Electric Vehicle (EV) Charging Station / EVSE Permit — Victor, Colorado · Requirements sheet
Verified 2026-07-20 · Source: https://www.cityofvictor.com/media/26
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Electric Vehicle (EV) Charging Station / EVSE Permit in Victor, Colorado
The City of Victor has no distinct EV charger/EVSE permit application or fee line. An EV charging station installation is permitted as ordinary electrical work through the City's own local Electrical Permit program (Victor runs its own electrical permitting/inspection via its contracted Building Official, ShumsCoda, rather than deferring to the Colorado State Electrical Board), billed under the 'Nonresidential Buildings and Residential Alteration or Addition' Electric Permit fee table -- the same valuation-based schedule the city's own fee schedule uses for the electrical-interconnection portion of its solar permit, since the Fee & Fine Schedule does not name EV chargers as their own line item. Governed by the 2014 NEC as locally adopted, which includes Article 625 (Electric Vehicle Power Transfer System) provisions. Victor's population (roughly 400) is far below the 10,000-person threshold that triggers 'covered municipality' status under Colorado's HB24-1173 (Electric Vehicle Charging System Permits Act, effective 8/7/2024), so that statute's mandatory model-code/objective-standards adoption and 3-business-day decision-notification requirement do not apply here.
Verified 2026-07-20 · Source
When you need this permit
- No standalone EV charger/EVSE permit application exists; apply for the City's standard Electrical Permit (Building Permit Application, Electrical scope), submitted in person at Victor City Hall
- City Building Inspectors perform contemporaneous, on-site license verification of electrical workers per City policy, the same requirement applied to all other electrical work
- Fee billed under the 'Nonresidential Buildings and Residential Alteration or Addition' Electric Permit fee table (valuation-based), the same category the city's fee schedule uses for the electrical portion of solar installations, since EV chargers are not enclosed-living-area new-construction wiring
- Governed by the 2014 NEC as adopted by the City of Victor, which includes Article 625 (Electric Vehicle Power Transfer System) requirements for EVSE branch circuits and disconnects
- Victor's population is far below the 10,000-person threshold for 'covered municipality' status under Colorado HB24-1173, so the Act's mandatory EV-permitting-standards adoption and 3-business-day decision timeline do not apply as a legal requirement here
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
EVSE circuit wiring and panel/disconnect installed before concealment
- 2
Final Inspection
Charging equipment installed, system energized and verified per 2014 NEC Article 625
See the full Victor inspection guide — scheduling & re-inspection fees →
Tips
- Victor runs its OWN electrical permitting/inspection program — do not assume the Colorado State Electrical Board (DORA) issues permits for EV charger work in Victor city limits; apply through the City Building Department the same way you would for the electrical portion of a solar installation.
- There is no dedicated EV charger fee category — expect the electrical permit to be billed under the same 'Nonresidential Buildings and Residential Alteration or Addition' valuation-based table used for solar and other non-new-construction electrical work.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Victor building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Victor
Electric Vehicle (EV) Charging Station / EVSE Permit in other cities
Compare electric vehicle (ev) charging station / evse permit fees across Colorado →
Look up this fee in a different city →