Electrical Permit in Crested Butte, Colorado

Required for electrical installation, alteration, or repair in Crested Butte. Governed by the 2023 National Electrical Code (NEC), adopted by Town Code Chapter 18, Article 5 with no local amendments. No standalone electrical permit fee schedule is published separately; electrical work fees are billed under the general Building Permit valuation-based fee table (Appendix A referenced in Town Code Sec. 18-5 fees provision).

Verified 2026-07-06 · Source

When you need this permit

  • Governed by the 2023 NEC as adopted, with no local amendments (Town Code Sec. 18-5-30: 'The code adopted herein is modified by the following amendments: None.')
  • Current Gunnison County building contractor license required Contractor
  • Fees billed under the same valuation-based Building Permit fee table as building permits; no separate electrical-specific fee line item found in the 2026 Fee Schedule
  • Inspection requests must be submitted at least 5 working days in advance (adopted IFC Sec. 108.2.1)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Permit Fee (valuation-based, same table as Building Permit)No standalone electrical permit fee schedule is published separately in the 2026 Fee Schedule; billed under the general valuation-based table
Per the 2026 Fee Schedule's Building Permit valuation tiers
Plan Review Fee
30% of Permit Fee (Residential) / 60% (Commercial)
Reinspection Fee
$65.00/hour, minimum two-hour charge

Review timeline

Plan review
Not published — contact the department

How long did your Electrical Permit permit actually take in Crested Butte?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Wiring and panel installed before concealment; 5 working days advance notice required

  2. 2

    Final Electrical

See the full Crested Butte inspection guide — scheduling & re-inspection fees →

Tips

  • Unlike some peer Colorado home-rule towns, Crested Butte publishes no separate electrical permit fee schedule — electrical work is billed under the same valuation-based Building Permit fee table used for general construction.

Frequently asked questions

Crested Butte requires an electrical permit for: Governed by the 2023 NEC as adopted, with no local amendments (Town Code Sec. 18-5-30: 'The code adopted herein is modified by the following amendments: None.'); Current Gunnison County building contractor license required; Fees billed under the same valuation-based Building Permit fee table as building permits; no separate electrical-specific fee line item found in the 2026 Fee Schedule; Inspection requests must be submitted at least 5 working days in advance (adopted IFC Sec. 108.2.1). If your project isn't listed, confirm with Town of Crested Butte Building Department (Community Development Department) at (970) 349-5338 before starting work.

No. Electrical permit fees are calculated using the same valuation-based Building Permit fee table published in the Town's 2026 Fee Schedule; no standalone electrical fee line item is published.

Crested Butte does not publish a plan-review timeline for this permit. Contact Town of Crested Butte Building Department (Community Development Department) at (970) 349-5338 for current turnaround.

You'll need: Electrical Permit Application; Gunnison County Building Contractor License. See the required-documents checklist on this page for details on each.

Crested Butte requires 2 inspection(s) for an electrical permit, in order: Rough Electrical, Final Electrical. Schedule each through Town of Crested Butte Building Department (Community Development Department) ((970) 349-5338).

Apply through Town of Crested Butte Building Department (Community Development Department) at 507 Maroon Ave, Crested Butte, CO 81224 (Building Department mailing address: PO Box 39, Crested Butte, CO 81224). Phone: (970) 349-5338, email: building@crestedbutte-co.gov. Office hours: Monday-Friday 8:30 a.m. to 5:00 p.m. Building Official Astrid Matison (ext. 116, amatison@crestedbutte-co.gov). Building Inspector Josh Staab (ext. 127, jstaab@crestedbutte-co.gov). Community Development Director Mel Yemma (ext. 119, melyemma@crestedbutte-co.gov). BOZAR/Planning questions: planning@crestedbutte-co.gov, (970) 349-5338 ext. 121.. Official information: https://townofcrestedbutte.colorado.gov/planning-permitting/community-development.

Crested Butte, Colorado has adopted: 2024 International Building Code (IBC), Chapters 1-35 without appendices — adopted by reference, Town Code Chapter 18, Article 1 (Sec. 18-1-10), pursuant to Title 31, Article 16, Part 2, C.R.S.; 2024 International Residential Code (IRC) — Town Code Chapter 18, Article 2 (Sec. 18-2-10), with extensive local amendments including an all-electric mandate and Table R301.2 climatic design data (Sec. 18-2-30); International Existing Building Code (IEBC) — Town Code Chapter 18, Article 2.5; International Green Construction Code (IgCC), selected sections — Town Code Chapter 18, Article 1.5 (Sec. 18-1.5-30), applicable to new commercial construction; 2021 International Mechanical Code (IMC), including Appendix A — Town Code Chapter 18, Article 3 (Sec. 18-3-10); 2021 International Plumbing Code (IPC), including Appendices C and E — Town Code Chapter 18, Article 4 (Sec. 18-4-10); 2023 National Electrical Code (NEC) — Town Code Chapter 18, Article 5 (Sec. 18-5-10), adopted with no local amendments; 2021 International Fire Code (IFC), including Appendices B-M — Town Code Chapter 18, Article 6 (Sec. 18-6-10), enforced with Crested Butte Fire Protection District (CBFPD) coordination; 2025 Colorado Wildfire Resiliency Code (CWRC), 8 CCR 1507-39 — Town Code Chapter 18, Article 6.5 (Sec. 18-6.5-10), established statewide July 1, 2025; Town enforcement begins June 1, 2026 per the Town's own CWRC Summary Sheet; 2021 International Fuel Gas Code (IFGC), including Appendices — Town Code Chapter 18, Article 7 (Sec. 18-7-10), with local amendments requiring high-efficiency direct-vent sealed-combustion appliances only (deleting IFGC's alternative combustion-air provisions); 2021 International Energy Conservation Code (IECC), without appendices — Town Code Chapter 18, Article 9, Sec. 18-9-40; new construction is additionally required to achieve DOE Zero Energy Ready Home (ZERH) certification per the Town's 2024 Building Code Information page and fact sheet, effective for permits starting January 1, 2026; Colorado Model Electric Ready and Solar Ready Code — referenced throughout the Town's 2024 Building Code fact sheet for EV-ready parking, solar-ready zones, and electric-ready gas-appliance provisions; Full Town Code Chapter 18 (Building Regulations) text hosted at townofcrestedbutte.colorado.gov (Town Code Chapter 18 Revised PDF, Supp. No. 22) and mirrored on library.municode.com/co/crested_butte. Local amendments apply — see the Crested Butte overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Crested Butte building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.