Roofing Permit (Re-Roof) in Frederick, Colorado

Required for re-roofing work in the Town of Frederick. Governed by the 2024 IRC/IBC as locally adopted. The Town's own submittal/fee pages do not carry a distinct, itemized re-roof fee or checklist separate from the general Building Permit process; billed under the general valuation-based schedule absent a listed flat fee.

Verified 2026-07-23 · Source

When you need this permit

  • Governed by the 2024 IRC/IBC as locally adopted by the Town of Frederick
  • Roofing material and installation must comply with applicable wind (115 mph) and snow load (30 psf) design criteria
  • Contractor must hold a current Town of Frederick contractor license Contractor

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Building Permit Fee (valuation-based; no distinct flat re-roof fee found in the 2026 Fee Schedule)
The Town's Fee Schedule does not list a separate flat re-roof line item; Show full citationThe Town's Fee Schedule does not list a separate flat re-roof line item; billed under the general Building Permit Fee valuation table. Re-confirmed 2026-07-23 against a visual read of the live Fee Schedule PDF's full flat-fee table (page 8) — re-roof is not among the 16 listed flat/hourly items (AC/Furnace, water heater, service upgrade, backflow, demolition, foundation-only, TCO, temp electrical, temp/accessory structure, block & tie, stock plan review x2, solar x2, administrative fee).
$35.00 minimum, scaling per the valuation tiers in the 2026 Fee Schedule
Plan Review FeeTown of Frederick Fee Schedule, effective January 1, 2026, Chapter 18 - Building Permit Fees, Plan Review Fee line
65% of Permit Fee
Re-inspection Fee
Town of Frederick Fee Schedule, January 01, 2026, Chapter 18 — Building Permit Flat and/or Hourly Fees — Re-inspection Fees at $100.00. Show full citationTown of Frederick Fee Schedule, January 01, 2026, Chapter 18 — Building Permit Flat and/or Hourly Fees — Re-inspection Fees at $100.00. The $120.00 previously shown as the top of a range is the next row, Inspections and/or Code Enforcement or Investigations for which no fee is specified.
$100.00 per re-inspection

Review timeline

Plan review
Not published — contact the department

How long did your Roofing Permit (Re-Roof) permit actually take in Frederick?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Inspection (roof)

    Completed roof — material, underlayment, and flashing compliance verified

See the full Frederick inspection guide — scheduling & re-inspection fees →

Tips

  • Frederick does not publish a distinct re-roof fee or checklist separate from its general Building Permit process — confirm with the Building Department (720-382-5516) whether your specific re-roof scope is billed as a flat item or under the valuation-based schedule before applying.
  • Checked the Town's public OpenGov permitting API (frederickco.portal.opengov.com/v2/frederickco/record_types) and the full Wayback Machine capture history of frederickco.gov since 2016 — neither shows a separate re-roof record type or page ever having existed. Frederick's re-roof handling is confirmed to be genuinely unified with the general Building Permit process rather than an undiscovered gap.

Frequently asked questions

Frederick requires a roofing permit (re-roof) for: Governed by the 2024 IRC/IBC as locally adopted by the Town of Frederick; Roofing material and installation must comply with applicable wind (115 mph) and snow load (30 psf) design criteria; Contractor must hold a current Town of Frederick contractor license. If your project isn't listed, confirm with Town of Frederick Building Department at 720-382-5516 (general questions); 720-382-5620 (inspection request line) before starting work.

In Frederick, the published Building Permit Fee (valuation-based; no distinct flat re-roof fee found in the 2026 Fee Schedule) is: $35.00 minimum, scaling per the valuation tiers in the 2026 Fee Schedule. Additional published fees: Plan Review Fee — 65% of Permit Fee; Re-inspection Fee — $100.00 per re-inspection. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Frederick does not publish a plan-review timeline for this permit. Contact Town of Frederick Building Department at 720-382-5516 (general questions); 720-382-5620 (inspection request line) for current turnaround.

You'll need: Permit Application — General (Re-Roof scope). See the required-documents checklist on this page for details on each.

Frederick requires 1 inspection(s) for a roofing permit (re-roof), in order: Final Inspection (roof). Schedule each through Town of Frederick Building Department (720-382-5516 (general questions); 720-382-5620 (inspection request line)).

Apply through Town of Frederick Building Department at 401 Locust Street, Frederick, CO 80530 (mailing: PO Box 435, Frederick, CO 80530). Phone: 720-382-5516 (general questions); 720-382-5620 (inspection request line), email: building@frederickco.gov. Office hours: Monday-Friday, 7:30 a.m. - 4:30 p.m. Chief Building Official: mtheile@FrederickCO.gov.. Official information: https://www.frederickco.gov/416/Building-Department.

Frederick, Colorado has adopted: 2024 International Building Code (IBC) — Town of Frederick Building Codes page; 2024 International Residential Code (IRC); 2024 International Fire Code (IFC); 2024 International Mechanical Code (IMC); 2024 International Fuel Gas Code (IFGC); 2024 International Plumbing Code (IPC); 2024 International Existing Building Code (IEBC); 2024 International Energy Conservation Code (IECC); 2024 International Swimming Pool and Spa Code (ISPSC); 2024 International Property Maintenance Code (IPMC); 2023 National Electrical Code (NEC); 2025 Colorado Wildfire Resiliency Code (as published by the State of Colorado Division of Fire Prevention and Control); Colorado Model Electric Ready and Solar Ready Code; All codes adopted with local amendments per Frederick Municipal Code, Chapter 18 (Buildings and Building Regulations) — Town of Frederick Building Codes page (frederickco.gov/141/Building-Codes); The Town's Residential/New Construction Building Permit Checklist still directs energy-code compliance to the 2021 IECC (REScheck, an energy rating report, or prescriptive HERS documentation), while the Town's Building Codes page lists the 2024 IECC as adopted. Treat the Building Codes page list — 2024 IBC, IRC, IECC, IMC, IPC, IFGC, IEBC, ISPSC, IPMC plus the 2023 NEC — as the governing adopted-code list, and confirm the current edition with the Building Department at 720-382-5516 before finalizing a code analysis, since the checklist has not been updated to match.. Local amendments apply — see the Frederick overview page for the full list.

The Town's published materials do not show a distinct re-roof-specific application or fee line separate from the General Permit application and the general valuation-based Building Permit Fee schedule; confirm current practice directly with the Building Department.

Sources & verification

Verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Frederick building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Property Access

Frederick's permit history is searchable by address

23,540 permits on record for Frederick — searchable by street address, with permit type, status, issued date and valuation where the city publishes them.

94% of Frederick's records carry a street address to match against, so a search that finds nothing here means we could not look — not that the property is clear.

Start your 7-day free trial7 days free for new customers, then $79/mo · the guide above stays free