Electric Vehicle (EV) Charger Permit in Mountain Village, Colorado

Mountain Village has no distinct EV-charger permit type or fee line — directly confirmed against the Town's 2026 Fee Resolution Building Department Fees Table 1-A, which lists a dedicated 'Solar Permit' (item 8) and 'Geothermal exchange as an energy alternative' (item 9) but no EV-charger/EVSE line item. A new circuit, outlet, or panel/service upgrade to serve an EV charger is therefore permitted under the Town's standard, valuation-based Electrical Permit (2023 NEC/NFPA 70), administered through the same OpenGov portal used for Building, Plumbing, and Mechanical permits.

Reviewed 2026-08-02 · Source

When you need this permit

  • A new circuit, outlet, or panel/service upgrade to serve an EV charger requires an Electrical Permit governed by the 2023 NEC (NFPA 70), incorporated into Municipal Code Chapter 17.7.16
  • Electrical contractors must be licensed through the State of Colorado (Master and Contractor licenses per 12-23-101 C.R.S.) AND registered with the Town of Mountain Village Contractor
  • Administered via OpenGov (mountainvillageco.portal.opengov.com), the same portal used for building, plumbing, and mechanical permits
  • Fee calculated per Table 1-A of the Community Development Fee Schedule based on electrical valuation — confirmed to have no distinct EV-charger line item as of the 2026 Fee Resolution

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Electrical Permit Fee (applies to a new EV charger circuit/outlet/service-upgrade)Town of Mountain Village 2026 Fee Resolution, Building Department Fees, Table 1-A — items 8 (Solar Permit, $500/$1,000 flat) and 9 (Geothermal) have their own dedicated flat lines; no equivalent EV-charger line exists, so the general valuation-based Electrical Permit Fee applies
Calculated per Table 1-A of the Community Development Fee Schedule, based on electrical valuation
Plan Review FeeTown of Mountain Village Community Development Fee Schedule
65% of the Electrical Permit Fee

Review timeline

Plan review
Not published — contact the department

How long did your Electric Vehicle (EV) Charger Permit permit actually take in Mountain Village?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before energizing

  2. 2

    Final

    Final electrical/building inspection preceding sign-off

See the full Mountain Village inspection guide — scheduling & re-inspection fees →

Tips

  • There is no Mountain Village-specific 'EV charger permit' — a new circuit or outlet for EV charging falls under the standard, valuation-based Electrical Permit, unlike Solar (which has its own flat $500/$1,000 fee) or Geothermal.
  • Mountain Village's population (~1,264 at the 2020 Census) is below the 10,000-resident threshold that triggers Colorado HB24-1173's municipal EV-charging-permit mandate, so the Town is not confirmed to be legally required to have adopted EV-specific permitting standards.
  • The Town received a Colorado Energy Office grant for a four-post public DC Fast Charging Station in the Gondola Parking Garage, targeted for summer 2027 — a public infrastructure project, distinct from private residential EV charger permitting.

Frequently asked questions

Mountain Village requires an electric vehicle (ev) charger permit for: A new circuit, outlet, or panel/service upgrade to serve an EV charger requires an Electrical Permit governed by the 2023 NEC (NFPA 70), incorporated into Municipal Code Chapter 17.7.16; Electrical contractors must be licensed through the State of Colorado (Master and Contractor licenses per 12-23-101 C.R.S.) AND registered with the Town of Mountain Village; Administered via OpenGov (mountainvillageco.portal.opengov.com), the same portal used for building, plumbing, and mechanical permits; Fee calculated per Table 1-A of the Community Development Fee Schedule based on electrical valuation — confirmed to have no distinct EV-charger line item as of the 2026 Fee Resolution. If your project isn't listed, confirm with Town of Mountain Village Planning and Development Services Department, Building Division at 970-728-8000 (Town main line); Building Division direct 970-728-1392; Inspection Request Line 970-369-8251 before starting work.

No. The Town's 2026 Fee Resolution Building Department Fees table (Table 1-A) has a dedicated flat Solar Permit fee (item 8) and Geothermal fee (item 9), but no equivalent EV-charger line item. A new circuit or outlet for EV charging is billed under the standard valuation-based Electrical Permit Fee instead.

Mountain Village does not publish a plan-review timeline for this permit. Contact Town of Mountain Village Planning and Development Services Department, Building Division at 970-728-8000 (Town main line); Building Division direct 970-728-1392; Inspection Request Line 970-369-8251 for current turnaround.

You'll need: Electrical Permit Application (OpenGov); Colorado State Electrical License Documentation. See the required-documents checklist on this page for details on each.

Mountain Village requires 2 inspection(s) for an electric vehicle (ev) charger permit, in order: Rough Electrical, Final. Schedule each through Town of Mountain Village Planning and Development Services Department, Building Division (970-728-8000 (Town main line); Building Division direct 970-728-1392; Inspection Request Line 970-369-8251).

Apply through Town of Mountain Village Planning and Development Services Department, Building Division at 455 Mountain Village Blvd., Suite A, Mountain Village, CO 81435 (Town Hall); Municipal Building at 411 Mountain Village Blvd., Mountain Village, CO 81435. Phone: 970-728-8000 (Town main line); Building Division direct 970-728-1392; Inspection Request Line 970-369-8251, email: Contact form only at time of this review (townofmountainvillage.com/business/building/building-division/); no single published department inbox address found. Office hours: Town Hall and Municipal Building: Monday-Friday 8:00 a.m.-5:00 p.m. Building Division fax: 970-728-4342. Licensed contractor list requests: Tracy Bach, 970-369-8242.. Official information: https://townofmountainvillage.com/business/building/building-division/.

Mountain Village, Colorado has adopted: 2024 International Building Code (IBC) — current per the Town's live Building Division 'Codes & Guides' listing; 2024 International Residential Code (IRC) — current per the same live listing; 2024 International Existing Building Code (IEBC); 2024 International Mechanical Code (IMC); 2024 International Fuel Gas Code (IFGC); 2024 International Fire Code (IFC) — enforced by the Telluride Fire Protection District (TFPD) per Chapter 17.7.19 of the Building Regulations; 2023 National Electrical Code (NEC/NFPA 70), as adopted by the State of Colorado; 2021 International Energy Conservation Code (IECC), plus the Town's own 'Local Energy Saving Measures' (HERS ratings, Smart Building Program/REMP) layered on top per Chapter 17.7.12; International Plumbing Code (IPC), as adopted by the State of Colorado — 2024 edition per the live Codes & Guides listing; Prior code cycle (superseded, retained for reference only): 2018-edition IBC/IRC/IEBC/IMC/IFGC/IPC/IPMC and 2020 NEC, per the Town's posted 'CHAPTER 17.7 BUILDING REGULATIONS' PDF (townofmountainvillage.com/site/assets/files/40818/building_regulations.pdf) — the PDF carries the full section-by-section amendment text (climatic design table, contractor licensing exam list, IECC HERS/REMP mechanics, plumbing/mechanical/electrical amendments). The Town's live Building Division page confirms Ordinance 2025-05 updated Chapter 17.7 to the 2024 ICC code cycle; the current amendment text is carried on the mountainvillage.municipal.codes host, but that ordinance's specific amendment-section text is not reflected here. Administrative structure (Building Division under Planning and Development Services, permit expiration/fee/inspection provisions, contractor licensing structure) is corroborated by the live page and treated as current; the code-specific numeric amendments below (snow load, wind speed, etc.) are sourced from the 2018-cycle PDF and flagged as potentially superseded rather than presented as current 2024-cycle figures.; All codes locally amended via Mountain Village Municipal Code Chapter 17.7 (Building Regulations, within the Community Development Code/CDC).. Local amendments apply — see the Mountain Village overview page for the full list.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-08-02.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Mountain Village building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Mountain Village's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Mountain Village yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when Mountain Village lands. Privacy.