Sign Permit — Brighton, Colorado · Requirements sheet
Verified 2026-08-13 · Source: https://www.brightonco.gov/363/Land-Use-Development-Code
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Sign Permit in Brighton, Colorado
Required before any permanent or temporary sign is erected, moved, altered, or reconstructed in Brighton, except signs specifically exempted under Land Use & Development Code (LUDC) Section 9.02.C. Governed by LUDC Article 9 (Sign Standards, part of Chapter 17 of the Municipal Code). Sign construction falls under the Class D (Jobbing Contractor) license at minimum (Municipal Code Article 15-16-50(4)), the same license class that covers patios, sheds, and fences. Brighton does not publish a distinct dollar fee specifically for an individual sign permit — confirmed via a full-text search of every attachment in the City's 2026 Community Development Fee Schedule — so a standalone sign permit is billed under the same unified valuation-based Building Permit Fee schedule used for all other trades in this file; only a Comprehensive Sign Plan (for coordinated multi-sign developments under LUDC 9.08) has its own published flat fee.
Verified 2026-08-13 · Source
When you need this permit
- A sign permit is required to erect, move, alter, or reconstruct any permanent or temporary sign, except signs exempt under LUDC Section 9.02.C (e.g., government signs, small public-purpose/safety signs under 4 sf, vehicle signs meeting size/use limits, scoreboards, handheld signs under 20 sf, certain flags/pennants, window signs not exceeding 25% of window area, incidental signs under 2 sf, and directional signs under 2 sf)
- No sign permit shall be issued for a permanent sign on private property without written consent of the property owner or the owner's authorized agent (LUDC 9.02.B.1)
- Professional sign installation requires a City of Brighton contractor's license — at minimum a Class D (Jobbing Contractor) license, which explicitly authorizes construction of signs among other nonhabitable structures (Municipal Code Article 15-16-50(4)); a broader Class A/B/C general contractor license also covers sign work Contractor
- Electrical work for illuminated signs must comply with the City's adopted Electrical Code and is subject to City inspection (LUDC 9.05.B); all professional sign installations require a contractor's license from the City prior to installation Contractor
- A separate City of Brighton building permit may additionally be required for signs incorporating structural elements or attached to a building (LUDC 9.02.B.3)
- Signs must conform to district-based standards: Table 9-1 (Residential Districts) or Tables 9-2 and 9-3 (Non-residential Districts, including setback-based freestanding pole/monument height and size limits) governing maximum number, area, and height by sign type
- A sign permit becomes void if work is not commenced within 180 days of issuance, or is suspended for a continuous 180-day period after work commences; the Director may grant written extensions of up to 180 days each for justifiable cause
- Temporary signs not otherwise exempt require a separate temporary sign permit: displayed no more than 60 days in any 90-day period, and no more than 180 days total per calendar year; a maximum of 2 temporary sign permits may be issued per nonresidential use at any given time, each permit covering up to 2 signs (4 temporary signs maximum posted at once)
- Coordinated or unified developments with multiple signs may file a single Comprehensive Sign Plan (LUDC 9.08) covering all signs on the site, in lieu of individual permits per sign
- Individual sign permit applications are submitted online via the City's OpenGov/ViewpointCloud portal (brightonco.viewpointcloud.com); Comprehensive Sign Plans are submitted via the City's GeoCivix portal (brightonco.geocivix.com/secure/)
- A denial of a sign permit by the Director may be appealed to the Board of Adjustment per the procedures in LUDC Article 2
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Pre-Installation Site Inspection
The Director is authorized to inspect the proposed sign location prior to acting on the application, per LUDC 9.02.B.4
- 2
Final Inspection
Verifies the constructed sign complies with the approved permit and LUDC Article 9 standards, including electrical compliance if illuminated
See the full Brighton inspection guide — scheduling & re-inspection fees →
Tips
- The Class D (Jobbing Contractor) license — the same minimum license class that covers patios, sheds, and fences elsewhere in this file's deck-covered-patio-permit entry — is also the minimum City license class that explicitly authorizes sign construction (Municipal Code Article 15-16-50(4)); confirm your sign installer holds this or a broader Class A/B/C license before applying.
- Brighton does not publish a distinct dollar fee for an individual sign permit — confirmed by searching every attachment of the 2026 fee schedule. Only a Comprehensive Sign Plan ($250, for coordinated multi-sign developments) has its own line item; a standalone single-sign permit is billed under the general unified valuation-based Building Permit Fee schedule.
- Window signs (not extending beyond the first story, not animated, not blocking egress, and not covering more than 25% of the window area), incidental signs under 2 sf, and several other categories listed in LUDC 9.02.C are permit-exempt — don't file for a permit you don't need, though exempt signs still can't be illuminated unless the exemption specifically allows it.
- Temporary signs are capped at 60 display-days per any 90-day period and 180 days per calendar year, with a maximum of 2 temporary sign permits (covering up to 4 signs total) per nonresidential use at any given time — plan seasonal/promotional signage around these caps.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-13.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Brighton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Brighton
Sign Permit in other cities
Compare sign permit fees across Colorado →
Look up this fee in a different city →
Now live
Build your Brighton project checklist
Describe your project once and get every permit, document, and fee it triggers in Brighton — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →