zoning Verification Letter, that the newly proposed use is allowed within the property's zoning district

  2. 2

    Fire Final Inspection / Approval

    Brighton Fire Rescue District approval logged in the City's OpenGov system, required per the Commercial CO checklist

  3. 3

    Building Final Inspection(s)

    Verifies compliance with applicable code for the newly proposed use; required per the Commercial CO checklist

  4. 4

    Certificate of Occupancy Issuance

    Final step once Fire, Public Works, Planning approvals and all Building final inspections are recorded and related permits closed; per the City's own Commercial CO checklist, 'COs or related comments can take up to 48 hours and cannot be processed at the counter'

See the full Brighton inspection guide — scheduling & re-inspection fees →

Tips

  • Unlike some peer Colorado cities in this dataset (e.g., Aurora), Brighton does not publish a single dedicated 'Change of Occupancy' guidance document — the same underlying requirement (a new CO whenever use/occupancy changes, per the adopted 2021 IBC Section 111) is instead enforced through three separate, real Brighton mechanisms: the Business License application, a Planning Division Zoning Verification Letter, and the City's own Commercial CO checklist. Budget time to coordinate across all three rather than expecting one consolidated 'change of use permit' application.
  • Get a Zoning Verification Letter from Planning (planner@brightonco.gov) BEFORE signing a lease or applying for a business license for a new use — it costs only $50 for the first hour and confirms whether the intended use is even allowed in that zone district.
  • The Commercial CO checklist requires sign-off from Brighton Fire Rescue District, Public Works, AND the Development Services Manager (Planning), plus closure of all related trade permits (sprinkler, alarm, retaining wall, landscape) — a change of use with zero construction can still require re-triggering some of these approvals if the prior CO's fire/life-safety basis doesn't match the new use.
  • A Temporary Certificate of Occupancy is not available for Group R (residential) uses, and requires written sign-off from every department on the Commercial CO checklist plus resolution of all life-health-safety concerns — don't count on a TCO as a fallback for a residential change of use.

Frequently asked questions

Brighton requires a change of occupancy / change of use permit for: The 2021 IBC (Section 111), as adopted by the City of Brighton, makes it unlawful to use or occupy a building or portion thereof for a purpose other than that shown on its most recent Certificate of Occupancy; a new or amended CO is required whenever the use or occupancy classification changes, whether or not construction work accompanies the change; Any business with a physical location within the City of Brighton is required to hold an active Business License (Municipal Code Chapter 5), filed through the City's Munirevs portal (brightonco.munirevs.com); renewal and new applications 'are subject to review and approval to ensure compliance with the City's code,' and additional licenses, permits, or approvals may be required depending on business type; Confirmation that the newly proposed use is allowed within the property's zoning district should be obtained from the Planning Division via a Zoning Verification Letter (planner@brightonco.gov, or the Planner on Duty at 303-655-2072) before proceeding with a lease or business license application; Where the change of use involves construction, remodeling, or tenant-improvement work, this file's Commercial Tenant Improvement / Nonresidential Permit entry applies (2021 IBC-governed building permit, Permit Checklist: Com, Ind, MF document set); Issuance of a new or amended Certificate of Occupancy — whether or not construction work is involved — follows the same multi-department sign-off documented on the City's own Commercial CO checklist: approval/final inspection from Brighton Fire (Brighton Fire Rescue District, logged in OpenGov), approval from Public Works, approval from the Development Services Manager (Planning), all passed Building final inspections (permit card uploaded to the portal), and closure of all related permits (sprinkler, alarm, retaining wall, landscape, etc.); A Temporary Certificate of Occupancy (TCO) requires written approval from Fire, Public Works, and Planning, with all life-health-safety concerns addressed; TCOs are NOT available for Group R (residential) occupancies; Certificate-of-Occupancy requests and related comments are processed via OpenGov and cannot be handled at the permit counter. If your project isn't listed, confirm with City of Brighton Community Development Department, Permitting Division at 303-655-2017 before starting work.

A general Business License is free to apply for. A Zoning Verification Letter costs $50 for the first hour ($25 per additional hour). No standalone 'change of use' or 'change of occupancy' fee beyond these is published in the City's 2026 fee schedule; if construction or tenant-improvement work accompanies the change, the standard Commercial Tenant Improvement building-permit fee basis applies instead.

Per the City's own Commercial CO checklist, 'COs or related comments can take up to 48 hours and cannot be processed at the counter' — this covers only the final CO-issuance step, once Fire, Public Works, Planning, and Building final-inspection approvals are already on record. Brighton does not publish an overall turnaround for the earlier zoning-verification and business-license steps.

You'll need: Business License Application; Zoning Verification Letter Request; Commercial CO Checklist Items. Depending on your project, Brighton may also ask for: Building Permit Application and Permit Checklist: Com, Ind, MF. See the required-documents checklist on this page for details on each.

Brighton requires 4 inspection(s) for a change of occupancy / change of use permit, in order: Zoning Use-Conformance Review, Fire Final Inspection / Approval, Building Final Inspection(s), Certificate of Occupancy Issuance. Schedule each through City of Brighton Community Development Department, Permitting Division (303-655-2017).

Apply through City of Brighton Community Development Department, Permitting Division at 500 S 4th Avenue, Brighton, CO 80601. Phone: 303-655-2017, email: 1stop@brightonco.gov. Office hours: City of Brighton main line 303-655-2000; Building Permit Counter direct line 303-655-2017; Homeowner Inspection Line 303-655-2151; Community Development general line 303-655-2072. City Hall closes at noon on Fridays, and all Community Development functions (planning and zoning, permitting and inspections) end at noon on Fridays as well.. Official information: https://www.brightonco.gov/222/Permitting.

Brighton, Colorado has adopted: 2021 International Building Code (IBC) — City of Brighton 'Building Code Editions, Design Loads, Etc.' sheet, Codes & Information page; 2021 International Residential Code (IRC); 2021 International Mechanical Code (IMC); 2021 International Plumbing Code (IPC); 2021 International Fuel Gas Code (IFGC); 2021 International Fire Code (IFC); 2021 International Energy Conservation Code (IECC); 2021 International Property Maintenance Code (IPMC); 2021 International Existing Building Code (IEBC); 2021 International Swimming Pool and Spa Code (ISPSC); 2023 National Electrical Code (NEC); ICC A117-17 (Accessible and Usable Buildings and Facilities); Effective date of the 2021 I-Code revisions: January 1, 2023. Effective date of the 2023 NEC adoption: July 1, 2023 — both per the City's own published 'Building Code Editions, Design Loads, Etc.' sheet (Codes & Information page), which is treated as the current, governing adopted-code list for this file.; Note on code-page currency: Brighton's Municode-hosted Chapter 15, Article 15-12 ('National Electrical Code') still codifies the '2005 National Electrical Code' verbatim in its Municode text — this is a known lag between the codified ordinance text on Municode and the live, actively-maintained Codes & Information page, which explicitly states the 2023 NEC is adopted effective 7/1/2023. The live department page is treated as authoritative for current code edition, consistent with the same lag pattern documented for other Colorado home-rule jurisdictions in this corpus (e.g. Vail's Minimum Submittal Requirements PDFs).. Local amendments apply — see the Brighton overview page for the full list.

Yes in substance, though Brighton does not publish a single named 'change of use permit.' Under the City's adopted 2021 IBC (Section 111), it is unlawful to occupy a building for a use other than that shown on its most recent Certificate of Occupancy, so a use change requires a new or amended CO — obtained via the City's Business License process, a Planning Division Zoning Verification Letter, and the Commercial CO checklist (Fire, Public Works, and Planning sign-off plus Building final inspection), even when no physical construction is involved.

Sources & verification

Verified against official sources. Last reviewed 2026-08-13.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Brighton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.