Solar PV Permit — City of Fountain, Colorado · Requirements sheet
Verified 2026-07-20 · Source: https://www.pprbd.org/File/ByAlias/AlternativeEnergyResidential
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar PV Permit in City of Fountain, Colorado
Required for installation of rooftop or ground-mounted photovoltaic (PV) and solar-thermal systems within Fountain city limits. As with all building permits in Fountain, the actual permit is issued by the Pikes Peak Regional Building Department (PPRBD) — not the City — under PPRBD's Alternative Energy Plan Requirements, which require both a building permit and an electrical permit for PV systems (plus a mechanical/plumbing permit for solar-thermal systems altering interior piping). PPRBD does not publish a solar-specific flat fee; systems are billed at standard Table A valuation-based building-permit rates plus an electrical trade fee. Colorado's statewide solar permit fee cap (C.R.S. § 24-48.5-113, enacted via HB21-1284) limits any local solar permit fee to $500 for a residential system and $1,000 for a commercial system, which applies as a ceiling on whatever PPRBD's valuation-based calculation would otherwise produce.
Verified 2026-07-20 · Source
When you need this permit
- Written utility approval for the system (including disconnect locations); site plan with north arrow, equipment locations, raceway routing, module layout, and access pathways
- Roof-mount PV: configurator printout/charts or Colorado-licensed design professional letter confirming design criteria — snow load Pf=30 psf/Pg=43 psf below 7,000 ft (Pf=40/Pg=57 above 7,000 ft), wind load 130 mph Vult Exposure C; roof connection spacing and fastener specifications
- Ground-mount PV: only arrays exceeding 7 feet in height require a building permit (an electrical permit is still required regardless of height); site plan showing tallest point of array; foundation depth/diameter/spacing per a Colorado-licensed design professional
- Energy Storage Systems (ESS) must comply with NEC 706.15 and include a DC disconnect between ESS output and inverter, plus a floor plan showing ESS location
- Solar-thermal systems: mechanical/plumbing submittal showing floor layout, isometric of the system, backflow devices, IPC 504.5 relief valve approval, and IRC combination pressure/temperature relief valves on water heaters and storage tanks
- Fountain City of Fountain zoning review is not separately called out for solar in the City's published Development Review Fee Schedule (unlike new-construction Plot Plans); confirm with the City Planning Department, (719) 322-2000, whether a rooftop retrofit installation on an existing structure requires a City zoning sign-off before PPRBD will issue the permit
- For solar removed/reinstalled during a reroof: both a building permit and electrical permit are required (plus mechanical/plumbing if solar-thermal piping is altered), in addition to the roofing permit
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before cover
- 2
Final — Structural / Racking and Electrical
Panel mounting, racking attachment, roof penetration sealing, and all electrical connections verified
See the full City of Fountain inspection guide — scheduling & re-inspection fees →
Tips
- PPRBD requires BOTH a building permit and an electrical permit for rooftop PV — budget for both fee lines, not just one, though the combined total is capped by Colorado's statewide solar fee cap.
- Ground-mount arrays 7 feet tall or less skip the building permit requirement but still need the electrical permit.
- Fountain does not operate its own building department — do not contact City Hall expecting to pull the solar permit itself; it is issued and inspected exclusively by PPRBD, though the City's own zoning prerequisites (as used for other construction permits in Fountain) may still apply to new structures supporting a ground-mount array.
- Whatever PPRBD's valuation-based Table A calculation produces, it cannot legally exceed Colorado's statewide solar permit fee cap: $500 residential / $1,000 commercial (C.R.S. § 24-48.5-113, HB21-1284).
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the City of Fountain building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in City of Fountain
Solar PV Permit in other cities
Compare solar pv permit fees across Colorado →
Look up this fee in a different city →