Residential Building Permit (New Single-Family Dwelling / Addition) in Moscow, Idaho

Required for new one- and two-family dwelling construction and additions within Moscow city limits, administered by the City of Moscow Building Safety Division. Building Permit Fees are based on ICC Building Valuations (February issue of the Building Safety Journal) on a bracketed fee table, with a separate Plan Review Fee for projects valued over $10,000.

Verified 2026-07-04 · Source

When you need this permit

  • Site/plot plan required with all building permit applications (except simple re-roof permits), showing property lines, all structures, street, driveway, sidewalk, and location of proposed work
  • Floor plans showing all door/window sizes and locations, room dimensions and uses
  • For new dwellings/additions: foundation plan, floor framing plan, roof framing plan, electrical plan (meter, switch, outlet, and light locations), and two sets of wet-stamped structural/truss calculations if required
  • Two complete paper sets of plans (or one electronic set, followed by two stamped paper sets after electronic approval) submitted to the Community Development Office
  • Contractor must be registered with the State of Idaho; name and registration number required on the application
  • Plan Review Fee (65% of Building Permit Fee, or 40% for duplicate plans) applies to projects over $10,000 in valuation; a $500 Plan Review Deposit is credited toward this fee

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Total Valuation $1.00 to $2,000 (Fee Amount for First $500)Plus $3.50 for each additional $100 or fraction thereof to and including $2,000. City of Moscow FY2026 Fee Schedule, Schedule C, page 5
$27.50
Total Valuation $2,001 to $25,000 (Fee Amount for First $2,000)Plus $14.50 for each additional $1,000 or fraction thereof, to and including $25,000. City of Moscow FY2026 Fee Schedule
$79.50
Total Valuation $25,001 to $50,000 (Fee Amount for First $25,000)Plus $10.50 for each additional $1,000 or fraction thereof, to and including $50,000. City of Moscow FY2026 Fee Schedule
$413.00
Total Valuation $50,001 to $100,000 (Fee Amount for First $50,000)Plus $7.50 for each additional $1,000 or fraction thereof to and including $100,000. City of Moscow FY2026 Fee Schedule
$675.50
Total Valuation $100,001 and up (Fee Amount for First $100,000)Plus $6.00 for each additional $1,000 or fraction thereof. City of Moscow FY2026 Fee Schedule
$1,050.50
Permit Issuance FeeCharged with all permits except flat-fee, Commercial, and Institutional permits. City of Moscow FY2026 Fee Schedule, page 6
$32.75
Decks (per square foot addition to base ICC valuation)Per square foot. City of Moscow FY2026 Fee Schedule, page 5
$15.75
Plan Review Fee (projects over $10,000 in valuation)City of Moscow FY2026 Fee Schedule, page 6
65% of the Building Permit Fee (40% for duplicate plans)
Plan Review DepositCredited toward the Plan Review Fee. City of Moscow FY2026 Fee Schedule, page 6
$500.00
No Permit (failure to obtain permit before commencing work)City of Moscow FY2026 Fee Schedule, page 6
Fee equal to the Building Permit Fee

Review timeline

Plan reviewMoscow’s published plan-review target
10–10 business days

How long did your Residential Building Permit (New Single-Family Dwelling / Addition) permit actually take in Moscow?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation

    Made when trenches are excavated, forms set, and all steel reinforcing, hold-down hardware and/or anchor bolts in place

  2. 2

    Concrete Slab or Under-Floor

    Made after all in-slab or under-floor equipment, piping, and conduit are in place, but before concrete is placed or floor sheathing installed

  3. 3

    Roof Sheathing Nailing

    Made when roof sheathing is installed and entirely nailed off

  4. 4

    Framing or Rough

    Made after all framing, fire-blocking, and bracing are in place, and all pipes, chimneys, vents, roof covering, and rough electrical/plumbing/heating are complete and inspected

  5. 5

    Insulation

    Made when all insulation is installed and all shell openings/gaps are caulked or sealed

  6. 6

    Lath and/or Gypsum Board

    Made after all lath/gypsum board is in place but before plastering is applied or joints/fasteners are taped and finished

  7. 7

    Final

    Made after finishing grading, when the building is complete and ready for occupancy, and all plumbing/electrical fixtures and appliances are installed; results in a Certificate of Occupancy

See the full Moscow inspection guide — scheduling & re-inspection fees →

Tips

  • New Single-Family Dwelling plan review is <10 business days for first review and <5 business days for subsequent reviews, per the City's published Submittal for Plan Review timeline table (Homeowner's Guide, page 9).
  • Inspection requests should be made the day prior to the requested inspection; call (208) 883-7022 or request in person at the Building Division counter.
  • Permits automatically expire if reasonable work is not accomplished during any 180-day period; renewal requires additional fees.
  • Special Inspectors (hired by the owner) may be required for specialized construction methods such as welding, epoxy, or high-strength concrete; reports must be given to the City inspector.

Frequently asked questions

Moscow requires a residential building permit (new single-family dwelling / addition) for: Site/plot plan required with all building permit applications (except simple re-roof permits), showing property lines, all structures, street, driveway, sidewalk, and location of proposed work; Floor plans showing all door/window sizes and locations, room dimensions and uses; For new dwellings/additions: foundation plan, floor framing plan, roof framing plan, electrical plan (meter, switch, outlet, and light locations), and two sets of wet-stamped structural/truss calculations if required; Two complete paper sets of plans (or one electronic set, followed by two stamped paper sets after electronic approval) submitted to the Community Development Office; Contractor must be registered with the State of Idaho; name and registration number required on the application; Plan Review Fee (65% of Building Permit Fee, or 40% for duplicate plans) applies to projects over $10,000 in valuation; a $500 Plan Review Deposit is credited toward this fee. If your project isn't listed, confirm with City of Moscow Building Safety Division (Community Development Department) at (208) 883-7022 before starting work.

In Moscow, the published Total Valuation $1.00 to $2,000 (Fee Amount for First $500) is: $27.50. Additional published fees: Total Valuation $2,001 to $25,000 (Fee Amount for First $2,000) — $79.50; Total Valuation $25,001 to $50,000 (Fee Amount for First $25,000) — $413.00; Total Valuation $50,001 to $100,000 (Fee Amount for First $50,000) — $675.50; Total Valuation $100,001 and up (Fee Amount for First $100,000) — $1,050.50; Permit Issuance Fee — $32.75; Decks (per square foot addition to base ICC valuation) — $15.75; Plan Review Fee (projects over $10,000 in valuation) — 65% of the Building Permit Fee (40% for duplicate plans); Plan Review Deposit — $500.00; No Permit (failure to obtain permit before commencing work) — Fee equal to the Building Permit Fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Per the City of Moscow's published Submittal for Plan Review timeline table, New Single-Family Dwelling review is under 10 business days for the first review and under 5 business days for subsequent reviews. Source: City of Moscow Homeowner's Guide to Construction Permits and Inspections, page 9.

You'll need: Building Permit Application; Site/Plot Plan; Construction Drawings (Floor, Foundation, Framing, Roof, Electrical Plans). See the required-documents checklist on this page for details on each.

Moscow requires 7 inspection(s) for a residential building permit (new single-family dwelling / addition), in order: Foundation, Concrete Slab or Under-Floor, Roof Sheathing Nailing, Framing or Rough, Insulation, Lath and/or Gypsum Board, Final. Schedule each through City of Moscow Building Safety Division (Community Development Department) ((208) 883-7022).

Apply through City of Moscow Building Safety Division (Community Development Department) at 504 S. Washington Street, Moscow, ID 83843. Phone: (208) 883-7022, email: jgoodwin@ci.moscow.id.us. Office hours: Community Development / Building Division, 504 S. Washington Street, Moscow, ID 83843. Building Official: Justin Goodwin, CBO, (208) 883-7014, jgoodwin@ci.moscow.id.us, fax (208) 883-7033. Inspection requests: (208) 883-7022, requests should be made the day prior to the requested inspection; field inspections generally completed 8:00 AM-5:00 PM.. Official information: https://www.ci.moscow.id.us/243/Building-Safety.

Moscow, Idaho has adopted: The City of Moscow independently administers and issues its own building permits within Moscow city limits through its Building Safety Division, part of the Community Development Department — this is a distinct office from the Latah County Planning & Building Department (522 South Adams Street, Moscow, ID), confirmed by the City's own Homeowner's Guide to Construction Permits and Inspections, which lists 'Latah County Planning/Building, (208) 883-7220' as a separate entry in its Useful Telephone Numbers page, distinct from the City's own Community Development line. Source: City of Moscow Homeowner's Guide to Construction Permits and Inspections (Building Division, Justin Goodwin CBO), https://www.ci.moscow.id.us/DocumentCenter/View/21221/City-of-Moscow-Project-Process-PDF, page 19; International Building Code (IBC), locally adopted and administered by the City of Moscow — specific edition year not published on the City's Construction Regulations index page as of 2026-07-04; the page lists 'International Building Code' as Chapter 01 of the City's adopted code chapters without stating the edition. Source: City of Moscow Construction Regulations page, https://www.ci.moscow.id.us/244/Construction-Regulations; International Residential Code (IRC), locally adopted and administered by the City of Moscow (Chapter 16 of the City's adopted code chapters); specific edition year not published on the Construction Regulations index page. Source: City of Moscow Construction Regulations page; Uniform Plumbing Code (UPC), locally adopted (Chapter 02 of the City's adopted code chapters) — notably the Uniform Plumbing Code rather than the International Plumbing Code; specific edition year not published on the index page. Source: City of Moscow Construction Regulations page; National Electrical Code (NEC), locally adopted (Chapter 03 of the City's adopted code chapters); specific edition year not published on the index page. Source: City of Moscow Construction Regulations page; International Fuel Gas Code (IFGC), locally adopted (Chapter 04 of the City's adopted code chapters). Source: City of Moscow Construction Regulations page; International Mechanical Code (IMC), locally adopted (Chapter 10 of the City's adopted code chapters). Source: City of Moscow Construction Regulations page; International Existing Building Code (IEBC), locally adopted (Chapter 12 of the City's adopted code chapters). Source: City of Moscow Construction Regulations page; International Property Maintenance Code (IPMC), locally adopted (Chapter 13 of the City's adopted code chapters). Source: City of Moscow Construction Regulations page; International Energy Conservation Code (IECC), locally adopted (Chapter 15 of the City's adopted code chapters); the City separately publishes an Energy Conservation Plan Review Supplement. Source: City of Moscow Construction Regulations page and Plan Review Information page, https://www.ci.moscow.id.us/256/Plan-Review-Information; Idaho Building Code Act (Idaho Code Title 39, Chapter 41) makes building code standards a matter of statewide concern; local governments that issue building permits and perform code enforcement (such as the City of Moscow) must adopt the International Building Code and Idaho Residential Code as amended by the Idaho Building Code Board through negotiated rulemaking. Source: Idaho Legislature, Idaho Code Title 39 Chapter 41 (39-4116), https://legislature.idaho.gov/statutesrules/idstat/title39/t39ch41/; NOTE ON OMISSION: The City of Moscow's Construction Regulations index page (ci.moscow.id.us/244/Construction-Regulations) lists adopted code chapters by title only (Building, Plumbing, Electrical, Fuel Gas, Mechanical, Existing Building, Property Maintenance, Energy Conservation, Residential) without publishing the specific edition years for any of them on that page; the City's Municipal Code chapter text (which would state exact editions and local amendment sections) was not independently reachable within this research pass. Specific edition years are omitted here rather than assumed to match a neighboring jurisdiction's editions.. Local amendments apply — see the Moscow overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-04.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Moscow building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Compare residential building permit (new single-family dwelling / addition) fees across Idaho

Look up this fee in a different city →

Embed this data card →

Now live

Build your Moscow project checklist

Describe your project once and get every permit, document, and fee it triggers in Moscow — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.

Get started →