Mountain Village building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Mountain Village, Colorado.
Verified 2026-07-06 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 455 Mountain Village Blvd., Suite A, Mountain Village, CO 81435 (Town Hall); Municipal Building at 411 Mountain Village Blvd., Mountain Village, CO 81435
- Phone
- 970-728-8000 (Town main line); Building Division direct 970-728-1392; Inspection Request Line 970-369-8251
- Office hours
- Town Hall and Municipal Building: Monday-Friday 8:00 a.m.-5:00 p.m. Building Division fax: 970-728-4342. Licensed contractor list requests: Tracy Bach, 970-369-8242.
- Website
- Official site
Inspection sequence
Applies to: Residential Building Permit (New Construction)
- 1
Foundation / Footings / Ufer / Setbacks
After forms and rebar placed, before pour; property corners/lines verification if within 5 ft of setback
- 2
Foundation Wall / Electrical Service
After form placement
- 3
Rough Frame / Rough Plumbing / Rough Mechanical / Rough Electric
Before covering; windows installed, flashed, and NFRC-labeled
- 4
Insulation
After rough approval
- 5
Final Building / Final Electrical / Final Plumbing / Final Mechanical / Final Grade
Fee and tax reconciliation completed at final building inspection
Applies to: Electrical Permit
- 1
Underground Electric / Electrical Service / Rough Electric
Wiring, service, and panel installed before concealment
- 2
Electrical Ceiling Close
Before cover, at rough inspection stage
- 3
Final Electrical
Devices installed, system energized and verified
Applies to: Mechanical / HVAC Permit
- 1
Rough Mechanical / Gas Pipe / Snow Melt
Ductwork, flues, hydronic snowmelt tubing, and equipment placement before concealment; gas pipe tested at 15 lbs air pressure for 20 minutes, hydronic piping at 60 lbs
- 2
Mechanical Ceiling Close
Before cover, at rough inspection stage
- 3
Final Mechanical
Equipment operational, commissioning report received for large systems; fee and tax reconciliation
Applies to: Plumbing Permit
- 1
Underground Plumbing
After pipe or wire is installed
- 2
Rough Plumbing
While exposed, before veneer; DWV air test 5 lbs, water test 60 lbs
- 3
Final Plumbing
Fixtures connected, no leaks, proper venting verified; fee and tax reconciliation
Applies to: Residential Addition / Interior Remodel Permit
- 1
Foundation (additions with new footings only)
Before concrete pour, per 48-inch minimum frost depth
- 2
Rough Frame / Rough Electrical / Rough Plumbing / Rough Mechanical
Trade rough-ins before concealment; connection to existing structure verified
- 3
Final Building / Final Electrical / Final Plumbing / Final Mechanical
All work complete per approved plans; fee and tax reconciliation
Applies to: Roofing Permit (Re-Roof)
- 1
Mid-Roofing / Roofing
After underlayment/flashing installed
- 2
Final Roofing
Completed roof; snow-shed safety measures and flashing/valley compliance verified
Applies to: Solar Permit, Electric Vehicle (EV) Charger Permit
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect placement before energizing
- 2
Final
Final electrical/building inspection preceding sign-off
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Mountain Village building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Mountain Village building permits
Get alerts for Mountain Village
We'll email you when Mountain Village's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.