Solar Permit — Mountain Village, Colorado · Requirements sheet
Verified 2026-07-19 · Source: https://townofmountainvillage.com/site/assets/files/47529/november_20-_2025_tow_council_2026_fee_resolution.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar Permit in Mountain Village, Colorado
Required for solar photovoltaic (and other solar energy) system installation in the Town of Mountain Village. The Town's Building Department Fees table (Table 1-A) lists a dedicated flat 'Solar Permit' fee line, separate from the general valuation-based Building Permit Fee table — $500 for residential, $1,000 for commercial — consistent with the Colorado statewide solar permit fee cap under C.R.S. § 24-48.5-113 (HB21-1284, $500 residential/$1,000 commercial). A standalone Renewable Energy System Only Planning Department application (Design Review Process, Class 3) carries no fee, as a Town incentive.
Verified 2026-07-19 · Source
When you need this permit
- Building Permit required from the Building Division for the solar installation, submitted via the Town's OpenGov online portal (mountainvillageco.portal.opengov.com)
- If the project is a Renewable Energy System Only Application under the Planning Department's Design Review Process (Class 3), no Planning Department fee applies (fee waived as an incentive)
- Licensed contractor required; contractor must complete OpenGov Contractor Registration before submitting the application Contractor
- Reviewed under the Town's currently-adopted ICC code cycle (2024 IBC/IRC per the Town's live Codes & Guides listing) as locally amended by Municipal Code Chapter 17.7, including NEC electrical provisions
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect placement before energizing
- 2
Final
Final electrical/building inspection preceding sign-off
See the full Mountain Village inspection guide — scheduling & re-inspection fees →
Tips
- Mountain Village's Solar Permit fee ($500 residential / $1,000 commercial) is a distinct flat line item on Table 1-A, separate from the general valuation-based Building Permit Fee bracket table used for other construction — do not apply the valuation formula to a stand-alone solar project.
- If filing as a Renewable Energy System Only Application through the Planning Department's Design Review Process, no Planning Department fee applies (waived as an incentive) — but the separate Building Department Solar Permit fee ($500/$1,000) still applies.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Mountain Village building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Mountain Village
Solar Permit in other cities
Compare solar permit fees across Colorado →
Look up this fee in a different city →