Skip to main content
PermitBase

Sign Permit in Brighton, Colorado

Required before any permanent or temporary sign is erected, moved, altered, or reconstructed in Brighton, except signs specifically exempted under Land Use & Development Code (LUDC) Section 9.02.C. Governed by LUDC Article 9 (Sign Standards, part of Chapter 17 of the Municipal Code). Sign construction falls under the Class D (Jobbing Contractor) license at minimum (Municipal Code Article 15-16-50(4)), the same license class that covers patios, sheds, and fences. Brighton does not publish a distinct dollar fee specifically for an individual sign permit — confirmed via a full-text search of every attachment in the City's 2026 Community Development Fee Schedule — so a standalone sign permit is billed under the same unified valuation-based Building Permit Fee schedule used for all other trades in this file; only a Comprehensive Sign Plan (for coordinated multi-sign developments under LUDC 9.08) has its own published flat fee.

Verified 2026-08-13 · Source

When you need this permit

  • A sign permit is required to erect, move, alter, or reconstruct any permanent or temporary sign, except signs exempt under LUDC Section 9.02.C (e.g., government signs, small public-purpose/safety signs under 4 sf, vehicle signs meeting size/use limits, scoreboards, handheld signs under 20 sf, certain flags/pennants, window signs not exceeding 25% of window area, incidental signs under 2 sf, and directional signs under 2 sf)
  • No sign permit shall be issued for a permanent sign on private property without written consent of the property owner or the owner's authorized agent (LUDC 9.02.B.1)
  • Professional sign installation requires a City of Brighton contractor's license — at minimum a Class D (Jobbing Contractor) license, which explicitly authorizes construction of signs among other nonhabitable structures (Municipal Code Article 15-16-50(4)); a broader Class A/B/C general contractor license also covers sign work Contractor
  • Electrical work for illuminated signs must comply with the City's adopted Electrical Code and is subject to City inspection (LUDC 9.05.B); all professional sign installations require a contractor's license from the City prior to installation Contractor
  • A separate City of Brighton building permit may additionally be required for signs incorporating structural elements or attached to a building (LUDC 9.02.B.3)
  • Signs must conform to district-based standards: Table 9-1 (Residential Districts) or Tables 9-2 and 9-3 (Non-residential Districts, including setback-based freestanding pole/monument height and size limits) governing maximum number, area, and height by sign type
  • A sign permit becomes void if work is not commenced within 180 days of issuance, or is suspended for a continuous 180-day period after work commences; the Director may grant written extensions of up to 180 days each for justifiable cause
  • Temporary signs not otherwise exempt require a separate temporary sign permit: displayed no more than 60 days in any 90-day period, and no more than 180 days total per calendar year; a maximum of 2 temporary sign permits may be issued per nonresidential use at any given time, each permit covering up to 2 signs (4 temporary signs maximum posted at once)
  • Coordinated or unified developments with multiple signs may file a single Comprehensive Sign Plan (LUDC 9.08) covering all signs on the site, in lieu of individual permits per sign
  • Individual sign permit applications are submitted online via the City's OpenGov/ViewpointCloud portal (brightonco.viewpointcloud.com); Comprehensive Sign Plans are submitted via the City's GeoCivix portal (brightonco.geocivix.com/secure/)
  • A denial of a sign permit by the Director may be appealed to the Board of Adjustment per the procedures in LUDC Article 2

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Sign Permit (individual sign — unified valuation-based schedule)No distinct flat or per-sign fee is published anywhere in the City's 2026 Community Development Fee Schedule (confirmed by a full-text search of all 14 attachments) — an individual sign permit is billed under the same unified valuation-based Building Permit Fee schedule used for Building/Electrical/Plumbing/Mechanical work elsewhere in this file
$23.50 minimum, scaling per the valuation tiers in the 2026 Community Development Fee Schedule
Comprehensive Sign Plan or Amendment thereto2026 Community Development Fee Schedule, Attachment 3 (Development Application Processing Fees) — the only sign-specific line item published in the fee schedule; covers a single coordinated multi-sign filing under LUDC 9.08, not an individual sign permit
$250.00
Electrical Permit Fee (if sign is illuminated)Billed under the same unified schedule as this file's electrical-permit entry
$23.50 minimum, scaling per the valuation tiers in the 2026 Community Development Fee Schedule
Construction Use TaxApplies where a taxable materials valuation exists for the sign installation
3.75% of 50% of total project valuation

Review timeline

Plan review
Not published — contact the department

How long did your Sign Permit permit actually take in Brighton?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Pre-Installation Site Inspection

    The Director is authorized to inspect the proposed sign location prior to acting on the application, per LUDC 9.02.B.4

  2. 2

    Final Inspection

    Verifies the constructed sign complies with the approved permit and LUDC Article 9 standards, including electrical compliance if illuminated

See the full Brighton inspection guide — scheduling & re-inspection fees →

Tips

  • The Class D (Jobbing Contractor) license — the same minimum license class that covers patios, sheds, and fences elsewhere in this file's deck-covered-patio-permit entry — is also the minimum City license class that explicitly authorizes sign construction (Municipal Code Article 15-16-50(4)); confirm your sign installer holds this or a broader Class A/B/C license before applying.
  • Brighton does not publish a distinct dollar fee for an individual sign permit — confirmed by searching every attachment of the 2026 fee schedule. Only a Comprehensive Sign Plan ($250, for coordinated multi-sign developments) has its own line item; a standalone single-sign permit is billed under the general unified valuation-based Building Permit Fee schedule.
  • Window signs (not extending beyond the first story, not animated, not blocking egress, and not covering more than 25% of the window area), incidental signs under 2 sf, and several other categories listed in LUDC 9.02.C are permit-exempt — don't file for a permit you don't need, though exempt signs still can't be illuminated unless the exemption specifically allows it.
  • Temporary signs are capped at 60 display-days per any 90-day period and 180 days per calendar year, with a maximum of 2 temporary sign permits (covering up to 4 signs total) per nonresidential use at any given time — plan seasonal/promotional signage around these caps.

Frequently asked questions

Brighton requires a sign permit for: A sign permit is required to erect, move, alter, or reconstruct any permanent or temporary sign, except signs exempt under LUDC Section 9.02.C (e.g., government signs, small public-purpose/safety signs under 4 sf, vehicle signs meeting size/use limits, scoreboards, handheld signs under 20 sf, certain flags/pennants, window signs not exceeding 25% of window area, incidental signs under 2 sf, and directional signs under 2 sf); No sign permit shall be issued for a permanent sign on private property without written consent of the property owner or the owner's authorized agent (LUDC 9.02.B.1); Professional sign installation requires a City of Brighton contractor's license — at minimum a Class D (Jobbing Contractor) license, which explicitly authorizes construction of signs among other nonhabitable structures (Municipal Code Article 15-16-50(4)); a broader Class A/B/C general contractor license also covers sign work; Electrical work for illuminated signs must comply with the City's adopted Electrical Code and is subject to City inspection (LUDC 9.05.B); all professional sign installations require a contractor's license from the City prior to installation; A separate City of Brighton building permit may additionally be required for signs incorporating structural elements or attached to a building (LUDC 9.02.B.3); Signs must conform to district-based standards: Table 9-1 (Residential Districts) or Tables 9-2 and 9-3 (Non-residential Districts, including setback-based freestanding pole/monument height and size limits) governing maximum number, area, and height by sign type; A sign permit becomes void if work is not commenced within 180 days of issuance, or is suspended for a continuous 180-day period after work commences; the Director may grant written extensions of up to 180 days each for justifiable cause; Temporary signs not otherwise exempt require a separate temporary sign permit: displayed no more than 60 days in any 90-day period, and no more than 180 days total per calendar year; a maximum of 2 temporary sign permits may be issued per nonresidential use at any given time, each permit covering up to 2 signs (4 temporary signs maximum posted at once); Coordinated or unified developments with multiple signs may file a single Comprehensive Sign Plan (LUDC 9.08) covering all signs on the site, in lieu of individual permits per sign; Individual sign permit applications are submitted online via the City's OpenGov/ViewpointCloud portal (brightonco.viewpointcloud.com); Comprehensive Sign Plans are submitted via the City's GeoCivix portal (brightonco.geocivix.com/secure/); A denial of a sign permit by the Director may be appealed to the Board of Adjustment per the procedures in LUDC Article 2. If your project isn't listed, confirm with City of Brighton Community Development Department, Permitting Division at 303-655-2017 before starting work.

Brighton does not publish a distinct fee specifically for an individual sign permit — it is billed under the same unified, valuation-based Building Permit Fee schedule used for all other trades in the City ($23.50 minimum, scaling with valuation). A Comprehensive Sign Plan covering multiple signs in a coordinated development has its own published flat fee of $250.00.

Brighton does not publish a plan-review timeline for this permit. Contact City of Brighton Community Development Department, Permitting Division at 303-655-2017 for current turnaround.

You'll need: Sign Permit Application; Site Plan and Elevations; Written Property Owner Consent. Depending on your project, Brighton may also ask for: Comprehensive Sign Plan. See the required-documents checklist on this page for details on each.

Brighton requires 2 inspection(s) for a sign permit, in order: Pre-Installation Site Inspection, Final Inspection. Schedule each through City of Brighton Community Development Department, Permitting Division (303-655-2017).

Apply through City of Brighton Community Development Department, Permitting Division at 500 S 4th Avenue, Brighton, CO 80601. Phone: 303-655-2017, email: 1stop@brightonco.gov. Office hours: City of Brighton main line 303-655-2000; Building Permit Counter direct line 303-655-2017; Homeowner Inspection Line 303-655-2151; Community Development general line 303-655-2072. City Hall closes at noon on Fridays, and all Community Development functions (planning and zoning, permitting and inspections) end at noon on Fridays as well.. Official information: https://www.brightonco.gov/222/Permitting.

A sign permit is required to erect, move, alter, or reconstruct almost any permanent or temporary sign. A specific list of permit-exempt signs — government signs, small public-purpose signs under 4 sf, certain vehicle and window signs, scoreboards, handheld signs under 20 sf, and others — is set out in LUDC Section 9.02.C.

At minimum a City of Brighton Class D (Jobbing Contractor) license, per Municipal Code Article 15-16-50(4), which explicitly authorizes sign construction. Illuminated signs additionally require the electrical work to comply with the City's adopted Electrical Code and pass City inspection.