Required for heating, cooling, and ventilation equipment installation or replacement in Brighton. Governed by the 2021 International Mechanical Code (IMC) and 2021 International Fuel Gas Code (IFGC) as adopted. Contractors must hold a City of Brighton Class M Mechanical Contractor license (or Class MP combination license).

Verified 2026-07-06 · Source

When you need this permit

  • Governed by the 2021 IMC and 2021 IFGC as adopted by the City of Brighton
  • Contractors must hold a City of Brighton Class M (Mechanical Contractor) or Class MP (Mechanical/Plumbing Combination) license (Municipal Code Article 15-16-50)
  • As of November 1, 2025, all high-efficiency fuel-burning appliances require a limestone (condensate-neutralizer) filter on the condensate line, per the City's Permitting page

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Mechanical Permit Fee (same unified valuation-based schedule as Building/Electrical/Plumbing)2026 Community Development Fee Schedule (Attachment 4)
$23.50 minimum, scaling per the valuation tiers in the 2026 Community Development Fee Schedule
Class M Mechanical Contractor License FeePlus a separate $15.00 registration fee; Class MP Combination license is $100.00 plus $15.00 registration
$75.00
Plan Review Fee
65% of Permit Fee (if plan review is required)
Construction Use Tax
3.75% of 50% of total project valuation

Review timeline

Plan review
Not published — contact the department

How long did your Mechanical / HVAC Permit permit actually take in Brighton?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Mechanical

    Ductwork, flues, and equipment placement before concealment

  2. 2

    Final Inspection

    Equipment operational, combustion air and venting verified

See the full Brighton inspection guide — scheduling & re-inspection fees →

Tips

  • At Brighton's elevation (4,984 ft per the City's own Manual J Design Criteria) and outdoor winter design dry-bulb temp of 1F, confirm your HVAC contractor is sizing equipment to the City's specific altitude correction factor (0.82), not sea-level assumptions.
  • As of November 1, 2025, high-efficiency fuel-burning appliances require a limestone filter on the condensate line — confirm this is included in your furnace/boiler/water heater installation scope before final inspection.

Frequently asked questions

Brighton requires a mechanical / hvac permit for: Governed by the 2021 IMC and 2021 IFGC as adopted by the City of Brighton; Contractors must hold a City of Brighton Class M (Mechanical Contractor) or Class MP (Mechanical/Plumbing Combination) license (Municipal Code Article 15-16-50); As of November 1, 2025, all high-efficiency fuel-burning appliances require a limestone (condensate-neutralizer) filter on the condensate line, per the City's Permitting page. If your project isn't listed, confirm with City of Brighton Community Development Department, Permitting Division at 303-655-2017 before starting work.

In Brighton, the published Mechanical Permit Fee (same unified valuation-based schedule as Building/Electrical/Plumbing) is: $23.50 minimum, scaling per the valuation tiers in the 2026 Community Development Fee Schedule. Additional published fees: Class M Mechanical Contractor License Fee — $75.00; Plan Review Fee — 65% of Permit Fee (if plan review is required); Construction Use Tax — 3.75% of 50% of total project valuation. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Brighton does not publish a plan-review timeline for this permit. Contact City of Brighton Community Development Department, Permitting Division at 303-655-2017 for current turnaround.

You'll need: Mechanical Permit Application; City of Brighton Class M or MP Contractor License. See the required-documents checklist on this page for details on each.

Brighton requires 2 inspection(s) for a mechanical / hvac permit, in order: Rough Mechanical, Final Inspection. Schedule each through City of Brighton Community Development Department, Permitting Division (303-655-2017).

Apply through City of Brighton Community Development Department, Permitting Division at 500 S 4th Avenue, Brighton, CO 80601. Phone: 303-655-2017, email: 1stop@brightonco.gov. Office hours: City of Brighton main line 303-655-2000; Building Permit Counter direct line 303-655-2017; Homeowner Inspection Line 303-655-2151; Community Development general line 303-655-2072. City Hall closes at noon on Fridays, and all Community Development functions (planning and zoning, permitting and inspections) end at noon on Fridays as well.. Official information: https://www.brightonco.gov/222/Permitting.

Brighton, Colorado has adopted: 2021 International Building Code (IBC) — City of Brighton 'Building Code Editions, Design Loads, Etc.' sheet, Codes & Information page; 2021 International Residential Code (IRC); 2021 International Mechanical Code (IMC); 2021 International Plumbing Code (IPC); 2021 International Fuel Gas Code (IFGC); 2021 International Fire Code (IFC); 2021 International Energy Conservation Code (IECC); 2021 International Property Maintenance Code (IPMC); 2021 International Existing Building Code (IEBC); 2021 International Swimming Pool and Spa Code (ISPSC); 2023 National Electrical Code (NEC); ICC A117-17 (Accessible and Usable Buildings and Facilities); Effective date of the 2021 I-Code revisions: January 1, 2023. Effective date of the 2023 NEC adoption: July 1, 2023 — both per the City's own published 'Building Code Editions, Design Loads, Etc.' sheet (Codes & Information page), which is treated as the current, governing adopted-code list for this file.; Note on code-page currency: Brighton's Municode-hosted Chapter 15, Article 15-12 ('National Electrical Code') still codifies the '2005 National Electrical Code' verbatim in its Municode text — this is a known lag between the codified ordinance text on Municode and the live, actively-maintained Codes & Information page, which explicitly states the 2023 NEC is adopted effective 7/1/2023. The live department page is treated as authoritative for current code edition, consistent with the same lag pattern documented for other Colorado home-rule jurisdictions in this corpus (e.g. Vail's Minimum Submittal Requirements PDFs).. Local amendments apply — see the Brighton overview page for the full list.

The City's published Manual J Design Criteria lists an elevation of 4,984 ft, an altitude correction factor of 0.82, an outdoor winter design dry-bulb temperature of 1F, and an outdoor summer design dry-bulb temperature of 91F.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Brighton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.