Demolition Permit — Cañon City, Colorado · Requirements sheet
Verified 2026-07-06 · Source: https://www.canoncity.org/DocumentCenter/View/3493/Demolition-Packet-PDF
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Demolition Permit in Cañon City, Colorado
Required for demolition of structures in Cañon City, per the City's own 'What requires a permit?' FAQ. State and federal asbestos regulations (administered by CDPHE) apply to any renovation or demolition project regardless of building age.
Verified 2026-07-06 · Source
When you need this permit
- Permit required for demolition, per the City's own FAQ
- Demolition Application packet requires: Building Permit Application, asbestos report, final CDPHE abatement approval (if abatement was performed), and State CDPHE approval for demolition
- Per CDPHE's 'Building Renovation and Demolition' guidance: the structure must be inspected for asbestos by a Colorado-certified asbestos inspector before any demolition, destructive salvage, de-construction, or house-moving activity, even when there is NO asbestos present
- A written Notification of Demolition Form must be submitted to CDPHE, with a notification fee and a mandatory ten (10) working-day waiting period, before demolition may proceed, regardless of whether asbestos was found
- Asbestos-containing material exceeding trigger levels (single-family residential: 50 linear ft on pipes, 32 sq ft on other surfaces, or a 55-gallon-drum volume equivalent) must be removed by a certified General Abatement Contractor before disturbance
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final Inspection
Confirms complete removal per permit scope and site condition
See the full Cañon City inspection guide — scheduling & re-inspection fees →
Tips
- You need CDPHE asbestos clearance (inspection plus the 10-working-day Notification of Demolition waiting period) BEFORE the City will issue its own demolition permit — budget calendar time for this state-level prerequisite regardless of whether asbestos is actually present.
- Even buildings of any age, including newly built ones, may contain asbestos per CDPHE's own guidance — do not assume a modern structure is automatically exempt from the inspection requirement.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Cañon City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Cañon City
Demolition Permit in other cities
Compare demolition permit fees across Colorado →
Look up this fee in a different city →