Solar Photovoltaic (PV) Permit in Hayden, Idaho

Required for installation of rooftop or ground-mount solar photovoltaic systems within Hayden city limits. Requires a City Building Permit (structural/racking, valuation-based per the City's Fee Schedule) plus a State of Idaho electrical permit (wiring/interconnection) issued by the Division of Occupational and Professional Licenses (DOPL, dbs.idaho.gov) -- the City's own Residential Permit Application Instructions expressly direct applicants to the state for electrical permits and require state permits to be final-approved before a City Final Inspection can be scheduled. The state's Contractor Electrical Permit Worksheet has a dedicated checkbox and valuation-based fee formula for 'Solar, Renewable Energy, power generation, power production, or energy storage systems.'

Verified 2026-07-20 · Source

When you need this permit

  • City Building Permit Application submitted via the BS&A Online portal for the structural/racking scope
  • Electrical wiring/interconnection scope requires a State of Idaho DOPL Contractor Electrical Permit (or Homeowner Electrical Permit if self-installed), applied for online at dbs.idaho.gov -- NOT through the City's BS&A Online portal, consistent with this corpus's existing electrical-permit entry for Hayden
  • State electrical permits must be final-approved before the City of Hayden will schedule a City Final Inspection on the associated building permit
  • On the DOPL Electrical Permit Worksheet, check the 'Solar, Renewable Energy, power generation, power production, or energy storage systems' box under 'Other Installations including Commercial/Industrial/Solar/Renewable Energy' and enter the total cost of the electrical system
  • Renewable energy installations require a plan check prior to final inspection, per the DOPL Electrical Permit Worksheet

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

City Building Permit Fee — total valuation $2,001 to $25,000 (typical residential solar range)City of Hayden Fee Schedule, Exhibit A, effective 9/1/2023 -- no dedicated solar/photovoltaic building fee line exists; billed under this general valuation table for the structural/racking scope
$71.35 for the first $2,000 plus $14.00 for each additional $1,000 or fraction thereof
City Plan Check Fee (residential, due prior to plan review, non-refundable)City of Hayden Fee Schedule, Exhibit A
10% of the Building Permit Fee, $25.00 minimum
State DOPL Electrical Permit — Solar/Renewable Energy, up to $10,000 system costIdaho DOPL Contractor Electrical Permit Worksheet (Fee Schedule), Rev. 8/17/2022 -- a state fee, not collected by the City of Hayden
(total system cost x 0.02) + $60
State DOPL Electrical Permit — Solar/Renewable Energy, $10,001-$100,000 system costIdaho DOPL Contractor Electrical Permit Worksheet, Rev. 8/17/2022
((system cost - $10,000) x 0.01) + $260
State DOPL Electrical Permit — Solar/Renewable Energy, over $100,001 system costIdaho DOPL Contractor Electrical Permit Worksheet, Rev. 8/17/2022; renewable energy installations require a plan check prior to final inspection
((system cost - $100,000) x 0.005) + $1,160

Review timeline

Plan reviewTypical estimate — confirm current times with the Hayden building department
~22–22 business days

How long did your Solar Photovoltaic (PV) Permit permit actually take in Hayden?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    State Electrical Inspection

    Performed by an Idaho DOPL inspector; wiring, disconnect placement, and interconnection point verified before energizing; renewable energy installations require a plan check prior to this final inspection

  2. 2

    City Final Inspection (Building)

    Racking/roof-penetration attachment and structural compliance verified by the City -- cannot be scheduled until the state electrical permit is final-approved

See the full Hayden inspection guide — scheduling & re-inspection fees →

Tips

  • Hayden splits solar permitting across two agencies: the City issues the structural Building Permit via BS&A Online, but the State of Idaho (DOPL, dbs.idaho.gov) issues the electrical permit on its own separate portal -- do not try to apply for the electrical permit through the City's system.
  • The City will not schedule its own Final Inspection until the state electrical permit is final-approved, so sequence your state electrical approval before requesting the City's final sign-off.
  • On the state electrical permit worksheet, be sure to check the dedicated 'Solar, Renewable Energy, power generation, power production, or energy storage systems' box -- this routes the project to the correct valuation-based fee formula rather than a generic electrical fee category.
  • Re-chase pass (2026-07-20): downloaded and read the current State of Idaho DOPL Application for Contractor Permit / Electrical Permit Worksheet (Fee Schedule) PDF directly from dopl.idaho.gov — live today, and its 'OTHER INSTALLATIONS including COMMERCIAL/INDUSTRIAL/SOLAR/RENEWABLE ENERGY' section matches this entry's tiered formula verbatim: (system cost x 0.02) + $60 up to $10,000; ((system cost - $10,000) x 0.01) + $260 for $10,001-$100,000; ((system cost - $100,000) x 0.005) + $1,160 over $100,001. This DOPL fee schedule is the explicit, statewide, currently-in-force state mechanism for the PV/renewable-energy electrical scope in any Idaho city (including this one) that has not independently certified its own electrical inspection program.

Frequently asked questions

Hayden requires a solar photovoltaic (pv) permit for: City Building Permit Application submitted via the BS&A Online portal for the structural/racking scope; Electrical wiring/interconnection scope requires a State of Idaho DOPL Contractor Electrical Permit (or Homeowner Electrical Permit if self-installed), applied for online at dbs.idaho.gov -- NOT through the City's BS&A Online portal, consistent with this corpus's existing electrical-permit entry for Hayden; State electrical permits must be final-approved before the City of Hayden will schedule a City Final Inspection on the associated building permit; On the DOPL Electrical Permit Worksheet, check the 'Solar, Renewable Energy, power generation, power production, or energy storage systems' box under 'Other Installations including Commercial/Industrial/Solar/Renewable Energy' and enter the total cost of the electrical system; Renewable energy installations require a plan check prior to final inspection, per the DOPL Electrical Permit Worksheet. If your project isn't listed, confirm with City of Hayden Community Development Department, Building Division at (208) 209-2025 (Building Division); (208) 209-2022 also published on department handouts before starting work.

Based on the total cost of the electrical system, per DOPL's Contractor Electrical Permit Worksheet: (system cost x 0.02) + $60 for systems up to $10,000; ((system cost - $10,000) x 0.01) + $260 for $10,001-$100,000. Applicants must check the dedicated Solar/Renewable Energy box on the worksheet.

Plan review for a solar photovoltaic (pv) permit in Hayden typically runs 22–22 business days. This is an estimate, not a published figure — confirm current review times with City of Hayden Community Development Department, Building Division at (208) 209-2025 (Building Division); (208) 209-2022 also published on department handouts.

You'll need: City of Hayden Residential Permit Application; Idaho DOPL Contractor (or Homeowner) Electrical Permit Application. See the required-documents checklist on this page for details on each.

Hayden requires 2 inspection(s) for a solar photovoltaic (pv) permit, in order: State Electrical Inspection, City Final Inspection (Building). Schedule each through City of Hayden Community Development Department, Building Division ((208) 209-2025 (Building Division); (208) 209-2022 also published on department handouts).

Apply through City of Hayden Community Development Department, Building Division at 8930 N Government Way, Hayden, ID 83835. Phone: (208) 209-2025 (Building Division); (208) 209-2022 also published on department handouts, email: permits@cityofhaydenid.us. Office hours: Not published on the Building Department page or in the Residential Permit Application Instructions as a discrete office-hours line; standard City Hall hours apply. Applications are submitted electronically through the BS&A Online portal (bsaonline.com/?uid=2689), not primarily in person.. Official information: https://www.haydenid.gov/departments/building/index.php.

Hayden, Idaho has adopted: Idaho has a mandatory statewide baseline building code under the Idaho Building Code Act (Idaho Code Title 39, Chapter 41). The City of Hayden is an INCORPORATED CITY within Kootenai County with its own separate Building Department, entirely distinct from Kootenai County Community Development's Building Division (which administers only the unincorporated area of the county). Kootenai County's own adopted-codes documentation explicitly lists Hayden among the incorporated cities in the county with their own building departments and codes. Source: Kootenai County Code Title 7, Chapter 1, Section 7.1.103 (Applicability), https://codelibrary.amlegal.com/codes/kootenaicountyid/latest/kootenaicounty_id/0-0-0-2406; City of Hayden adopted codes, in effect as of January 1, 2021 (City Code, Title 9, Building Regulations): 2018 International Building Code (IBC), 2018 International Existing Building Code (IEBC), 2018 International Residential Code (IRC), 2018 International Mechanical Code (IMC), 2018 International Fuel/Gas Code (IFGC), 2018 International Energy Conservation Code (IECC), 2018 International Fire Code (IFC), 2015 International Swimming Pool and Spa Code (ISPSC), 2009 ICC A117.1 Accessible and Usable Buildings and Facilities, and the Idaho Manufactured Home Installation Standard (State of Idaho Division of Building Safety, 1-2018). Source: City of Hayden Building Department Design Criteria handout, https://cms2.revize.com/revize/hayden/document_center/Government/CED/Building/Frequently%20Asked%20Questions/BuildingDepartmentDesignCriteria.pdf; Plumbing, sewer, and electrical permitting and inspection within Hayden city limits are handled by the STATE of Idaho (Division of Building Safety / DOPL), NOT the City of Hayden — the City's own Residential Permit Application Instructions expressly direct applicants to 'Contact the State of Idaho, Division of Building Safety at (800)955-3044 or apply online https://dbs.idaho.gov/' for plumbing, sewer, and electrical permits/inspections, and state that 'State Permits must be final approved prior to scheduling a City Final Inspection.' This differs from neighboring Coeur d'Alene and Post Falls, which each issue their own electrical and plumbing permits directly. Source: City of Hayden Residential Permit Application Instructions, https://cms2.revize.com/revize/hayden/document_center/Government/CED/Building/Residential%20Permits/ResidentialPermitApplicationPacket.pdf; Mechanical/HVAC permits ARE issued directly by the City of Hayden Building Department (not the State), using the City's own itemized Residential Mechanical Worksheet and fee schedule. Source: City of Hayden Residential Mechanical Worksheet (same packet) and City of Hayden Fee Schedule (Exhibit A, eff. 9/1/2023); Building permit applications and construction documents are submitted electronically as PDFs through the BS&A Online portal (bsaonline.com/?uid=2689); the City does not describe an in-person plan drop-off as the primary application method. Source: City of Hayden Residential Permit Application Instructions. Local amendments apply — see the Hayden overview page for the full list.

The State of Idaho Division of Building Safety / DOPL (dbs.idaho.gov), not the City of Hayden. The City's own Residential Permit Application Instructions expressly direct applicants to the state for electrical permits, and require the state permit to be final-approved before the City will schedule its own Final Inspection.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Hayden building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.