EV Charger / EVSE Permit — Larkspur, Colorado · Requirements sheet
Verified 2026-07-20 · Source: https://www.townoflarkspur.org/media/2901
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Larkspur, Colorado
Electric vehicle charging equipment (EVSE) installation within Larkspur Town limits is an electrical permit, processed as an 'Electric Only Permit' or 'Electrical Service Change' under the Town's One Stop Permits expedited category. Larkspur does not run its own local electrical fee program — it republishes the Colorado DORA (Division of Professions and Occupations) statewide Electrical Permit Fee Schedule (effective April 1, 2016) directly on its own website, the same schedule documented on this file's general Electrical Permit entry. That schedule has no distinct EV-charger/EVSE line item; a discrete EVSE circuit addition (not tied to a whole-dwelling square-footage remodel) is billed under the schedule's valuation-based 'Commercial and other fees' tier, the same tier used for a garage or shop electrical installation.
Verified 2026-07-20 · Source
When you need this permit
- Electric Only Permit or Electrical Service Change application required for EVSE circuit installation, submitted via SAFEbuilt's CommunityCore portal, part of the Town's expedited One Stop Permits category
- Fee computed under Colorado DORA's statewide Electrical Permit Fee Schedule (effective April 1, 2016, per CRS 12-23-117(3)), not a Larkspur-specific local rate
- Permit must be filed in advance of commencing installation, or the inspection fee is doubled per CRS 12-23-117(3)
- No dedicated EV-charger/EVSE fee line exists on the DORA schedule — a discrete EVSE circuit addition is billed under the 'Commercial and other fees (including residential installations not based on square footage, e.g. garage/shop)' valuation-based tier rather than the square-footage-based 'Residential Electrical Only Installation' tier, since an EVSE addition is not a whole-dwelling electrical remodel
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Required prior to covering; requested via the online permit system
- 2
Final Inspection
EVSE circuit, breaker/disconnect, and NEC Article 625 compliance verified prior to use
See the full Larkspur inspection guide — scheduling & re-inspection fees →
Tips
- EV charger installation falls under Larkspur's 'One Stop Permits' expedited category (Electric Only Permit / Electrical Service Change) — the same fast-track category used for A/C, water heater, and furnace replacement permits.
- Larkspur does not set its own local electrical fee — it republishes the Colorado DORA statewide fee schedule directly, so out-of-town contractors already familiar with DORA's fee structure from other Colorado jurisdictions can generally apply the same calculation here.
- File your permit before starting work: per CRS 12-23-117(3), if the permit is not filed in advance of the installation's commencement, the inspection fee is doubled.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Larkspur building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Larkspur
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Colorado →
Look up this fee in a different city →