Commercial Building Permit (New Construction, Alteration & Tenant Improvement) — Crested Butte, Colorado · Requirements sheet
Verified 2026-08-02 · Source: https://townofcrestedbutte.colorado.gov/planning-permitting/community-development
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit (New Construction, Alteration & Tenant Improvement) in Crested Butte, Colorado
Required for all commercial construction in the Town of Crested Butte — new commercial and mixed-use buildings, additions, alterations, changes of use, and tenant improvements — under Town Code Sec. 18-13-40(a) ('No building or structure shall be erected, constructed, structurally altered, moved, demolished or changed without first obtaining a building permit'). Reviewed under the 2024 IBC (Chapter 18, Article 1), the IEBC for work on existing buildings, and the Town's IgCC Article 1.5 green-construction provisions for new commercial construction. Crested Butte has no separate commercial permit application or tenant-improvement permit type: the Town's own Jan-June 2026 issued-permit report shows commercial interior projects run through the single Building Permit process classified as 'Alteration Level 1 Commercial', 'Alteration Level 2 Commercial', or 'Commercial Change of Use'. Because most of downtown sits in the B1/B2/B3 Business Districts inside the National Historic District, commercial building permit applications are automatically classified 'special review' at BOZAR (Town Code Sec. 16-22-110(b)), the Town's historic/architectural review board — BOZAR approval is required BEFORE the building permit application may be submitted.
Verified 2026-08-02 · Source
When you need this permit
- BOZAR (Board of Zoning and Architectural Review) approval of a Development Permit Application is required before a building permit application may be submitted (Town Code Sec. 18-13-40(d); BOZAR page: 'you must receive BOZAR approval before applying for building permits') — BOZAR, not a separately named 'Historic Preservation Commission', is the body that administers historic-district design review in Crested Butte
- Automatic 'special review' BOZAR classification for any building permit in a B1, B2 or B3 Business District (Town Code Sec. 16-22-110(b)) — special review applications pay an additional $750 fee and their public notice must include a published three-dimensional perspective drawing showing the building's facade and relationship to neighboring structures plus a location map
- All construction documents for commercial projects must be prepared by Colorado registered or licensed design professionals and signed and stamped with a seal (Town Code Sec. 18-13-20(a)(16))
- New commercial buildings must be All Electric Buildings — no combustion equipment for space heating, water heating, or clothes drying; Commercial Food Heat-processing Equipment is exempt from the electrification mandate (IBC Sec. 1301.1.2 as amended by Town Code Sec. 18-1-30; All Electric Building definition, Town Code Chapter 18)
- EV parking for new commercial: buildings/accessory structures with 2+ parking spaces must provide one Level II EVSE; 10% of total required spaces (rounded up) must be Electric Vehicle Ready; one 25 kW DC Fast Charger required where 5 or more parking spaces are required (IBC Sec. 1301.1.3 as amended)
- Solar for new commercial: buildings under 5,000 sq ft must install Solar Ready Components; buildings 5,000 sq ft or larger must install rooftop solar PV per Town Code Sec. 18-1.5-30(5), capped at Gunnison County Electric Association net-metering limits (IBC Sec. 1301.1.4 as amended; Town Code Sec. 18-9-50)
- New commercial construction must comply with the Town's adopted International Green Construction Code sections (Town Code Article 1.5): stormwater management, building water use reduction, appliance/HVAC efficiency, commercial food service operations, hot water distribution, on-site renewable energy systems, and kitchen exhaust systems
- Alterations, repairs, additions and changes of occupancy of existing commercial buildings are governed by the 2021 IEBC (Town Code Article 2.5; IECC Chapter 5 [CE] as replaced); commercial Level 3 alterations must additionally be Electric Ready, install Solar Ready Components (under 5,000 sq ft) or rooftop PV (5,000+ sq ft), and provide Level II EVSE plus 10% EV-Ready spaces where the building has 2+ parking spaces (IEBC Secs. 907.2-907.3 as amended)
- Current Gunnison County building contractor license required — no permit issued since February 1, 2023 without one (Town Code Sec. 18-13-40(e)) Contractor
- Complete Sec. 18-13-20 submittal package: legal description, deed, plot plan, elevations, floor plans, site development plan (paving, walls/fences, landscaping, exterior lighting), front elevation showing site context, and cross-sections
- Valuation set by the Building Official from the ICC building valuation data table multiplied by a 2.70 regional modifier, or other evidence of value, whichever is greater (Town Code Sec. 18-13-40(b))
- If the parcel falls in a mapped Class 1 or Class 2 Colorado Wildfire Resiliency Code fire hazard area, CWRC structure-hardening applies to new commercial structures, changes of use, additions increasing footprint 500+ sq ft, and replacement of more than 25% of exterior siding or roof covering (Town Code Article 6.5; Town enforcement begins June 1, 2026)
- Certificate of occupancy required before any structure or altered portion may be rented, occupied or used (Town Code Sec. 18-13-70)
- Construction must commence within 180 days of permit issuance; the permit expires one year after issuance with a single 6-month renewal available for good cause (Building Permit Contract Agreement; Town Code Sec. 18-13-60)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 5 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation
Before concrete pour; 36-inch minimum frost line depth per the Town's design criteria (new construction/additions)
- 2
Rough Frame
Structural framing complete before cover; work must match BOZAR-approved plans — deviations discovered by the Building Inspector or Board members trigger a stop-work order and possible new-permit requirement (Town Code Sec. 18-13-40(g))
- 3
Rough Electrical / Plumbing / Mechanical
Trade rough-ins before concealment; inspection requests must be submitted at least five (5) working days prior to the requested date (adopted IFC Sec. 108.2.1, Town Code Sec. 18-6-20(4))
- 4
Fire / Life-Safety
2021 IFC enforced in coordination with the Crested Butte Fire Protection District (CBFPD); kitchen exhaust/hood systems per the Town's adopted IgCC Sec. 701.4.3.8 and the $200 mechanical exhaust hood permit line
- 5
Final Building Inspection / Certificate of Occupancy
Certificate of occupancy required before the space may be rented, occupied or used (Town Code Sec. 18-13-70); permit expires one year after issuance, single 6-month renewal available for good cause
See the full Crested Butte inspection guide — scheduling & re-inspection fees →
Tips
- There is NO separate commercial building permit application or tenant-improvement permit type in Crested Butte — one Building Permit form covers all use types, and the Town's own Jan-June 2026 issued-permit report classifies commercial interior projects as 'Alteration Level 1 Commercial', 'Alteration Level 2 Commercial', or 'Commercial Change of Use' within the same BLD permit series. Budget for the commercial differences instead: 60% plan review (double the residential 30%), sealed construction documents on every commercial project, and the automatic BOZAR special review classification in the business districts.
- Crested Butte's historic-district gatekeeper is BOZAR (Board of Zoning and Architectural Review), not a separately named Historic Preservation Commission — and its approval must come BEFORE you may even submit a building permit application. Any building permit in the B1, B2 or B3 Business Districts (essentially the historic downtown core) is automatically classified 'special review' (Town Code Sec. 16-22-110(b)): plan on the $750 special review surcharge, a published 3-D perspective drawing of your facade in the Crested Butte News, and the Town's stated 2-month minimum review cycle (BOZAR must decide within 90 days of a complete application).
- Interior-only tenant improvements have a genuine fast path: work judged 'insubstantial' (Town Code Sec. 16-1-20 — judged on visibility from the street, extent of change relative to the structure, and neighborhood effect) can be waived past the full BOZAR hearing and publication by the Building Inspector plus one designated Board member, paying only the $120 Insubstantial Design Review - DRC fee. Interior fit-outs with no exterior changes are the textbook case; confirm the classification with the Building Department (building@crestedbutte-co.gov) before assuming it.
- Restaurant and food-service TIs: Commercial Food Heat-processing Equipment is exempt from the all-electric mandate (but must be electric-ready), the mechanical exhaust hood permit is $200, kitchen exhaust must meet the Town's adopted IgCC Sec. 701.4.3.8, and a Fats/Oils/Grease pretreatment application ($48.50) is required before discharging to the Town sewer.
- A commercial Level 3 alteration (more than 50% of the work area) is where an ambitious tenant improvement gets expensive: it triggers Electric Ready wiring, Solar Ready Components (or rooftop PV at 5,000+ sq ft), and Level II EVSE plus 10% EV-Ready parking where the building has 2 or more spaces (IEBC Secs. 907.2-907.3 as locally amended).
- New non-residential floor area pays a $41.82/sq ft affordable-housing payment-in-lieu on top of permit fees — on a small commercial addition this line item can rival the building permit fee itself.
- A change of use is itself permit-triggering ('...or changed without first obtaining a building permit', Town Code Sec. 18-13-40(a)) and appears as its own 'Commercial Change of Use' classification in the Town's permit reports — converting, say, retail to restaurant needs a permit even with minimal construction, and a change of use can also trigger Colorado Wildfire Resiliency Code hardening in mapped Class 1/Class 2 zones once Town enforcement begins June 1, 2026.
- The Town has announced online permitting and payment via Cloudpermit as 'coming soon' (Licensing & Permitting page, checked 2026-08-02) and asks architects, designers, contractors, and owner-builders to register in the Cloudpermit User Registry now — check whether submittal has moved online before mailing paper applications. Owner-builder
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-02.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Crested Butte building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Crested Butte.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Crested Butte
Commercial Building Permit (New Construction, Alteration & Tenant Improvement) in other cities
Look up this fee in a different city →
Now live
Build your Crested Butte project checklist
Describe your project once and get every permit, document, and fee it triggers in Crested Butte — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →