Roofing Permit (Re-Roof) — Mountain Village, Colorado · Requirements sheet
Verified 2026-07-06 · Source: https://townofmountainvillage.com/site/assets/files/45318/community_development_fee_schedule_2025.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Roofing Permit (Re-Roof) in Mountain Village, Colorado
Required for re-roofing work in the Town of Mountain Village, reviewed as a Building Permit under the same Table 1-A valuation-based fee schedule (no separate flat re-roof fee is published). Roofing contractors must hold current ICC Roofing Contractor certification. Local amendments relax corrosion-resistance requirements for metal roofing given the Town's aged-metal aesthetic, but a Design Review Process fee applies for roof material changes reviewed by the Planning Department.
Verified 2026-07-06 · Source
When you need this permit
- Reviewed under the Town's currently-adopted IBC/IRC cycle; billed under the same Building Permit Table 1-A valuation schedule (no standalone flat roofing fee published)
- Roofing contractors must hold current ICC Roofing Contractor Exam certification for a Town building license
- Metal sheet roof coverings and valley flashing are NOT required to be corrosion-resistant or listed by any agency in Mountain Village (local amendment deleting the IBC/IRC's standard corrosion-resistance requirement) — where installed, metal roofing must be a minimum of 22 gauge
- Roof Material changes also route through the Planning Department's Design Review Process (Class 1, Staff Level Review) as a distinct fee/approval from the Building Division permit itself
- Snowmelt-free roof designs (with snow/ice-fall safety measures at protected entries) are eligible for a 20% Building Permit Fee discount under the Smart Building Incentive Program
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Mid-Roofing / Roofing
After underlayment/flashing installed
- 2
Final Roofing
Completed roof; snow-shed safety measures and flashing/valley compliance verified
See the full Mountain Village inspection guide — scheduling & re-inspection fees →
Tips
- Mountain Village's local amendment removes the standard IBC/IRC corrosion-resistance requirement for metal roofing and valley flashing (aged/unfinished metal is explicitly allowed) — don't assume a corrosion-resistant-coating requirement applies here as it might elsewhere.
- Even a like-for-like roof material swap routes through a separate Planning Department Class 1 Design Review, not just the Building Division permit — budget for both approvals.
- A snowmelt-free roof design with protected-entry safety measures qualifies for a 20% Building Permit Fee discount under the Smart Building Incentive Program — confirm eligibility with the Building Official before assuming standard fees apply.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Mountain Village building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Mountain Village
Roofing Permit (Re-Roof) in other cities
Compare roofing permit (re-roof) fees across Colorado →
Look up this fee in a different city →