Commercial Building Permit (New Construction, Alteration & Tenant Improvement) in Crested Butte, Colorado

Required for all commercial construction in the Town of Crested Butte — new commercial and mixed-use buildings, additions, alterations, changes of use, and tenant improvements — under Town Code Sec. 18-13-40(a) ('No building or structure shall be erected, constructed, structurally altered, moved, demolished or changed without first obtaining a building permit'). Reviewed under the 2024 IBC (Chapter 18, Article 1), the IEBC for work on existing buildings, and the Town's IgCC Article 1.5 green-construction provisions for new commercial construction. Crested Butte has no separate commercial permit application or tenant-improvement permit type: the Town's own Jan-June 2026 issued-permit report shows commercial interior projects run through the single Building Permit process classified as 'Alteration Level 1 Commercial', 'Alteration Level 2 Commercial', or 'Commercial Change of Use'. Because most of downtown sits in the B1/B2/B3 Business Districts inside the National Historic District, commercial building permit applications are automatically classified 'special review' at BOZAR (Town Code Sec. 16-22-110(b)), the Town's historic/architectural review board — BOZAR approval is required BEFORE the building permit application may be submitted.

Verified 2026-08-02 · Source

When you need this permit

  • BOZAR (Board of Zoning and Architectural Review) approval of a Development Permit Application is required before a building permit application may be submitted (Town Code Sec. 18-13-40(d); BOZAR page: 'you must receive BOZAR approval before applying for building permits') — BOZAR, not a separately named 'Historic Preservation Commission', is the body that administers historic-district design review in Crested Butte
  • Automatic 'special review' BOZAR classification for any building permit in a B1, B2 or B3 Business District (Town Code Sec. 16-22-110(b)) — special review applications pay an additional $750 fee and their public notice must include a published three-dimensional perspective drawing showing the building's facade and relationship to neighboring structures plus a location map
  • All construction documents for commercial projects must be prepared by Colorado registered or licensed design professionals and signed and stamped with a seal (Town Code Sec. 18-13-20(a)(16))
  • New commercial buildings must be All Electric Buildings — no combustion equipment for space heating, water heating, or clothes drying; Commercial Food Heat-processing Equipment is exempt from the electrification mandate (IBC Sec. 1301.1.2 as amended by Town Code Sec. 18-1-30; All Electric Building definition, Town Code Chapter 18)
  • EV parking for new commercial: buildings/accessory structures with 2+ parking spaces must provide one Level II EVSE; 10% of total required spaces (rounded up) must be Electric Vehicle Ready; one 25 kW DC Fast Charger required where 5 or more parking spaces are required (IBC Sec. 1301.1.3 as amended)
  • Solar for new commercial: buildings under 5,000 sq ft must install Solar Ready Components; buildings 5,000 sq ft or larger must install rooftop solar PV per Town Code Sec. 18-1.5-30(5), capped at Gunnison County Electric Association net-metering limits (IBC Sec. 1301.1.4 as amended; Town Code Sec. 18-9-50)
  • New commercial construction must comply with the Town's adopted International Green Construction Code sections (Town Code Article 1.5): stormwater management, building water use reduction, appliance/HVAC efficiency, commercial food service operations, hot water distribution, on-site renewable energy systems, and kitchen exhaust systems
  • Alterations, repairs, additions and changes of occupancy of existing commercial buildings are governed by the 2021 IEBC (Town Code Article 2.5; IECC Chapter 5 [CE] as replaced); commercial Level 3 alterations must additionally be Electric Ready, install Solar Ready Components (under 5,000 sq ft) or rooftop PV (5,000+ sq ft), and provide Level II EVSE plus 10% EV-Ready spaces where the building has 2+ parking spaces (IEBC Secs. 907.2-907.3 as amended)
  • Current Gunnison County building contractor license required — no permit issued since February 1, 2023 without one (Town Code Sec. 18-13-40(e)) Contractor
  • Complete Sec. 18-13-20 submittal package: legal description, deed, plot plan, elevations, floor plans, site development plan (paving, walls/fences, landscaping, exterior lighting), front elevation showing site context, and cross-sections
  • Valuation set by the Building Official from the ICC building valuation data table multiplied by a 2.70 regional modifier, or other evidence of value, whichever is greater (Town Code Sec. 18-13-40(b))
  • If the parcel falls in a mapped Class 1 or Class 2 Colorado Wildfire Resiliency Code fire hazard area, CWRC structure-hardening applies to new commercial structures, changes of use, additions increasing footprint 500+ sq ft, and replacement of more than 25% of exterior siding or roof covering (Town Code Article 6.5; Town enforcement begins June 1, 2026)
  • Certificate of occupancy required before any structure or altered portion may be rented, occupied or used (Town Code Sec. 18-13-70)
  • Construction must commence within 180 days of permit issuance; the permit expires one year after issuance with a single 6-month renewal available for good cause (Building Permit Contract Agreement; Town Code Sec. 18-13-60)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 5 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — valuation $1.00 to $500.002026 Town of Crested Butte Fee Schedule (Exhibit A), effective January 1, 2026, adopted by Resolution 34, Series 2025; same valuation-based table for residential and commercial
$28.42
Building Permit Fee — valuation $501.00 to $2,000.00
$28.42 plus $3.68 per $100 of TSV or fraction thereof above $501
Building Permit Fee — valuation $2,001.00 to $25,000.00
$83.74 plus $16.95 per $1,000 of TSV or fraction thereof above $2,001
Building Permit Fee — valuation $25,001.00 to $50,000.00
$473.79 plus $12.18 per $1,000 of TSV or fraction thereof above $25,001
Building Permit Fee — valuation $50,001.00 to $100,000.00
$778.58 plus $8.47 per $1,000 of TSV or fraction thereof above $50,001
Building Permit Fee — valuation $100,001.00 to $500,000.00
$1,202.07 plus $6.77 per $1,000 of TSV or fraction thereof above $100,001
Building Permit Fee — valuation $500,001.00 to $1,000,000.00
$3,911.05 plus $5.74 per $1,000 of TSV or fraction thereof above $500,001
Building Permit Fee — valuation $1,000,001.00 to $5,000,000.00
$6,681.04 plus $3.00 per $1,000 of TSV or fraction thereof above $1,000,001
Building Permit Fee — valuation $5,000,001.00 and over
$18,327 plus $1.00 per $1,000 of TSV or fraction thereof above $5,000,001
Plan Review Fee (Commercial)2026 Fee Schedule: 'Plan Review Fee 30% Permit Fee Residential/60% Commercial' — commercial plan review is double the residential rate
60% of Permit Fee
Construction Documents Examination (Commercial)Separate 2026 Fee Schedule line: 60% commercial / 30% residential; outside consultants billed at actual cost, other examination at $65/hour
60% of Permit Fee
BOZAR Design Review — Major ProjectMaximum fee depending on complexity; plus $300 for each full Board meeting and $60 for each DRC meeting beyond the first 2
$1,000.00 plus $125.00 publication fee
BOZAR Design Review — Minor Project (small remodel/accessory building)
$750.00 plus $125.00 publication fee ($700.00 with no-picture publication)
BOZAR Special Review Classification surchargeAutomatic for building permits in B1/B2/B3 Business Districts per Town Code Sec. 16-22-110(b) — effectively a standard cost of commercial-district projects
$750.00 additional
Insubstantial Design Review - DRCFor work the Building Inspector and a designated BOZAR member deem insubstantial under Town Code Sec. 16-1-20 / 16-22-100(a) — the typical path for interior-only tenant improvements
$120.00
Additional DRC Meeting
$100.00 per meeting beyond the first 2
Use Tax Deposit
Not less than 4.5% of 60% of Total Project Valuation
Performance Deposit
0.50% of Total Structure Value
Affordable housing payment-in-lieu (new non-residential floor area)2026 Fee Schedule: assessed on newly constructed non-residential floor area in lieu of providing Resident Occupied Affordable Housing units; $4,445.76 per lodging unit for new lodging/short-term accommodation units
$41.82 per sq ft
Capital Expansion Fee — Fire (business/commercial/tourist)2026 Fee Schedule capital expansion section
$0.14 per sq ft
Mechanical Permit (boiler/compressor/absorption system)
$100.00
Mechanical Exhaust HoodDirectly relevant to restaurant tenant improvements
$200.00
Water/Sewer Tap Fees (new construction)2026 Fee Schedule; EQR = Equivalent Residential Usage of a standard 1,875 sq ft residential unit
$14,349 water plus $17,726 sewer, per EQR
Work without Permit
$250 to $1,000 per day, plus applicable permit fee

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Building Permit (New Construction, Alteration & Tenant Improvement) permit actually take in Crested Butte?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation

    Before concrete pour; 36-inch minimum frost line depth per the Town's design criteria (new construction/additions)

  2. 2

    Rough Frame

    Structural framing complete before cover; work must match BOZAR-approved plans — deviations discovered by the Building Inspector or Board members trigger a stop-work order and possible new-permit requirement (Town Code Sec. 18-13-40(g))

  3. 3

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment; inspection requests must be submitted at least five (5) working days prior to the requested date (adopted IFC Sec. 108.2.1, Town Code Sec. 18-6-20(4))

  4. 4

    Fire / Life-Safety

    2021 IFC enforced in coordination with the Crested Butte Fire Protection District (CBFPD); kitchen exhaust/hood systems per the Town's adopted IgCC Sec. 701.4.3.8 and the $200 mechanical exhaust hood permit line

  5. 5

    Final Building Inspection / Certificate of Occupancy

    Certificate of occupancy required before the space may be rented, occupied or used (Town Code Sec. 18-13-70); permit expires one year after issuance, single 6-month renewal available for good cause

See the full Crested Butte inspection guide — scheduling & re-inspection fees →

Tips

  • There is NO separate commercial building permit application or tenant-improvement permit type in Crested Butte — one Building Permit form covers all use types, and the Town's own Jan-June 2026 issued-permit report classifies commercial interior projects as 'Alteration Level 1 Commercial', 'Alteration Level 2 Commercial', or 'Commercial Change of Use' within the same BLD permit series. Budget for the commercial differences instead: 60% plan review (double the residential 30%), sealed construction documents on every commercial project, and the automatic BOZAR special review classification in the business districts.
  • Crested Butte's historic-district gatekeeper is BOZAR (Board of Zoning and Architectural Review), not a separately named Historic Preservation Commission — and its approval must come BEFORE you may even submit a building permit application. Any building permit in the B1, B2 or B3 Business Districts (essentially the historic downtown core) is automatically classified 'special review' (Town Code Sec. 16-22-110(b)): plan on the $750 special review surcharge, a published 3-D perspective drawing of your facade in the Crested Butte News, and the Town's stated 2-month minimum review cycle (BOZAR must decide within 90 days of a complete application).
  • Interior-only tenant improvements have a genuine fast path: work judged 'insubstantial' (Town Code Sec. 16-1-20 — judged on visibility from the street, extent of change relative to the structure, and neighborhood effect) can be waived past the full BOZAR hearing and publication by the Building Inspector plus one designated Board member, paying only the $120 Insubstantial Design Review - DRC fee. Interior fit-outs with no exterior changes are the textbook case; confirm the classification with the Building Department (building@crestedbutte-co.gov) before assuming it.
  • Restaurant and food-service TIs: Commercial Food Heat-processing Equipment is exempt from the all-electric mandate (but must be electric-ready), the mechanical exhaust hood permit is $200, kitchen exhaust must meet the Town's adopted IgCC Sec. 701.4.3.8, and a Fats/Oils/Grease pretreatment application ($48.50) is required before discharging to the Town sewer.
  • A commercial Level 3 alteration (more than 50% of the work area) is where an ambitious tenant improvement gets expensive: it triggers Electric Ready wiring, Solar Ready Components (or rooftop PV at 5,000+ sq ft), and Level II EVSE plus 10% EV-Ready parking where the building has 2 or more spaces (IEBC Secs. 907.2-907.3 as locally amended).
  • New non-residential floor area pays a $41.82/sq ft affordable-housing payment-in-lieu on top of permit fees — on a small commercial addition this line item can rival the building permit fee itself.
  • A change of use is itself permit-triggering ('...or changed without first obtaining a building permit', Town Code Sec. 18-13-40(a)) and appears as its own 'Commercial Change of Use' classification in the Town's permit reports — converting, say, retail to restaurant needs a permit even with minimal construction, and a change of use can also trigger Colorado Wildfire Resiliency Code hardening in mapped Class 1/Class 2 zones once Town enforcement begins June 1, 2026.
  • The Town has announced online permitting and payment via Cloudpermit as 'coming soon' (Licensing & Permitting page, checked 2026-08-02) and asks architects, designers, contractors, and owner-builders to register in the Cloudpermit User Registry now — check whether submittal has moved online before mailing paper applications. Owner-builder

Frequently asked questions

Crested Butte requires a commercial building permit (new construction, alteration & tenant improvement) for: BOZAR (Board of Zoning and Architectural Review) approval of a Development Permit Application is required before a building permit application may be submitted (Town Code Sec. 18-13-40(d); BOZAR page: 'you must receive BOZAR approval before applying for building permits') — BOZAR, not a separately named 'Historic Preservation Commission', is the body that administers historic-district design review in Crested Butte; Automatic 'special review' BOZAR classification for any building permit in a B1, B2 or B3 Business District (Town Code Sec. 16-22-110(b)) — special review applications pay an additional $750 fee and their public notice must include a published three-dimensional perspective drawing showing the building's facade and relationship to neighboring structures plus a location map; All construction documents for commercial projects must be prepared by Colorado registered or licensed design professionals and signed and stamped with a seal (Town Code Sec. 18-13-20(a)(16)); New commercial buildings must be All Electric Buildings — no combustion equipment for space heating, water heating, or clothes drying; Commercial Food Heat-processing Equipment is exempt from the electrification mandate (IBC Sec. 1301.1.2 as amended by Town Code Sec. 18-1-30; All Electric Building definition, Town Code Chapter 18); EV parking for new commercial: buildings/accessory structures with 2+ parking spaces must provide one Level II EVSE; 10% of total required spaces (rounded up) must be Electric Vehicle Ready; one 25 kW DC Fast Charger required where 5 or more parking spaces are required (IBC Sec. 1301.1.3 as amended); Solar for new commercial: buildings under 5,000 sq ft must install Solar Ready Components; buildings 5,000 sq ft or larger must install rooftop solar PV per Town Code Sec. 18-1.5-30(5), capped at Gunnison County Electric Association net-metering limits (IBC Sec. 1301.1.4 as amended; Town Code Sec. 18-9-50); New commercial construction must comply with the Town's adopted International Green Construction Code sections (Town Code Article 1.5): stormwater management, building water use reduction, appliance/HVAC efficiency, commercial food service operations, hot water distribution, on-site renewable energy systems, and kitchen exhaust systems; Alterations, repairs, additions and changes of occupancy of existing commercial buildings are governed by the 2021 IEBC (Town Code Article 2.5; IECC Chapter 5 [CE] as replaced); commercial Level 3 alterations must additionally be Electric Ready, install Solar Ready Components (under 5,000 sq ft) or rooftop PV (5,000+ sq ft), and provide Level II EVSE plus 10% EV-Ready spaces where the building has 2+ parking spaces (IEBC Secs. 907.2-907.3 as amended); Current Gunnison County building contractor license required — no permit issued since February 1, 2023 without one (Town Code Sec. 18-13-40(e)); Complete Sec. 18-13-20 submittal package: legal description, deed, plot plan, elevations, floor plans, site development plan (paving, walls/fences, landscaping, exterior lighting), front elevation showing site context, and cross-sections; Valuation set by the Building Official from the ICC building valuation data table multiplied by a 2.70 regional modifier, or other evidence of value, whichever is greater (Town Code Sec. 18-13-40(b)); If the parcel falls in a mapped Class 1 or Class 2 Colorado Wildfire Resiliency Code fire hazard area, CWRC structure-hardening applies to new commercial structures, changes of use, additions increasing footprint 500+ sq ft, and replacement of more than 25% of exterior siding or roof covering (Town Code Article 6.5; Town enforcement begins June 1, 2026); Certificate of occupancy required before any structure or altered portion may be rented, occupied or used (Town Code Sec. 18-13-70); Construction must commence within 180 days of permit issuance; the permit expires one year after issuance with a single 6-month renewal available for good cause (Building Permit Contract Agreement; Town Code Sec. 18-13-60). If your project isn't listed, confirm with Town of Crested Butte Building Department (Community Development Department) at (970) 349-5338 before starting work.

In Crested Butte, the published Building Permit Fee — valuation $1.00 to $500.00 is: $28.42. Additional published fees: Building Permit Fee — valuation $501.00 to $2,000.00 — $28.42 plus $3.68 per $100 of TSV or fraction thereof above $501; Building Permit Fee — valuation $2,001.00 to $25,000.00 — $83.74 plus $16.95 per $1,000 of TSV or fraction thereof above $2,001; Building Permit Fee — valuation $25,001.00 to $50,000.00 — $473.79 plus $12.18 per $1,000 of TSV or fraction thereof above $25,001; Building Permit Fee — valuation $50,001.00 to $100,000.00 — $778.58 plus $8.47 per $1,000 of TSV or fraction thereof above $50,001; Building Permit Fee — valuation $100,001.00 to $500,000.00 — $1,202.07 plus $6.77 per $1,000 of TSV or fraction thereof above $100,001; Building Permit Fee — valuation $500,001.00 to $1,000,000.00 — $3,911.05 plus $5.74 per $1,000 of TSV or fraction thereof above $500,001; Building Permit Fee — valuation $1,000,001.00 to $5,000,000.00 — $6,681.04 plus $3.00 per $1,000 of TSV or fraction thereof above $1,000,001; Building Permit Fee — valuation $5,000,001.00 and over — $18,327 plus $1.00 per $1,000 of TSV or fraction thereof above $5,000,001; Plan Review Fee (Commercial) — 60% of Permit Fee; Construction Documents Examination (Commercial) — 60% of Permit Fee; BOZAR Design Review — Major Project — $1,000.00 plus $125.00 publication fee; BOZAR Design Review — Minor Project (small remodel/accessory building) — $750.00 plus $125.00 publication fee ($700.00 with no-picture publication); BOZAR Special Review Classification surcharge — $750.00 additional; Insubstantial Design Review - DRC — $120.00; Additional DRC Meeting — $100.00 per meeting beyond the first 2; Use Tax Deposit — Not less than 4.5% of 60% of Total Project Valuation; Performance Deposit — 0.50% of Total Structure Value; Affordable housing payment-in-lieu (new non-residential floor area) — $41.82 per sq ft; Capital Expansion Fee — Fire (business/commercial/tourist) — $0.14 per sq ft; Mechanical Permit (boiler/compressor/absorption system) — $100.00; Mechanical Exhaust Hood — $200.00; Water/Sewer Tap Fees (new construction) — $14,349 water plus $17,726 sewer, per EQR; Work without Permit — $250 to $1,000 per day, plus applicable permit fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

The Building Division publishes no plan-review SLA. The BOZAR gate that precedes it does have published clocks: formally reviewed projects take at least 2 months per the Town's schedule overview, applicants are entitled to a decision within 60 days of a complete application (unless they elect extra DRC meetings), and BOZAR must decide within 90 days or the application is deemed approved (Town Code Secs. 16-22-90 and 16-22-110).

You'll need: BOZAR Development Permit Application; Building Permit Application; Sealed commercial construction documents; Gunnison County Building Contractor License; Materials List Form - Primary Structure. Depending on your project, Crested Butte may also ask for: Statement of Authority Form; Limited Power of Attorney; Pretreatment Application (Fats, Oils & Grease). See the required-documents checklist on this page for details on each.

Apply through Town of Crested Butte Building Department (Community Development Department) at 507 Maroon Ave, Crested Butte, CO 81224 (Building Department mailing address: PO Box 39, Crested Butte, CO 81224). Phone: (970) 349-5338, email: building@crestedbutte-co.gov. Office hours: Monday-Friday 8:30 a.m. to 5:00 p.m. Building Official Astrid Matison (ext. 116, amatison@crestedbutte-co.gov). Building Inspector Josh Staab (ext. 127, jstaab@crestedbutte-co.gov). Community Development Director Mel Yemma (ext. 119, melyemma@crestedbutte-co.gov). BOZAR/Planning questions: planning@crestedbutte-co.gov, (970) 349-5338 ext. 121.. Official information: https://townofcrestedbutte.colorado.gov/planning-permitting/community-development.

No. Crested Butte issues one building permit type for all commercial work; the Town's own issued-permit reports classify TI-style projects as 'Alteration Level 1 Commercial', 'Alteration Level 2 Commercial', or 'Commercial Change of Use'. The practical TI distinctions are the 60% commercial plan review fee, mandatory sealed construction documents, and — for interior-only work — the possibility of an 'insubstantial' determination ($120 DRC fee) that skips the full BOZAR hearing and newspaper publication.

Every building permit application must clear BOZAR before submittal, and permits in the B1/B2/B3 Business Districts are automatically 'special review' class with a $750 surcharge and published 3-D perspective drawing. But the Building Inspector plus one designated BOZAR member may waive the full Board hearing for work judged 'insubstantial' — evaluated on street visibility, extent of change relative to the structure, and neighborhood effect — which is how interior-only tenant finishes typically proceed.

Yes, for new construction: all new commercial buildings must be All Electric Buildings (commercial kitchen heat-processing equipment excepted but electric-ready), buildings under 5,000 sq ft must be solar-ready, buildings 5,000 sq ft and larger must install rooftop PV, and EV parking (one Level II charger, 10% EV-ready spaces, DC fast charger at 5+ required spaces) is required. Existing-building TIs escape these unless the alteration reaches Level 3 (more than 50% of the work area).

This one’s complicated · Get an expediter