Residential Building Permit (New Construction) — Mountain Village, Colorado · Requirements sheet
Verified 2026-07-06 · Source: https://townofmountainvillage.com/business/building/building-division/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit (New Construction) in Mountain Village, Colorado
Required for new construction of single-family, duplex, and townhouse structures in the Town of Mountain Village. Reviewed under the Town's currently-adopted ICC code cycle (2024 IBC/IRC per the Town's live Codes & Guides listing) as locally amended by Municipal Code Chapter 17.7, including HERS energy-rating thresholds, Renewable Energy Mitigation Program (REMP) requirements for exterior energy use, and the Town's Climatic and Geographic Design Criteria.
Verified 2026-07-06 · Source
When you need this permit
- Plans must comply with the Town's currently-adopted IBC/IRC cycle (2024 edition per the live Codes & Guides page) as amended by Municipal Code Chapter 17.7
- Site-specific soil and/or geologic investigation required before permit issuance wherever new foundations are placed, stamped by a soils engineer/engineering geologist; a geohazard analysis is additionally required where slopes exceed 30%, or landslide/avalanche/rockfall/expansive-soil/floodplain hazards are present
- HERS rating confirmation required before permit issuance for detached single-family/condominium homes over 3,600 sq ft gross floor area (sliding scale: 60 or lower for 3,601-7,000 sq ft; 55 or lower for 7,001-13,000 sq ft; 50 or lower above 13,000 sq ft), confirmed again at or before Certificate of Occupancy
- Exterior energy use (snowmelt, site-built pools/spas) must be offset through the Renewable Energy Mitigation Program (REMP) or paid in lieu, calculated via the Town's Exterior Energy Use Calculation Spreadsheet, before permit issuance, unless within the exempt square-footage thresholds
- Licensed general contractor (with current ICC certification matching project scope) required for multi-trade projects; contractor must complete OpenGov Contractor Registration before submitting the building permit application Contractor
- Applications submitted via the Town's OpenGov online portal (mountainvillageco.portal.opengov.com)
- Permit becomes invalid if work is not commenced within 180 days of issuance, suspended/abandoned for 180 days, or if no inspection is requested within 180 days of the last approved inspection
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation / Footings / Ufer / Setbacks
After forms and rebar placed, before pour; property corners/lines verification if within 5 ft of setback
- 2
Foundation Wall / Electrical Service
After form placement
- 3
Rough Frame / Rough Plumbing / Rough Mechanical / Rough Electric
Before covering; windows installed, flashed, and NFRC-labeled
- 4
Insulation
After rough approval
- 5
Final Building / Final Electrical / Final Plumbing / Final Mechanical / Final Grade
Fee and tax reconciliation completed at final building inspection
See the full Mountain Village inspection guide — scheduling & re-inspection fees →
Tips
- The Town's live Building Division page lists the current code cycle as 2024 IBC/IRC/IMC/IFGC/IEBC/IFC, 2023 NEC, and 2021 IECC — but the only full amendment-text PDF this session could access is still on the 2018 code cycle (2020 NEC). Confirm current section-by-section amendment language (climatic design table, HERS thresholds, contractor exam list) against the Town directly before relying on older figures for a specific project.
- A site-specific soils/geologic report is mandatory before permit issuance for any new foundation — budget time for this ahead of submittal, especially on sites with steep slopes, potential avalanche/rockfall exposure, or expansive soils, which additionally require a stamped geohazard analysis.
- Projects with any exterior energy use (snowmelt driveways, hot tubs, pools) should calculate REMP offset obligations early via the Town's Exterior Energy Use Calculation Spreadsheet — this is a payment or renewable-offset requirement due before permit issuance, not an afterthought.
- Permits under $1,500 total valuation are fee-waived entirely under Table 1-A — useful for small trade-specific repairs.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Mountain Village building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Mountain Village
Residential Building Permit (New Construction) in other cities
Compare residential building permit (new construction) fees across Colorado →
Look up this fee in a different city →