Change of Use / Change of Occupancy in Mountain Village, Colorado
Mountain Village has no standalone 'Change of Use Permit' application or OpenGov record type -- confirmed against both the Town's live Planning Department (9 record types) and Building Department (8 record types) OpenGov category pages, neither of which lists one. Instead, Municipal Code 17.7.7.A (Certificate of Occupancy) requires that 'no permitted change in the existing occupancy classification of a building or structure or portion thereof shall be made until the Building Official has issued a Certificate of Occupancy' -- meaning a change of use/occupancy is processed through the standard Building Division permit and CO process (filed as a 'Commercial and Residential Remodels' or 'Miscellaneous Permit' OpenGov record, depending on scope), not a dedicated application. A change of use that generates new employees separately triggers Housing Impact Mitigation Requirements under CDC 17.3.9.
Verified 2026-08-14 · Source
When you need this permit
- No building/structure may be used or occupied, and no permitted change in existing occupancy classification may be made, until the Building Official issues a Certificate of Occupancy (CO), per Municipal Code 17.7.7.A
- Because no distinct 'Change of Use Permit' OpenGov record type exists, a change of use/occupancy is filed under whichever existing Building Division record type matches the scope of any associated work (e.g., 'Commercial and Residential Remodels' if tenant improvements are involved, or 'Miscellaneous Permit' for single-trade work) -- confirmed by reviewing the Town's live 8-item Building Department OpenGov list directly
- Design Regulations (Chapter 17.5, DRB Design Review) apply to 'all development where there is an exterior alteration proposed or where an exterior alteration is required due to a change in use,' per Sec. 17.5.2.A -- meaning a pure change of use with NO exterior alteration does not by itself trigger DRB/Design Review, only the Building Official's CO process
- A change of use that generates new employees is subject to Housing Impact Mitigation Requirements (CDC 17.3.9.B: 'This Section also applies to a change of use that generates new employees'), requiring production of workforce housing units (in or out of Town) or, as a less-preferred alternative, a cash payment, calculated via the Town's Mitigation Worksheet
- Redevelopment of a preexisting use, and a change in use, are EXEMPT from Housing Impact Mitigation Requirements provided the activity does not generate new employees, per CDC 17.3.9.E.3
- In the Town's Active Open Space zone districts specifically, a change in use of an existing active open space use requires a Conditional Use Permit, per CDC 17.3.4.A.1 -- a zone-specific trigger distinct from the general CO process
- A Certificate of Compliance is issued in lieu of a CO when the permitted work is not designed for occupancy; a Completion Certificate is issued at completion of additions, remodels, or repair from flood/fire/natural disaster, per Sec. 17.7.7.B
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Building Official Compliance Review / Certificate of Occupancy
The Building Official must issue a Certificate of Occupancy (or a Certificate of Compliance for non-occupancy work) before a permitted change in occupancy classification may be made, per Sec. 17.7.7
See the full Mountain Village inspection guide — scheduling & re-inspection fees →
Tips
- Mountain Village has no dedicated 'Change of Use Permit' -- confirmed against the Town's own live OpenGov Planning and Building Department category lists, neither of which has one. Don't search for a form that doesn't exist; instead file the underlying Building Division permit type that matches the physical scope of the change and let the Certificate of Occupancy process govern the occupancy-classification change itself.
- A change of use with NO exterior alteration does not trigger DRB/Design Review under Sec. 17.5.2.A -- but a change of use WITH an exterior alteration does, so confirm early whether your project's scope includes any exterior work.
- If your change of use will generate new employees (e.g., converting low-employee-generation retail to a restaurant), budget for Housing Impact Mitigation under CDC 17.3.9 -- workforce housing production or a cash payment calculated via the Town's Mitigation Worksheet. A change of use that does NOT generate new employees is explicitly exempt.
- If your change of use is within one of the Town's Active Open Space zone districts, check CDC 17.3.4.A.1 first -- that zone-specific rule requires a Conditional Use Permit, not just the general CO process.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-14.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Mountain Village building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Mountain Village
Change of Use / Change of Occupancy in other cities
Compare change of use / change of occupancy fees across Colorado →