Required for new single-family and townhome construction in the Town of Frederick. Reviewed under the 2024 IRC/IBC as locally adopted, the Town's structural design criteria (115 mph wind, 30 psf ground snow load, 36-inch footing depth, Seismic Design Category B), and energy-code compliance. Issued by the Town of Frederick Building Department; inspections performed by Town staff or CAA (the Town's private inspection partner).

Verified 2026-07-06 · Source

When you need this permit

  • Plans must comply with the 2024 IRC/IBC as locally adopted and Frederick's structural design criteria: 115 mph wind speed, 30 psf ground snow load, 36-inch minimum footing depth, Seismic Design Category B
  • Soils report from a Colorado-licensed engineer
  • Foundation plans stamped by a Colorado-licensed engineer (footings, reinforcing, anchor bolts)
  • Structural framing plans (foundation, floor, roof)
  • Architectural/floor plans with dimensions, ceiling heights, window/door locations; building elevations for all four sides identifying materials and roof pitches
  • NEC-compliant electrical plans; mechanical plans with equipment/duct locations and Manual J/D/S HVAC compliance documentation
  • Stamped plot/site plan showing property lines, easements, setbacks, lot coverage, utilities, and grading (minimum 5% downward slope away from the foundation within the first 10 feet); erosion control measures (silt fencing, vehicle tracking pads)
  • Energy code compliance documentation (REScheck, energy rating report, or prescriptive HERS documentation per the Town's checklist)
  • A large-format (22x34 or 24x36 inch) copy of the approved plan set must be kept on the job site at all times until final inspections pass
  • Electrician and plumber performing work must be listed with active, Town-verified Colorado DORA license numbers per the Contemporaneous Review Guidelines
  • Water Dedication documentation required for projects located east of I-25

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — valuation $1.00 to $500Town of Frederick Fee Schedule, effective January 1, 2026
$35.00
Building Permit Fee — valuation $501 to $2,000
$35.00 for the first $500, plus $3.72 for each additional $100 or fraction thereof, up to and including $2,000
Building Permit Fee — valuation $2,001 to $25,000
$90.80 for the first $2,000, plus $17.08 for each additional $1,000 or fraction thereof, up to and including $25,000
Building Permit Fee — valuation $25,001 to $50,000
$483.64 for the first $25,000, plus $12.32 for each additional $1,000 or fraction thereof, up to and including $50,000
Building Permit Fee — valuation $50,001 to $100,000
$791.64 for the first $50,000, plus $8.54 for each additional $1,000 or fraction thereof, up to and including $100,000
Building Permit Fee — valuation $100,001 to $500,000
$1,218.64 for the first $100,000, plus $6.83 for each additional $1,000 or fraction thereof, up to and including $500,000
Building Permit Fee — valuation $500,001 to $1,000,000
$3,950.64 for the first $500,000, plus $5.80 for each additional $1,000 or fraction thereof, up to and including $1,000,000
Building Permit Fee — valuation $1,000,001 and up
$6,850.64 for the first $1,000,000, plus $4.45 for each additional $1,000 or fraction thereof
Plan Review Fee
65% of Building Permit Fee
Permit fee if work commences before permit issuance
Subject to double the calculated Building Permit fee
Administrative Fee (based on project valuation)
$20 (under $10,000); $100 ($10,001-$80,000); $150 ($80,000-$150,000); $200 (over $150,000)
Additional Plan Review (changes/additions/revisions to approved plans)
$200.00 per item
Inspections outside normal business hours
$120.00/hour (2-hour minimum)
Re-inspection Fee
$100.00-$120.00 per re-inspection

Review timeline

Plan review
Not published — contact the department

How long did your Residential Building Permit (New Construction) permit actually take in Frederick?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation

    Before concrete pour, per 36-inch minimum footing depth

  2. 2

    Framing

    Structural framing complete before cover

  3. 3

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment; electrician/plumber identity may be verified at inspector's discretion

  4. 4

    Final Inspection

    All work complete per approved plans and applicable codes

See the full Frederick inspection guide — scheduling & re-inspection fees →

Tips

  • Frederick's structural design criteria (115 mph wind, 30 psf ground snow load, 36-inch footing depth, Seismic Design Category B) are lighter than mountain-corridor jurisdictions like Vail but still must be confirmed with your engineer rather than assumed from a generic Front Range template.
  • A large-format (22x34 or 24x36 inch) copy of the approved plan set must physically remain on the job site at all times until final inspections pass — keep this on-site, not just in a digital file, to avoid a failed inspection on a technicality.
  • The Town's own checklist still references '2021 IECC Energy Code' compliance paths even though the live Building Codes page lists 2024 IECC as adopted — both meet or exceed Colorado's HB22-1362 energy floor, but confirm with the Building Department which edition governs your specific application if the timing is ambiguous.

Frequently asked questions

Frederick requires a residential building permit (new construction) for: Plans must comply with the 2024 IRC/IBC as locally adopted and Frederick's structural design criteria: 115 mph wind speed, 30 psf ground snow load, 36-inch minimum footing depth, Seismic Design Category B; Soils report from a Colorado-licensed engineer; Foundation plans stamped by a Colorado-licensed engineer (footings, reinforcing, anchor bolts); Structural framing plans (foundation, floor, roof); Architectural/floor plans with dimensions, ceiling heights, window/door locations; building elevations for all four sides identifying materials and roof pitches; NEC-compliant electrical plans; mechanical plans with equipment/duct locations and Manual J/D/S HVAC compliance documentation; Stamped plot/site plan showing property lines, easements, setbacks, lot coverage, utilities, and grading (minimum 5% downward slope away from the foundation within the first 10 feet); erosion control measures (silt fencing, vehicle tracking pads); Energy code compliance documentation (REScheck, energy rating report, or prescriptive HERS documentation per the Town's checklist); A large-format (22x34 or 24x36 inch) copy of the approved plan set must be kept on the job site at all times until final inspections pass; Electrician and plumber performing work must be listed with active, Town-verified Colorado DORA license numbers per the Contemporaneous Review Guidelines; Water Dedication documentation required for projects located east of I-25. If your project isn't listed, confirm with Town of Frederick Building Department at 720-382-5516 (general questions); 720-382-5620 (inspection request line) before starting work.

In Frederick, the published Building Permit Fee — valuation $1.00 to $500 is: $35.00. Additional published fees: Building Permit Fee — valuation $501 to $2,000 — $35.00 for the first $500, plus $3.72 for each additional $100 or fraction thereof, up to and including $2,000; Building Permit Fee — valuation $2,001 to $25,000 — $90.80 for the first $2,000, plus $17.08 for each additional $1,000 or fraction thereof, up to and including $25,000; Building Permit Fee — valuation $25,001 to $50,000 — $483.64 for the first $25,000, plus $12.32 for each additional $1,000 or fraction thereof, up to and including $50,000; Building Permit Fee — valuation $50,001 to $100,000 — $791.64 for the first $50,000, plus $8.54 for each additional $1,000 or fraction thereof, up to and including $100,000; Building Permit Fee — valuation $100,001 to $500,000 — $1,218.64 for the first $100,000, plus $6.83 for each additional $1,000 or fraction thereof, up to and including $500,000; Building Permit Fee — valuation $500,001 to $1,000,000 — $3,950.64 for the first $500,000, plus $5.80 for each additional $1,000 or fraction thereof, up to and including $1,000,000; Building Permit Fee — valuation $1,000,001 and up — $6,850.64 for the first $1,000,000, plus $4.45 for each additional $1,000 or fraction thereof; Plan Review Fee — 65% of Building Permit Fee; Permit fee if work commences before permit issuance — Subject to double the calculated Building Permit fee; Administrative Fee (based on project valuation) — $20 (under $10,000); $100 ($10,001-$80,000); $150 ($80,000-$150,000); $200 (over $150,000); Additional Plan Review (changes/additions/revisions to approved plans) — $200.00 per item; Inspections outside normal business hours — $120.00/hour (2-hour minimum); Re-inspection Fee — $100.00-$120.00 per re-inspection. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

The Town does not publish a specific numeric turnaround time for residential building permit review on its Building Department page, Submittal Requirements page, checklist, or fee schedule.

You'll need: Permit Application — New Residential; Residential/New Construction Building Permit Checklist submittal package. See the required-documents checklist on this page for details on each.

Frederick requires 4 inspection(s) for a residential building permit (new construction), in order: Foundation, Framing, Rough Electrical / Plumbing / Mechanical, Final Inspection. Schedule each through Town of Frederick Building Department (720-382-5516 (general questions); 720-382-5620 (inspection request line)).

Apply through Town of Frederick Building Department at 401 Locust Street, Frederick, CO 80530 (mailing: PO Box 435, Frederick, CO 80530). Phone: 720-382-5516 (general questions); 720-382-5620 (inspection request line), email: building@frederickco.gov. Office hours: Monday-Friday, 7:30 a.m. - 4:30 p.m. Chief Building Official: mtheile@FrederickCO.gov.. Official information: https://www.frederickco.gov/416/Building-Department.

Frederick, Colorado has adopted: 2024 International Building Code (IBC) — Town of Frederick Building Codes page; 2024 International Residential Code (IRC); 2024 International Fire Code (IFC); 2024 International Mechanical Code (IMC); 2024 International Fuel Gas Code (IFGC); 2024 International Plumbing Code (IPC); 2024 International Existing Building Code (IEBC); 2024 International Energy Conservation Code (IECC); 2024 International Swimming Pool and Spa Code (ISPSC); 2024 International Property Maintenance Code (IPMC); 2023 National Electrical Code (NEC); 2025 Colorado Wildfire Resiliency Code (as published by the State of Colorado Division of Fire Prevention and Control); Colorado Model Electric Ready and Solar Ready Code; All codes adopted with local amendments per Frederick Municipal Code, Chapter 18 (Buildings and Building Regulations) — Town of Frederick Building Codes page (frederickco.gov/141/Building-Codes); Note on code-cycle currency: the Town's own Residential/New Construction Building Permit Checklist (a submittal-requirements document, not the code-adoption page) still directs energy-code compliance via '2021 IECC Energy Code' (REScheck, energy rating report, or prescriptive HERS documentation), even though the live Building Codes page lists 2024 IECC as currently adopted — this is the same pattern seen in other Colorado jurisdictions in this corpus where a static submittal PDF lags the actively-maintained code-adoption webpage. The 2024 IBC/IRC/IECC/IMC/IPC/IFGC/IEBC/ISPSC/IPMC + 2023 NEC list from the Building Codes page is treated as the current, governing adopted-code list for this file; confirm current code edition directly with the Building Department (720-382-5516) before finalizing a code analysis for any specific project, since the checklist PDF may not yet be updated to match the webpage.. Local amendments apply — see the Frederick overview page for the full list.

The Town of Frederick Building Department issues its own building, electrical, mechanical, and plumbing permits for all work within town limits. Inspections are performed by Town staff or by CAA (Code Administration & Associates), described by the Town as its private building inspection partner.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Frederick building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.