EV Charger / EVSE Permit — City of Fountain, Colorado · Requirements sheet
Verified 2026-07-20 · Source: https://www.pprbd.org/Information/FeeSchedule
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in City of Fountain, Colorado
Required for installation of a residential or commercial electric vehicle charging station (EVSE) within Fountain city limits. As with all electrical work in Fountain, the permit is issued by the Pikes Peak Regional Building Department (PPRBD), not the City. PPRBD's published fee schedule (pprbd.org/Information/FeeSchedule) has no distinct 'EV charger' or 'EVSE' line item — a standalone EVSE circuit is billed as a standalone electrical permit under Table C (valuation-based), or as a Table B.1 residential trade attachment fee ($50.00) if the electrical work is filed together with another building permit (e.g., a panel upgrade or new construction).
Verified 2026-07-20 · Source
When you need this permit
- Electrical permit for EVSE/charging equipment installation, reviewed under the 2023 National Electrical Code (NEC) per PPRBD's adopted codes
- Current State of Colorado (DORA) master electrician/contractor license on file, if using a licensed contractor Contractor
- If the installation requires a panel or service upgrade to support the added EVSE load, that upgrade is filed as a separate or combined electrical permit line item
- Applications submitted via PPRBD's online account portal (account.pprbd.org)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final Electrical
Circuit, disconnect, and EVSE unit connections verified before energizing, per PPRBD's standard electrical final inspection practice.
See the full City of Fountain inspection guide — scheduling & re-inspection fees →
Tips
- PPRBD has no distinct 'EV charger' fee line item — unlike some Colorado cities (e.g., Aurora's flat $99 residential EV charger fee), a Fountain-area EVSE circuit is billed as a standard electrical permit under PPRBD's general Table C valuation schedule (standalone) or Table B.1 trade-attachment fee ($50) if filed with another permit.
- If your EVSE installation also requires a panel or service upgrade, budget for that as part of the same or an additional electrical permit line item — confirm the total scope with PPRBD before applying.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the City of Fountain building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in City of Fountain
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Colorado →
Look up this fee in a different city →