Mountain Village building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Mountain Village, Colorado.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
455 Mountain Village Blvd., Suite A, Mountain Village, CO 81435 (Town Hall); Municipal Building at 411 Mountain Village Blvd., Mountain Village, CO 81435
Phone
970-728-8000 (Town main line); Building Division direct 970-728-1392; Inspection Request Line 970-369-8251
Office hours
Town Hall and Municipal Building: Monday-Friday 8:00 a.m.-5:00 p.m. Building Division fax: 970-728-4342. Licensed contractor list requests: Tracy Bach, 970-369-8242.

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation / Footings / Ufer / Setbacks

    After forms and rebar placed, before pour; property corners/lines verification if within 5 ft of setback

  2. 2

    Foundation Wall / Electrical Service

    After form placement

  3. 3

    Rough Frame / Rough Plumbing / Rough Mechanical / Rough Electric

    Before covering; windows installed, flashed, and NFRC-labeled

  4. 4

    Insulation

    After rough approval

  5. 5

    Final Building / Final Electrical / Final Plumbing / Final Mechanical / Final Grade

    Fee and tax reconciliation completed at final building inspection

Applies to: Electrical Permit

  1. 1

    Underground Electric / Electrical Service / Rough Electric

    Wiring, service, and panel installed before concealment

  2. 2

    Electrical Ceiling Close

    Before cover, at rough inspection stage

  3. 3

    Final Electrical

    Devices installed, system energized and verified

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical / Gas Pipe / Snow Melt

    Ductwork, flues, hydronic snowmelt tubing, and equipment placement before concealment; gas pipe tested at 15 lbs air pressure for 20 minutes, hydronic piping at 60 lbs

  2. 2

    Mechanical Ceiling Close

    Before cover, at rough inspection stage

  3. 3

    Final Mechanical

    Equipment operational, commissioning report received for large systems; fee and tax reconciliation

Applies to: Plumbing Permit

  1. 1

    Underground Plumbing

    After pipe or wire is installed

  2. 2

    Rough Plumbing

    While exposed, before veneer; DWV air test 5 lbs, water test 60 lbs

  3. 3

    Final Plumbing

    Fixtures connected, no leaks, proper venting verified; fee and tax reconciliation

Applies to: Residential Addition / Interior Remodel Permit

  1. 1

    Foundation (additions with new footings only)

    Before concrete pour, per 48-inch minimum frost depth

  2. 2

    Rough Frame / Rough Electrical / Rough Plumbing / Rough Mechanical

    Trade rough-ins before concealment; connection to existing structure verified

  3. 3

    Final Building / Final Electrical / Final Plumbing / Final Mechanical

    All work complete per approved plans; fee and tax reconciliation

Applies to: Roofing Permit (Re-Roof)

  1. 1

    Mid-Roofing / Roofing

    After underlayment/flashing installed

  2. 2

    Final Roofing

    Completed roof; snow-shed safety measures and flashing/valley compliance verified

Applies to: Solar Permit, Electric Vehicle (EV) Charger Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before energizing

  2. 2

    Final

    Final electrical/building inspection preceding sign-off

Re-inspection fees

Electrical PermitRe-inspection / Investigation Fee
$125.00 per hour

Mountain Village building permits

Get alerts for Mountain Village

We'll email you when Mountain Village's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.