Required for new commercial construction and commercial additions in the Town of Mountain Village. Confirmed as a genuinely distinct record type from residential permits directly on the Town's own live OpenGov Building Department portal (mountainvillageco.portal.opengov.com/ -> Building Department -> 'Commercial New Building Permit', described there as 'New commercial construction including commercial additions,' listed separately from 'Residential New Building Permit'). Reviewed under the Town's currently-adopted IBC cycle (2024 edition per the live Codes & Guides listing) as locally amended by Municipal Code Chapter 17.7, administered by the same Building Division, OpenGov portal, and Table 1-A valuation-based fee schedule as the Town's residential permits -- there is no separate commercial fee table, only a handful of commercial-specific fee/requirement differences (see below). The Town's OpenGov portal has no standalone 'tenant improvement' permit type: interior commercial remodels/tenant fit-outs are filed under the same 'Commercial and Residential Remodels' record type used for residential remodels, confirmed on the same live OpenGov Building Department page.

Verified 2026-08-02 · Source

When you need this permit

  • Applied for as the distinct 'Commercial New Building Permit' record type in the Town's OpenGov online portal (mountainvillageco.portal.opengov.com), separate from 'Residential New Building Permit'
  • Plans must comply with the Town's currently-adopted IBC cycle (2024 edition per the live Codes & Guides page) as amended by Municipal Code Chapter 17.7, rather than the IRC cycle used for one- and two-family residential permits
  • General contractors must hold the ICC General Contractor (A) Exam certification to obtain a Town building license for 'structures covered under the IBC'; the General Contractor (B) Exam instead covers 'light commercial and residential permits issued under the IBC and IRC' (Municipal Code 17.7.9.C.1) -- confirm which certification tier applies to your project scope with the Building Official before assuming GC-B is sufficient for a full commercial build
  • Contractor must complete OpenGov Contractor Registration before submitting the Commercial New Building Permit application Contractor
  • Site-specific soils and/or geologic investigation required before permit issuance wherever new foundations are placed (Municipal Code 17.7.5.E), stamped by a soils engineer/engineering geologist; this requirement applies to all new construction, not only residential; a geohazard analysis is additionally required where slopes exceed 30%, or landslide/avalanche/rockfall/expansive-soil/floodplain hazards are present
  • HERS (Home Energy Rating System) energy-rating thresholds (Municipal Code 17.7.12.C.7) apply only to detached single-family and condominium homes over 3,600 sq ft gross floor area -- confirmed NOT to apply to commercial building permits; no HERS documentation is required for this permit type
  • Exterior energy use (snowmelt systems, site-built pools/spas) for multi-family, mixed-use, and commercial development must be offset through the Renewable Energy Mitigation Program (REMP) or paid in lieu, calculated via the Town's Exterior Energy Use Calculation Spreadsheet, before permit issuance; the exempt square-footage threshold for this Multi-family/Mixed-Use/Commercial tier (1,000 sq ft plus 50 sq ft per dwelling unit) differs from the single-family tier (Municipal Code 17.7.11.A.5(d)(ii))
  • Fire Code (IFC) compliance -- including fire alarm systems (Section 907), fire sprinkler systems (Section 903), and Commercial Kitchen Hoods (Section 607, relevant to restaurant/food-service commercial buildouts) -- is administered separately by the Telluride Fire Protection District (TFPD), not the Town's own Building Division, per Municipal Code 17.7.19
  • Permit becomes invalid if work is not commenced within 180 days of issuance, suspended/abandoned for 180 days, or if no inspection is requested within 180 days of the last approved inspection (Municipal Code 17.7.3.B) -- the same universal rule applied to all Building Division permit types in this record

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Building Permit Fee — total valuation $1.00 to $1,500.00Table 1-A, 2025 Community Development Fee Schedule; the same valuation-based Table 1-A applies to both commercial and residential Building Permit Fees -- no separate commercial fee table exists
Waived
Building Permit Fee — total valuation $1,501.00 to $25,000.00Community Development Fee Schedule 2025, Building Department Fees, Table 1-A Building Permit Fee
$90.00 for the first $2,000 plus $15.75 for each additional $1,000 or fraction thereof, to and including $25,000.00
Building Permit Fee — total valuation $25,001.00 to $50,000.00Community Development Fee Schedule 2025, Building Department Fees, Table 1-A Building Permit Fee
$453.20 for the first $25,000 plus $11.50 for each additional $1,000 or fraction thereof, to and including $50,000.00
Building Permit Fee — total valuation $50,001.00 to $100,000.00Community Development Fee Schedule 2025, Building Department Fees, Table 1-A Building Permit Fee
$750.00 for the first $50,000 plus $7.95 for each additional $1,000 or fraction thereof, to and including $100,000.00
Building Permit Fee — total valuation $100,001.00 to $500,000.00Community Development Fee Schedule 2025, Building Department Fees, Table 1-A Building Permit Fee; the published table prints this tier's lower bound as "$100,0001.00"
$1,150.00 for the first $100,000 plus $6.50 for each additional $1,000 or fraction thereof, to and including $500,000.00
Building Permit Fee — total valuation $500,001.00 to $1,000,000.00Community Development Fee Schedule 2025, Building Department Fees, Table 1-A Building Permit Fee
$3,760.00 for the first $500,000 plus $5.75 for each additional $1,000 or fraction thereof, to and including $1,000,000.00
Building Permit Fee — total valuation $1,000,001.00 and upCommunity Development Fee Schedule 2025, Building Department Fees, Table 1-A Building Permit Fee
$6,700.00 for the first $1,000,000 plus $5.25 for each additional $1,000 or fraction thereof
Plan Review FeeNon-refundable, due at time of permit submittal
65% of the Building Permit Fee
Mountain Village Use TaxCommunity Development Fee Schedule 2025, formula for calculating permit fees based on construction valuation, "Mountain Village Use Tax: 4 1/2% of 40% of valuation of project"
4.5% of 40% of project valuation
San Miguel County Use TaxCommunity Development Fee Schedule 2025, formula for calculating permit fees based on construction valuation, "San Miguel County Use Tax: 1% of 40% of valuation of the project"
1% of 40% of project valuation
Road Impact Fee2025 Community Development Fee Schedule explicitly states this $1.00/sq ft rate applies to 'all new construction, residential and commercial, including additions' -- confirmed to be the same rate, not a separate commercial rate
$1.00 per gross square foot of new construction
Use of Outside Consultants for Plan Checking and Inspections
Per the primary-source Community Development Fee Schedule 2025 PDF (page 5, item 5): 'Use of outside consultants for plan checking and inspections -- $250 Per Hour,' with no commercial/residential split stated. Show full citationPer the primary-source Community Development Fee Schedule 2025 PDF (page 5, item 5): 'Use of outside consultants for plan checking and inspections -- $250 Per Hour,' with no commercial/residential split stated. Independently corroborated by the Town's Development Guide PDF (Last updated 2026-05-14), page 18, which carries the same $250/hour figure under 'Building Department Fees continued.' Do not confuse this line with Table 1-A item 8 (Solar Permit fee), a wholly unrelated line item that carries a $1,000 commercial / $500 residential split; that Solar Permit fee is not separately modeled in this permit type.
$250.00 per hour
Exterior Energy Use Offset (REMP) — Multi-family/Mixed-Use/Commercial tierApplies to snowmelt systems, site-built pools/spas beyond the exempt threshold of 1,000 sq ft plus 50 sq ft per dwelling unit for this tier (vs. a smaller single-family exemption); payable before permit issuance
Calculated via the Town's Exterior Energy Use Calculation Spreadsheet

Review timeline

Plan reviewMountain Village’s published plan-review target
14–42 business days

How long did your Commercial New Building Permit permit actually take in Mountain Village?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation / Footings / Ufer / Setbacks

    After forms and rebar placed, before pour; property corners/lines verification if within 5 ft of setback

  2. 2

    Rough Frame / Rough Plumbing / Rough Mechanical / Rough Electric

    Before covering; windows installed, flashed, and NFRC-labeled

  3. 3

    Rough Fire Alarm Wiring / Fire Sprinkler Rough

    At rough inspection, before cover; approved fire alarm plans required; coordinated with the Telluride Fire Protection District

  4. 4

    Occupancy Separation (Fire Wall, Fire Stopping) / Draft Stopping

    At rough inspection, before cover -- inspection items specific to multi-occupancy and commercial construction per the Town's own Inspection Information document

  5. 5

    Rough Accessibility

    After backing install; installation instructions requested

  6. 6

    Insulation

    After rough approval

  7. 7

    Final Building / Final Electrical / Final Plumbing / Final Mechanical / Final Accessibility

    Fee and tax reconciliation completed at final building inspection; signed Fire Marshal approval required before final building inspection

See the full Mountain Village inspection guide — scheduling & re-inspection fees →

Tips

  • Mountain Village's OpenGov portal treats 'Commercial New Building Permit' and 'Residential New Building Permit' as two distinct application record types -- make sure you select the correct one; selecting the wrong type on a mixed-use or light-commercial project is a common early mistake.
  • There is NO standalone tenant-improvement or TI permit type in Mountain Village. A commercial interior remodel/tenant fit-out is filed under the same 'Commercial and Residential Remodels' OpenGov record type used for residential remodels -- don't search for a 'tenant improvement permit' that doesn't exist in this jurisdiction's system.
  • Confirm which ICC General Contractor exam tier applies to your project before assuming your license is sufficient: GC-A covers all IBC structures, GC-B is explicitly limited to 'light commercial and residential' work, and GC-C (Residential) only covers one- and two-family IRC dwellings.
  • Restaurant, food-service and commercial-kitchen buildouts trigger the Town's local Commercial Kitchen Hoods amendment (Municipal Code 17.7.19, IMC Section 607) - budget time and cost for that review on top of the standard Building Division process.
  • The $250/hour 'Use of Outside Consultants for Plan Checking and Inspections' fee (Table 1-A item 5) applies equally to commercial and residential projects -- there is no commercial/residential split for this line item, unlike the (separate, unrelated) Solar Permit fee.
  • Budget 2-6 weeks for Building Division plan review of a commercial or single-family project, per the Town's own Development Guide FAQ -- faster utility/small-remodel/re-roof permits are reviewed within 2 working days by contrast, so don't assume the same fast turnaround applies to a full commercial building permit.

Frequently asked questions

Mountain Village requires a commercial new building permit for: Applied for as the distinct 'Commercial New Building Permit' record type in the Town's OpenGov online portal (mountainvillageco.portal.opengov.com), separate from 'Residential New Building Permit'; Plans must comply with the Town's currently-adopted IBC cycle (2024 edition per the live Codes & Guides page) as amended by Municipal Code Chapter 17.7, rather than the IRC cycle used for one- and two-family residential permits; General contractors must hold the ICC General Contractor (A) Exam certification to obtain a Town building license for 'structures covered under the IBC'; the General Contractor (B) Exam instead covers 'light commercial and residential permits issued under the IBC and IRC' (Municipal Code 17.7.9.C.1) -- confirm which certification tier applies to your project scope with the Building Official before assuming GC-B is sufficient for a full commercial build; Contractor must complete OpenGov Contractor Registration before submitting the Commercial New Building Permit application; Site-specific soils and/or geologic investigation required before permit issuance wherever new foundations are placed (Municipal Code 17.7.5.E), stamped by a soils engineer/engineering geologist; this requirement applies to all new construction, not only residential; a geohazard analysis is additionally required where slopes exceed 30%, or landslide/avalanche/rockfall/expansive-soil/floodplain hazards are present; HERS (Home Energy Rating System) energy-rating thresholds (Municipal Code 17.7.12.C.7) apply only to detached single-family and condominium homes over 3,600 sq ft gross floor area -- confirmed NOT to apply to commercial building permits; no HERS documentation is required for this permit type; Exterior energy use (snowmelt systems, site-built pools/spas) for multi-family, mixed-use, and commercial development must be offset through the Renewable Energy Mitigation Program (REMP) or paid in lieu, calculated via the Town's Exterior Energy Use Calculation Spreadsheet, before permit issuance; the exempt square-footage threshold for this Multi-family/Mixed-Use/Commercial tier (1,000 sq ft plus 50 sq ft per dwelling unit) differs from the single-family tier (Municipal Code 17.7.11.A.5(d)(ii)); Fire Code (IFC) compliance -- including fire alarm systems (Section 907), fire sprinkler systems (Section 903), and Commercial Kitchen Hoods (Section 607, relevant to restaurant/food-service commercial buildouts) -- is administered separately by the Telluride Fire Protection District (TFPD), not the Town's own Building Division, per Municipal Code 17.7.19; Permit becomes invalid if work is not commenced within 180 days of issuance, suspended/abandoned for 180 days, or if no inspection is requested within 180 days of the last approved inspection (Municipal Code 17.7.3.B) -- the same universal rule applied to all Building Division permit types in this record. If your project isn't listed, confirm with Town of Mountain Village Planning and Development Services Department, Building Division at 970-728-8000 (Town main line); Building Division direct 970-728-1392; Inspection Request Line 970-369-8251 before starting work.

In Mountain Village, the published Building Permit Fee — total valuation $1.00 to $1,500.00 is: Waived. Additional published fees: Building Permit Fee — total valuation $1,501.00 to $25,000.00 — $90.00 for the first $2,000 plus $15.75 for each additional $1,000 or fraction thereof, to and including $25,000.00; Building Permit Fee — total valuation $25,001.00 to $50,000.00 — $453.20 for the first $25,000 plus $11.50 for each additional $1,000 or fraction thereof, to and including $50,000.00; Building Permit Fee — total valuation $50,001.00 to $100,000.00 — $750.00 for the first $50,000 plus $7.95 for each additional $1,000 or fraction thereof, to and including $100,000.00; Building Permit Fee — total valuation $100,001.00 to $500,000.00 — $1,150.00 for the first $100,000 plus $6.50 for each additional $1,000 or fraction thereof, to and including $500,000.00; Building Permit Fee — total valuation $500,001.00 to $1,000,000.00 — $3,760.00 for the first $500,000 plus $5.75 for each additional $1,000 or fraction thereof, to and including $1,000,000.00; Building Permit Fee — total valuation $1,000,001.00 and up — $6,700.00 for the first $1,000,000 plus $5.25 for each additional $1,000 or fraction thereof; Plan Review Fee — 65% of the Building Permit Fee; Mountain Village Use Tax — 4.5% of 40% of project valuation; San Miguel County Use Tax — 1% of 40% of project valuation; Road Impact Fee — $1.00 per gross square foot of new construction; Use of Outside Consultants for Plan Checking and Inspections — $250.00 per hour; Exterior Energy Use Offset (REMP) — Multi-family/Mixed-Use/Commercial tier — Calculated via the Town's Exterior Energy Use Calculation Spreadsheet. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

The Town's Development Guide (last updated May 14, 2026) states that building reviews for single-family dwellings and commercial projects take 2-6 weeks, depending on complexity and size. Faster-track permit types (utility permits, small remodels, re-roofs) are usually reviewed within 2 working days by the Building Division instead.

You'll need: Commercial New Building Permit Application (OpenGov); Contractor Registration (OpenGov); Soils/Geologic Investigation Report. See the required-documents checklist on this page for details on each.

Mountain Village requires 7 inspection(s) for a commercial new building permit, in order: Foundation / Footings / Ufer / Setbacks, Rough Frame / Rough Plumbing / Rough Mechanical / Rough Electric, Rough Fire Alarm Wiring / Fire Sprinkler Rough, Occupancy Separation (Fire Wall, Fire Stopping) / Draft Stopping, Rough Accessibility, Insulation, Final Building / Final Electrical / Final Plumbing / Final Mechanical / Final Accessibility. Schedule each through Town of Mountain Village Planning and Development Services Department, Building Division (970-728-8000 (Town main line); Building Division direct 970-728-1392; Inspection Request Line 970-369-8251).

Apply through Town of Mountain Village Planning and Development Services Department, Building Division at 455 Mountain Village Blvd., Suite A, Mountain Village, CO 81435 (Town Hall); Municipal Building at 411 Mountain Village Blvd., Mountain Village, CO 81435. Phone: 970-728-8000 (Town main line); Building Division direct 970-728-1392; Inspection Request Line 970-369-8251, email: Contact form only at time of this review (townofmountainvillage.com/business/building/building-division/); no single published department inbox address found. Office hours: Town Hall and Municipal Building: Monday-Friday 8:00 a.m.-5:00 p.m. Building Division fax: 970-728-4342. Licensed contractor list requests: Tracy Bach, 970-369-8242.. Official information: https://townofmountainvillage.com/business/building/building-division/.

Yes. The Town's own OpenGov Building Department portal lists 'Commercial New Building Permit' ('New commercial construction including commercial additions') as a distinct record type from 'Residential New Building Permit.' Both are reviewed by the same Building Division under Municipal Code Chapter 17.7 and billed on the same Table 1-A valuation-based fee schedule -- commercial construction uses the IBC cycle rather than the IRC used for one- and two-family homes, and a handful of fee/requirement items (REMP exempt-footage tier, HERS inapplicability, ICC GC-A/GC-B contractor certification) differ from the residential permit.

No. The Town's OpenGov portal has no standalone tenant-improvement permit type. Interior commercial remodels and tenant fit-outs are filed under the same 'Commercial and Residential Remodels' record type used for residential remodels, per the Town's OpenGov Building Department page.

Sources & verification

Verified against official sources. Last reviewed 2026-08-02.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Mountain Village building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Mountain Village.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.

Mountain Village's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Mountain Village yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when Mountain Village lands. Privacy.